HomeMy WebLinkAboutROCHESTER AND ASOCIATED SUPPLEMENTAL AGREEMENT NO 3
AUGUSTA, GEORGIA
ENGINEERING DEPARTMENT
SUPPLEMENTAL AGREEMENT
Project No. 323-041110-201823332
Supplemental Agreement N03
PO: '1248
WHEREAS, We, "Rochester and Associates" Consultant, entered into a contract with
Augusta-Richmond County on "February 18,2003", for engineering design services associated
with the "Belair Road Improvements Project", Project No. 323-041110-201823332, File
Reference No. 08-014 (A), and
WHEREAS, certain revisions to the design requested by Augusta-Richmond County are not
covered by the scope of the original contract, we desire to submit the following Supplemental
Agreement to-wit:
Assist Augusta-Richmond County with surveying, planning, design and
permitting of three (3) intersections along Belair Road based on the
recommendations in the March 13, 2009 Traffic Study prepared by
Southeastem Engineering, Inc.
It is agreed that as a result of the above described modification the contract amount is
increased by $65_000.00 from $164-578.09 to a new total of $229.578.09.
Any modifications to submittal dates shall be as identified in the attached proposal. This
agreement in no way modifies or changes the original contract of which it becomes a part,
except as specifically stated herein,
NOW, THEREFORE, We, "Rochester and Associates", Consultant, hereby agree to said
Supplemental Agreement consisting of the above mentioned items and prices, and agree that
this Supplemental Agreement is hereby made a part of the original contract to be performed
under the specifications thereof, and that the original contract is in full force and effect,
except insofar as it might be modified by this Supplemental Agreement.
This IS/!. day of ~ ' 20"9.
RECOMMEND FOR APPROVAL:
CITY OF AUGUSTA-RICHMOND COUNTY
AUEff:X:;~
Deke Copenhaver, Mjlyor I
Approved: Date q t-kf- c..t) ~
(SAOl - For changes more than $20,000)
ArrEST: ~ t~ _
Title: YIP E- ~ecs\DE'N7
August 2009