AUGUSTA-RICHMOND COUNTY, GEORGIA
CPB# 322-04-203822642
CAPITAL PROJECT BUDGET
PINNACLE PLACE DRAINAGE IMPROVEMENT
CHANGE NUMBER TWO
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County,
Georgia that the following Capital Project Budget is hereby adopted:
Section 1: The project is authorized to CPB# 322-04-203822642. The
funding for this project is needed for Right of Way, Construction
and Contingency. We propose to address the drainage issues.
The additional amount of $-230,000 will be funded by the Special
1 % Sales Tax, Phase II Recapture Funds.
Section 2: The following revenues are anticipated to be available to the
Consolidated Government to complete the project:
Special 1 % Sales Tax, Phase I Recapture
Special 1 % Sales Tax, Phase II Recapture
Special 1 % Sales Tax, Phase II Recapture
$ 211,000
$ 289,000
$ 230,000
$ 730,000
Section 3: The following amounts are appropriated for the project:
Bv Basin
Bv District
Butler Creek
$ 730,000
4th
$ 730,000
Section 4: Copies of this Capital Project Budget shall be made available to
the Comptroller for direction in carrying out this project.
Adopted this
1,
daYOf1~ ,
Approved
'/A ......
~~~ 2J5j;/ Zi
~ ~. .(;eZ
Bob Yo ng, yor ::::::-.::::(:::: ..
... .....:-......... -
............. -
-
Original - Commission -Council Office
Copy - Public Works
Copy - Finance Department
Copy - Purchasing Department
, ....,
,.; AUGUSTA-RICHMOND COUNTY, GEORGIA
.CPB# 322-04-203822642
CAPITAL PROJECT BUDGET
PINNACLE PLACE DRAINAGE IMPROVEMENT
CHANGE NUMBER TWO
CPB AMOUNT CPB NEW 2005 G/L
SOURCE OF FUNDS CPB CHANGE CPB AMOUNT
SPLOST PHASE I RECAPTURE
321-04-1110-6011110-288821333 ($211,000) $0 ($211,000) $0
SPLOSTPHASEIIRECAPTURE
322-04-1110-6011110-292822333 ($289,000) $0 ($289,000)
SPLOSTPHASEIIRECAPTURE ($230,000) ($230,000)
322-04-1110-6011110-292822333
TOTAL SOURCES: ($500,000) ($230,000) ($730,000) $0
USE OF FUNDS
ADVERTISING
322-04-1110-5233119-203822642 $2,000 $0 $2,000 $0
ENGINEERING
322-04-1110-5212115-203822642 $50;150 $0 $50,150 $0
RIGHT OF WAY
322-04-1110-5411120/203822642 $ 25,000 $25,000
CONSTRUCTION
322-04-1110-5414710-203822642 $408,000 $ 185,000 $593,000 $0
CONTINGENCY
322-04-1110-6011110-203822642 $39,850 $ 20,000 $59,850 $0
TOTAL USES: $500,000 $230,000 $730,000 $0
5/12/2005