HomeMy WebLinkAboutMARVIN GRIFFIN ROAD IMPROVEMENTS (SUPPLEMENTAL AGREE,MENT 1
<,'
'~
/
AUGUSTA-RICHMOND COUNTY
DEPARTMENT OF PUBLIC WORKS & ENGINEERING
SUPPLEMENTAL AGREEMENT
Project No. 323-04-296823603
SUPPLEMENTAL AGREEMENT NO.1
P.O. 57943
WHEREAS, We, Hussey, Gay, Bell & DeYoung International, Inc., Consultant, entered into a
contract with Augusta-Richmond County on December 18, 2001, for engineering design services
associated with the Marvin Griffin Road Improvements, Project No. 323-04-296823603, File
Reference No. 05-014 (A), and
WHEREAS, certain revisions to the design requested by Augusta-Richmond County are not
covered by the scope of the original contract, we desire to submit the following Supplemental
Agreement to-wit:
Additional Engineering services needed for finalizing the field survey and storm sewer
design that was not included in the original design scope.
It is agreed that as a result of the above modification the contract amount is increased by
$19,600.00 from $121,477.49 to a new total of $141,077.49
This agreement in no way modifies or changes the original contract of which it becomes a part,
except as specifically stated herein.
NOW, THEREFORE, We, Hussey, Gay, Bell & DeYoung International, Inc. Consultant, hereby
agree to said Supplemental Agreement consisting of the above mentioned items and prices, and
agree that this Supplemental Agreement is hereby made a part of the original contract to be
performed under the specifications thereof, and that the original contract is in full force and effect,
except insofar as it might be modified by this Supplemental Agreement.
This 14th day of February
,2005.
RECOMMEND FOR APPROVAL:
)~
Fred
~~~
Approved: Date
.r/2ylc1'~
Approved: Date ..?~0.J
[ATTACH C~RPIJJE SEA: ] .
ATTEST~/c(~~
&c-
Title:
~
.
'.,
ACCEPTANCE COpy
PLEASE REtURN TO
HUSSEY, GAY, BELL & DEYOUNG
C.
OF SOUTH CAROLINA
'.
HUSSEY, GAY, BELL & DEY
A Bell Company
AMENDMENT NO.1
, Amendment No. 1 amends the Consultant Services Agreement between the Augusta, GA Public
Works and Engineering Department (the Owner) and Hussey, Gay, Bell & DeYoung, Inc. (the
Engineer) for Marvin Griffin Road Improvements (Project No. 323-04-296823603) and dated
January 3,2003. ,This amendment gives the Engineer the Owner's authorization to proceed with
the items identified in the following paragraphs.
This amendment is a result of guidance provided by the City's project officer to the Engineer
during a meeting on November 30, 2004. '
Introduction
The proposed roadway improvements to Marvin Griffin Road (MGR) will more than double the
amount of impervious surface area. When impervious area is created on what was previously
pervious, there is an increase in the amount of stormwater runoff.
MGR is currently an open ditch section, and the ditches provide storage in addition to being a
means of conveyance of the stormwater runoff. By changing the roadway to a curb and gutter
section with a closed stormwater system, the storage and infiltration provided by the roadside
ditches is no longer available. Therefore, the amount of stormwater runoff reaching the outfalls
will be greater than what was discharged prior to the road improvements.
Background
On the basis of our work, we offer the following:
1. In order to ensure that post-development runoff flows are not greater than pre-
development flows at the outfalls, detention will be necessary. Due to the lack of
topographic relief, a traditional detention pond with outlet structure is not considered
suitable for use. A retention pond or underground detention system are suggested as the
most logical solutions. These facilities allow for the discharge of runoff before the pipe
system gets too large or too deep.
2. A retention pond or underground detention system will require that the Owner acquire
additional rights-of-way.
3. Presently, the conversion to a closed system from an open system results in the proposed
pipe. invert elevations being lower than the pipes and/or ditches to which they are
intended to connect. By placing intermittent detention facilities along the road corridor,
the primary outfalls should remain usable as is.
1219 ASSEMBLY STREET (29201)' P.O. BOX 7967' COLUMBIA, SOUTH CAROLINA 29202' TELEPHONE 803.799.0444' FACSIMILE 803.799.1499
www.hgbd.com
v'
~-_._---,~_.__.............
Amendment No.1
Page 2
Objectives
ACCEPTP,:"~CE. COpy
PLEASE FiETUi={N TO
HUSSEY, GAY, BELL & DEYOUNG
The work authorized by this amendment will allow the Engineer to:
1. Identify the preferred location(s) for retention ponds based on hydraulic considerations
2. Tentatively size storage capacities at the retention ponds
3. Tentatively size conveyance pipes comprising the drainage collection system.
Final design of the stormwater system will be dependent upon the City's choice of locations for
the retention ponds.
Compensation to HGBD ................................................................................. Lump Sum $9,600.00
In a~dition, the following services may be required by sub-consultants:
Laboratory tests, geo-technical tests (for example, field density tests, soil
borings), determination, delineation, and permitting activities for impacts to
wetlands and the crossing of streams, historical preservation research, endangered
species evaluation, and specialized geological studies may be recommended by
HGBD.
The cost of such tests and/or studies shall be borne by the Owner; provided, however that the
Owner shall be advised of and given consent to such tests and/or studies prior to their being
made.
This amendment is formally entered into and agreed upon this _ day of
,2004,
HU SEY, GAY, BELL & DEYOUNG, INC.
AUGUSTA, GEORGIA DEPARTMENT OF PUBLIC WORKS AND ENGINEERING
Authorized Signature
Print Name and Title
Witness
..
HUSSEY, GAY, BELL & DEYO
ACCEPTAr\lCE COpy
PLEASE RETURN TO
t@IQA1QUNC
OF SOUTH CAR A
A Bell Company
:;.
. ~
to ;'
)....
AMENDMENT NO.2
Amendment No.2 amends the Consultant Services Agreement between the Augusta, GA Public
Works and Engineering Department (the Owner) and Hussey, Gay, Bell & DeYoung, Inc. (the
Engineer) for Marvin Griffin Road Improvements (Project No. 323-04-296823603) and dated
January 3,2003. This amendment gives the Engineer the Owner's authorization to proceed with
the items identified in the following paragraphs.
This amendment is a result of guidance provided by the City's project officer to the Engineer
during a meeting on November 30,2004.
Item
Provide additional topographic survey, where required, at'those locations identified as intended
sites of proposed stormwater retention ponds.
Compensation to HGBD for additional topographic survey shall be on an hourly basis and shall
be based on technical salary cost, plus chargeable expenses in accordance with the attached
Schedule of Hourly Rates. We estimate the fee to be in the range of $7,500.00 to $10,000.00.
This amendment does not include any engineering services.
This amendment is formally entered into and agreed upon this --.--:... day of
,2004,
HU SEY, GAY, BELL & DEYOUNG, INC.
/ '
AUGUST A, GEORGIA DEPARTMENT OF PUBLIC WORKS AND ENGINEERING
Authorized Signature
Print Name and Title
Witness
[219 ASSEMBLY STREET (2920l)' P.O. BOX 7967' COLUMBlA, SOUTH CAROLINA 29202' TELEPHONE 803.799.0444' FACSIMILE 803.799.1499
www.hgbd.com