~-.Aut;USTA-RICHMOND COUNTY, GEORGIA
,r .
CPB# 57-8270-096
CAPITAL PROJECT BUDGET AMENDl\ffiNT
FOREST PARI\: SID DRAINAGE IMPROVEl\ffiNTS, PHASES I & IT
CHANGE NUMBER TWO
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County, Georgia
that the following Capital Project Budget is hereby amended:
section 1.
Section 2.
section 3.
section 4.
section 5.
The project change authorized is to CPB#57-8270-096 adopted
May 21, 1996. This change is to combine Phase I and II of the
Forest Park Subdivision Drainage Improvements projects into
one (including the Castlewood Drive Detention Basin). The
additional funds of $607,737 are set aside in Special One
Percent Sales Tax, Phase III for these projects.
The project director is hereby instructed to proceed with the
project within the terms of the funds appropriated herein.
The foilowing revenues are anticipated to be available to the
Commission-Council to complete the project:
Special One Percent Sales Tax, Phase III
$783,550
The following amounts are appropriated for the project:
BY BASIN
BY DISTRICT
Rock
$783,550
7th
$783,550
Copies of this capital Project Budget Amendment shall be made
available to the Comptroller for direction in carrying out
this project.
Adopted this
3,
k~#-
/ Ifft
day of
; JJ:J 2f 7)~ j
~
Original - Commission-Council Office
Copy ~ Finance Department
Copy - Public Works & Engineering Department
Copy - Purchasing Department
"
"
.AUGUSTA-RICHMOND COUNTY, GEORGIA
; -
CPB# 57-8270-096
CAI)ITAL PROJECT BUDGET AMENDMENT
FOREST PARJK SID DRAINAGE IMPROVEMENTS, PHASE I & IT
CHANGE NUMBER TWO
SOURCE OF FUNDS
CURRENT
CPB
CPB
CHANGE
NEW
CPB
1998 G/L
AMOUNT
special 1% Sales Tax, Phase III
57-3131-00-0000
($175,813) ($607,737) ($783,550)
contingency
57-4981-00-0606
($607,737)
TOTAL SOURCES
($175,813) ($607,737) ($783,550) ($607,737)
USE OF FUNDS
Advertising
57-8270-00-0254 $1,000 $1,000 $1,000
Engineering
57-8270-00-0442 $29,713 $29,713
Contingency
57-8270-00-0606 $12,100 $12,737 $24,837 $12,737
Rights-of-way
57-8270-00-0813 $13,000 $65,000 $78,000 $65,000
Construction
57-8270-00-0882 $121, 000 $529,000 $650,000 $529,000
TOTAL USES: $175,813 $607,737 $783,550 $607,737