AUGUSTA-RICHMOND COUNTY, GEORGIA
CPB# 323-04-203823372
CAPITAL PROJECT BUDGET
POINTE WEST DRAINAGE IMPROVEMENT
CHANGE NUMBER ONE
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County,
Georgia that the following Capital Project Budget is hereby adopted:
Section 1: The project be set up is authorized to CPB# 323-04-203823372.
The funding for this project is needed for Advertising, Right of
Way, Construction and Contingency. We propose address the
drainage issues. The total amount of $600,000 and will be
funded by the Special 1 % Sales Tax, Phase III Recapture Funds.
The additional $200,000 is to fund additional scope for piping
storm water to the County's detention pond.
Section 2: The following revenues are anticipated to be available to the
Consolidated Government to complete the project:
Special 1 % Sales Tax, Phase III Recapture
$ 800,000
$ 800,000
Section 3: The following amounts are appropriated for the project:
Bv Basin
Bv District
Raes Creek
$ 800,000
7th
$800,000
Section 4: Copies of this Capital Project Budget shall be made available to
the Comptroller for direction in carrying out this project.
Adopted this jtj#V day of ~ ,;(oas-, if?
Approved
~u1~~
Original - Commission -Council Office
Copy - Engineering Department
Copy - Finance Department
Copy - Purchasing Department
Jll"'1'
-'
L,
AUGUST.A-RICHMOND COUNTY, GEORGIA
. , '
, .
CPB :# 323-04-203823372
CAPITAL PROJECT BUDGET
POINTE SEST DRAINAGE IMPROVEMENTS
CHANGE NUMBER ONE
CPB AMOUNT CPB NEW 2005 GIL
SOURCE OF FUNDS CPB CHANGE CPB AMOUNT
SPECIAL 1 % SALES TAX, PHASE III
RECAPTURE
323-04-1110-60111110-2896823333 ($600,000) ($200,000) ($800,000) $0
TOTAL SOURCES: ($600,000) ($200,000) ($800,000) $0
USE OF FUNDS
ADVERTISING
323-04-1110-5233119-203823372 $2,000 $0 $2,000 $0
ENGINEERING
323-04-1110-5212115-203823372 $40,000 $13,000 $53,000 $13,000
RIGHT OF WAY
323-04-1110-5411120-203823372 $40,000 $40,000 $0
CONSTRUCTION
323-04-1110-5414110-203823372 $478,000 $ 137,000.00 $615,000 $137,000
CONTINGENCY
323-04-1110-6011110-203823372 $40,000 $ 50,000.00 $90,000 $50,000
TOTAL USES: $600,000 $200,000 $800,000 $200,000
Construction budget includes $81,280 for emergency completed in Sept. 2004. Total
construction available with 4/05 approval is $533,720
AUGUSTA-RICHMOND COUNTY
DEPARTMENT OF PUBLIC WORKS & ENGINEERING
SUPPLEMENTAL AGREEMENT
Project No.: 323-04-203823372
SUPPLEMENTAL AGREEMENT NO.: ONE
WHEREAS, We, Cranston, Robertson & Whitehurst, P.C,,- entered into a contract with Augusta-
Richmond County on April 6, 2004, for engineering design services associated with the Pointe
West Subdivision Drainage, Project No. 323-04-203823372.
WHEREAS, certain revisions to the design requested by Augusta-Richmond County are not
covered by the scope of the original contract, we desire to submit the following Supplemental
Agreement to-wit:
Additional engineering services associated with the work with Phase I-B and the
extension of the Phase II ditch piping work to the city's detention pond.
It is agreed that as a result of the above modification the contract amount is increased by
$12,965.00 to total of $64,346.40.
This agreement in no way modifies or changes the original contract of which it becomes a part,
except as specifically stated herein.
NOW, THEREFORE, We, Cranston, Robertson & Whitehurst, P.C, hereby agree to said
Supplemental Agreement consisting of the above mentioned items and prices, and agree that this
Supplemental Agreement is hereby made a part of the original contract to be performed under
the specifications thereof, and that the original contract is in full force and effect, except insofar
as it might be modified by this Supplemental Agreement.
This /qM dayof ~ ,2005.
RECOMMEND FOR APPROVAL:
L:2.
~.W~
Approved: Date
[ATTACHED COR~ORATE SEAL]
Approved: Date 4-/ /4} bS
[ATTACHED CORPORATE SEAL]
-'/
(SA02 - For changes greater than $20,000)
April 2005
~
Cranston, Robertson & Whitehurst, P.C.
ENGINEERS
PLANNERS
SURVEYORS
J. CRANSTON, P.E., R.L.S.
THOMAS H. ROBERTSON, P.E., RL.S.
ELD~IDGE A. WHITEHURST, JR., P.E.
JAMES B. CRANFORD, JR., P.E.
DENNISJ. WELCH, P.E.
OLD ENGINE COMPANY NO.1 POST OFFICE BOX 2546
452 ELLlS STREET AUGUSTA, GEORGlA 30903.2546
TELEPHONE (706) 722.1588
TELECOPIER (706) 722.8379
E..MAIL CRWPC@CRWPC.COM
Ms. Teresa C. Smith, P.E.
Director
Augusta Public Works and Engineering Department
1815 Marvin Griffin Road
Augusta, Georgia 30906
r'-~--~<-",: '
March 15, 2001 ~..
I
\
I I.
l~~...-,..,
JOlIN T. ATTAWAY, RL.S.
WAYNE SWANN, P.E., RL.s.
KYLE G. BAXLEY
JACOB E LANG
, . "''''''''':;J. DAN'L MOULTON
JAMES M. SINGLETON
" i BOBBY M. USRY
"''''''0 JASD~~C~~;~~~
I
I
I
I
I
___J
\.
Re: Pointe West Subdivision Drainage
Our File No. 2004-014
Dear Teresa:
In accordance with our meeting of February 17,2005, we have revised our plans to extend the Phase
II piping work to the detention pond as requested and have enclosed, for your review and comments, three
sets of the 60% plans for Phase I-B, Phase II and Phase III of the Pointe West Drainage Improvements
proj ect.
As we discussed in our meeting, the work associated with Phase I-B (piping the Publix detention
pond) and the extension of the Phase II piping down to the detention pond is beyond our original scope of
work. Therefore, we are hereby requesting the following supplemental fees to cover the additional required
surveying and engineering design work.
Phase I-B: Field Locate Existing Sanitary Sewers
& Profile Approximately 1,500 Feet of Proposed
Storm Line from the Publix Pond to the City
Detention Pond
$
5,025.00
Phase II Extension: Field Profile approximately
500 Feet Extension of the Phase II Pipe to the City
Detention Pond
$
1,850,00
Engineering Design of Phase I-B & Phase II
Extension
$
6,090.00
Additional Surveying & Engineering Fees
$
12,965.00
Ms. Teresa C. Smith, P.E.
March 15,2005
Page 2
Once you have had a chance to review the plans, we would like to meet with you to go over any
comments that you may have. In the meantime, should you have any questions regarding the plans or the
additional fees, please do not hesitate to give us a call.
Sincerely,
CRANSTON, ROBERTSON & WHITEHURST, P.e.
~..-=-- -
~.W~
Dennis J. Welch, P.E.
DJW /tdj
G:IAA-CORRESPONDENCE\2004104-014 pointe west suM drainage impIProposalsl04-014 Add'! Services ProposaLwpd
.' .
AUGUST A-RICHMOND COUNTY
DEPARTMENT OF PUBLIC WORKS & ENGINEERING'
SUPPLEMENTAL AGREEMENT
Project No.: 323-04-203823372
SUPPLEMENTAL AGREEMENT NO.: ONE
WHEREAS, We, Cranston, Robertson & Whitehurst, P.C,,- entered into a contract with Augusta-
Richmond County on April 6, 2004, for engineering design services associated with the Pointe
West Subdivision Drainage, Project No. 323-04-203823372.
WHEREAS, certain revisions to the design requested by Augusta-Richmond County are not
covered by the scope of the original contract, we desire to submit the following Supplemental
Agreement to-wit:
Additional engineering services associated with the work with Phase I-B and the
extension ofthe Phase II ditch piping work to the city's detention pond.
It is agreed that as a result of the above modification the contract amount is increased by
$12,965.00 to total of $64,346.40.
This agreement in no way modifies or changes the original contract of which it becomes a part,
except as specifically stated herein.
NOW, THEREFORE, We, Cranston, Robertson & Whitehurst, P.C, hereby agree to said
Supplemental Agreement consisting of the above mentioned items and prices, and agree that this
Supplemental Agreement is hereby made a part of the original contract to be performed under
the specifications thereof, and that the original contract is in full force and effect, except insofar
as it might be modified by this Supplemental Agreement.
This ~ day of ~ ,2005.
RECOMMEND FOR APPROVAL:
1'W~~
Approved: Date
[ATTACHED CORPORATE SEAL]
Approved: Date ;1t + ! t) 'S
[ATTACHED CORPO TE EAL]
"
"
(SA02 - For changes greater than $20,000)
April 2005
~
Cranston, Robertson & Whitehurst, PC.
ENGINEERS PLANNERS SURVEYORS
J. CRANSTON, P.E., RL.S.
THOMAS H. ROBERTSON, P.E., RL.8.
ELD~lDGE A. WHITEHURST, JR., P.E.
JAMES B. CRANFORD, JR., P.E.
DENNISJ. WELCH, P.E.
OLD ENGINE COMPANY NO.1 POST OFFICE BOX 2546
452 ELLIS STREET AUGUSTA, GEORGIA 30903.2546
TELEPHONE (706) 722.1588
TELECOPIER (706) 722.8379
E.MAIL CRWPC@CRWPC.COM
r----.....;:
March 15, 200$ ~,'.,.
r-....
I.
JOHN T. ATTAWAY, RL.S.
WAYNE SWANN, P.E., RL.8.
KYLE G. BAXLEY
JACOB E. LANG
. ",-"-'-'-J. DAN'L MOULTON
JAMES M. SINGLETON
i BOBBY M. USRY
''''''~JASD1~c~~:L~~~
I
,
,
I.,"
i
\
i
I__..._.._J
Ms. Teresa C. Smith, P.E.
Director
Augusta Public Works and Engineering Department
1815 Marvin Griffin Road
Augusta, Georgia 30906
il !.'
L_,._.......
Re: Pointe West Subdivision Drainage-
Our File No. 2004-014
Dear Teresa:
In accordance with our meeting of February 17,2005, we have revised our plans to extend the Phase
II piping work to the detention pond as requested and have enclosed, for your review and comments, three
sets of the 60% plans for Phase I-B, Phase II and Phase III of the Pointe West Drainage Improvements
project. .
As we discussed in our meeting, the work associated with Phase I-B (piping the Publix detention
pond) and the extension of the Phase II piping down to the detention pond is beyond our original scope of
work. Therefore, we are hereby requesting the following supplemental fees to cover the additional required
surveying and engineering desigri work.
Phase I-B: Field Locate Existing Sanitary Sewers
& Profile Approximately 1,500 Feet of Proposed
Storm Line from the Publix Pond to the City
Detention Pond
$
5,025.00
Phase II Extension: Field Profile approximately
500 Feet Extension of the Phase II Pipe to the City
Detention Pond
$
1,850.00
Engineering Design of Phase I-B & Phase II
Extension
$
6,090.00
Additional Surveying & Engineering Fees
$
12,965.00
Ms. Teresa C. Smith, P.E.
March 15,2005
Page 2
Once you have had a chance to review the plans, we would like to meet with you to go over any
comments that you may have. In the meantime, should you have any questions regarding the plans or the
additional fees, please do not hesitate to give us a call.
Sincerely,
CRANSTON, ROBERTSON & WHITEHURST, P.c.
~~
~_W~
Dennis J. Welch, P.E.
DJW /tdj
G:\AA-CORRESPONDENCE\2004104-014 pointe west subd, drainage implProposalsl04.014 Add'l Services ProposaLwpd
iJII
..
AUGUSTA-RICHMOND COUNTY
DEPARTMENT OF PUBLIC WORKS & ENGINEERING'
SUPPLEMENTAL AGREEMENT
Project No.: 323-04-203823372
SUPPLEMENTAL AGREEMENT NO.: ONE
WHEREAS, We, Cranston, Robertson & Whitehurst, P.C.:. entered into a contract with Augusta-
Richmond County on April 6, 2004, for engineering design services associated with the Pointe
West Subdivision Drainage, Project No. 323-04-203823372.
WHEREAS, certain revisions to the design requested by Augusta-Richmond County are not
covered by the scope of the original contract, we desire to submit the following Supplemental
Agreement to-wit:
Additional engineering services associated with the work with Phase I-B and the
extension of the Phase II ditch piping work to the city's detention pond.
It is agreed that as a result of the above modification the contract amount is increased by
$12,965.00 to total of $64,346.40.
This agreement in no way modifies or changes the original contract of which it becomes a part,
except as specifically stated herein.
NOW, THEREFORE, We, Cranston, Robertson & Whitehurst, P.C, hereby agree to said
Supplemental Agreement consisting of the above mentioned items and prices, and agree that this
Supplemental Agreement is hereby made a part of the original contract to be performed under
the specifications thereof, and that the original contract is in full force and effect, except insofar
as it might be modified by this Supplemental Agreement.
/J f'JA. : /J
This /qltvdayof ~ ,2005.
RECOMMEND FOR APPROVAL:
o .GIT)[ OF
~ ~AUGUST
c--o__-
-5 W~h
Approved: Date
[ATTACHED CORPORATE SEAL]
AT~df~
Title: ('jl~~~~
Approved: Date 4}14/ /:) S
[ATTACHED CORPORATE SEAL]
Title:
(SA02 - For changes greater than $20,000)
April 2005
..
~
Cranston, Robertson & Whitehurst, PC.
ENGINEERS PLANNERS SURVEYORS
OLD ENGINE COMPANY NO. 1 POST OFFICE BOX 2546
452 ELLIS STREET AUGUSTA, GEORGlA 30903.2546
TELEPHONE (706) 722.1588
TELECOPIER (706) 722.8379
E.MAIL CRWPC@CRWPC.COM
J. cRANSTON, P.E., RL.S.
THOMAS H. ROBERTSON, P.E., RL.S.
ELD~IIlGE A. WHITEHURST, JR., P.E.
JAMES B. CRANFORD, JR., P.E.
DENNISJ. WELCH, P.E.
l-...~.
March 15, 200 ~.
r-"""'" "
1
I
l
! i\!
!
\
..................
Ms. Teresa C, Smith, P.E.
Director
Augusta Public Works and Engineering Department
1815 Marvin Griffin Road
Augusta, Georgia 30906
Dear Teresa:
(
L.-.."...
..
!', 1
JOHN T. ATTAWAY, ilL.S.
WAYNE SWANN, P.E., RL.S.
KYLE G. BAXLEY
JACOB E LANG
,." . "'-'~-J. DAN'L MOULTON
J~' S M. SINGLETON
c, , " BOBBY M, USRY
,,,' ".......,. JASN M. WHINGHTER
DSCOTT WILLIAMS
\
i
i
I
I
...._-1
Re: Pointe West Subdivision Drainage
Our File No. 2004-014
Phase I-B: Field Locate Existing Sanitary Sewers
& Profile Approximately 1,500 Feet of Proposed
Storm Line from the Publix Pond to the City
Detention Pond
$
In accordance with our meeting of February 17,2005, we have revised our plans to extend the Phase
IT piping work to the detention pond as requested and have enclosed, for your review and comments, tlrree
sets of the 60% plans for Phase I-B, Phase IT and Phase III of the Pointe West Drainage Improvements
project.
As we discussed in our meeting, the work associated with Phase I-B(piping the Publix detention
pond) and the extension of the Phase II piping down to the detention pond is beyond our original scope of
work. Therefore, we are hereby requesting the following supplemental fees to cover the additional required
surveying and engineering design work.
Phase II Extension: Field Profile approximately
500 Feet Extension of the Phase II Pipe to the City
Detention Pond
$
Engineering Design of Phase I~B & Phase IT
Extension
$
Additional Surveying & Engineering Fees
$
5,025.00
1,850.00
6,090.00
12,965.00
Ms. Teresa C. Smith, P.E.
March '15,2005
Page 2
Once you have had a chance to review the plans, we would like to meet with you to go over any
comments that you may have. In the meantime, should you have any questions regarding the plans or the
additional fees, please do not hesitate to give us a call.
..
Sincerely,
CRANSTON, ROBERTSON & WHITEHURST, P.C.
-U..a-- -
~~W~
Dennis J. Welch, P.E.
DJW/tdj
G:IAA.CORRESPONDENCE\2004104.014 pointe westsubd. drainage implProposals\04cOl4 Add') Services Proposal.wpd