CAPIT AL PROJECT BUDGET
PAVING VARIOUS ROADS, PHASE VI
BE IT ORDAINED by the Commission of Augusta-Richmond County, Georgia that the
following capital project budget is hereby adopted:
Section 1. The project authorized is for the grading, draining and paving of 22 dirt roads. These
roads are: Pollard Road, 14th Avenue, McComlick Road, Queen's Way, Gaskill Road, Martin
Lane, Carter's Lane, Unbecker Road, Wise Drive, County Line Road West, Hobson Mill Road,
Pine Tucker Road, Baxley Lane, Mytris Street, Gracewood Drive ,Nunnery Road, Forest Road
Extension, Meyers Lane, Bowers Road, Carter Lane, Winter Street and Jason Lane. The
estimated costs of $1,000,000 are to be funded by the balance of County Forces funds in Special
1 % Sales Tax, Phase III Suburban which is $950,000 and $5,000 is to come form Special 1 %
Sales Tax, Phase III Urban.
Section 2. The following revenues are anticipated to be available to the Commission to complete
the project:
Special 1 % Sales Tax, Phase III Urban
Special 1 % Sales Tax, Phase III Suburban
$ 50,000.00
$950,000.00
$1,000,000.00
Section 3. The following amount(s) are to be expended for the project:
By District
Adopted this
15t $ 67,600
2nd $ 19,700
3rd $119,500
4th $ 15,800
5th $ 16,200
6th $142,900
ih $ 57,800
8th $ 564,500
$1,000,000
2/ day of ~NI-'
,1998.
Approved:
Original - Commission Office
Copy - Finance Department
Copy - Public Works Department -Engineering Division
Copy - Purchasing Department
.~
-.
. .....
....v '.... '.
-.
Augusta-Richmond County
CPB# 57 -8709-098
CPB# 59-8709-098
CAPITAL PROJECT BUGET
PAVING VARIOUS ROADS PHASE VI
SOURCE OF FUNDS
CPB
Amount
1998 G/L
Amount
Special 1 % Sales Tax,Phase III
57 -3131-00-0000
$ (950,000.00)
Special 1 % Sales Tax-Phase III
59-3131-00-0000
$ (50,000.00)
Contingency
57 -4981-00-0606
TOTAL SOURCES
$ (1,000,000.00)
$ (950,000.00)
$ (50,000.00)
$ (1,000,000.00)
Contingency
59-4981-00-0606
USE OF FUNDS
Advertising
57 -8709-0254 $ 1,000.00 $ 1,000.00
Engineering
57 -8709-0442 $ 80,000.00 $ 80,000.00
Construction
57-8709-0881 $ 777,100.00 $ 777,100.00
Construction
59-8709-0881 $ 50,000.00 $ 50,000.00
Contingency
57 -8709-0606 $ 91.900.00 $ 91,900.00
$ 1,000,000.00 $ 1,000,000.00