HomeMy WebLinkAboutBRW CONSTRUCTION GROUP
". . .. '
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~ It /7 9 so
CONTR.A.CT DOCUMENTS AND SPECIFICATIONS
FOR
AUGUSTA WATER SYSTEM IMPROVEMENTS
CHLORINE BOOSTER STATION
BOND PROJECT NO. 10110
Augusta-Richmond County, Georgia
-=-~== ~
/Y-~~ ~
/, ~
I' ~ .' -. ", " . =
( ( ", .~.
( I 01.11 "'I'~-." lI.t'" 'U'I b ""..
..~.. ." r ~..... v..r'" ~
~ \. I
\ \ f. /
\\" "~ illll.mJOO\.~lXlOOm...n!WI.DI '. / /
" ~'"- ll1~@ ...-;~
, -=---= ~-= ,"
,~~~~
AUGUSTA-RICHMOND COUNTY COMMISSION
Cranston, Robertson & Whitehurst, P.C.
Engineers - Planners - Surveyors
P.O. Box 2546 - 452 Ellis Street
Augusta, Georgia 30903
November, 2004
...,.,
01-387
-16-2005 00:04
ARC PURCHASING
7063124602
P.02/02
I
~~
~10eU/T-e?'nBn.t &~~
9Ui' @f>>fi ({}h~. &~
R 0 I .A
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ADDENDUM
TO:
FROM:
DATE:
SUBJ:
All Bidders
Geri A Sams
May 16, 2005
Addendum #2
Bid Item #OS-061A
Please note the following addition/changes to your bid specifications:
PROJECT NO. 10110-
AUGUSTA WATER SYSTEM IMPROVEMENTS - CHLORINE BOOSTER
STATION
The bid opening date has been changed from Wednesday, May 18, 2005 @3:00 p.m.
to Monday, May 23, 2005 @ 3:00 p.m.
I. The following items have been revised or added to the contract documents and
specifications:
A Revise all references to the time of completion from Ninety (90) to One-
Hundred- Eighty (I 80) days.
IT. The following clarifications/amendments have been made to the contract
drawings: (No revised contract drawing sheets will be reissued.)
A. Revise all references to the time of completion from Ninety (90) to One-
Hundred-Eiehty (180) days. '
Please acknowledge receipt of addendum in your bid package.
If you have, any questions regarding this correspondence, please contact me at
(706) 821-2422.
Room 605 - 530 Greene Street, Augusta, Georgia 30911
(706) 821-2422 - Fax (706) 821-2811
WWW.llt1rnsta~~OV
Register atwww dem8ndstar,c:om/8Uppll~ for alItOmatlc bid notifiC<1tion
TOTAL P.02
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Addendum No.1
to the
Contract Documents and Drawings
for the construction of
PROJECT NO. 10110
AUGUSTA WATER SYSTEM IMPROVEMENTS - CHLORINE BOOSTER
STATION
Our File No. 2001-387
May 10, 2005
1. The following questions from the Pre-Bid Conference and subsequent correspondence have
been addressed:
A. What is the amperage of the service to the new building?
See enclosed detail on Page 2 of 2.
B. What type and size of wiring is required for the signal line to the altitude valve
pit?
The signal line between the sodium hypochlorite system and the altitude valve shall
be a low voltage cable to be coordinated with the system supplier.
C. What type of breaker is required to match existing equipment?
See enclosed detail on Page 2 of 2.
D. Is the wiring on Sheet 5 of the contract drawings factory installed or field
installed?
Internal wiring shall be coordinated with sodium hypochlorite system supplier.
IT. The following clarifications/amendments have been made to the contract drawings: (No
revised contract drawing sheets will be reissued.)
A. Sheet 3 - Revise 2" and 4" PVC conduct for electrical to 1" and 11/2", respectively.
B. Sheet 4 - Revise power service note from single phase to three phase.
C. Sheet 6. Building, Note IF - Delete in its entirety and replace with "prewired
electrical panel suitable for 1201208 volt, 3 phase, 125 amp M.L.O."
D. Sheet 8 - Add enclosed detail on Page 2 of 2.
Addendum No.1 Page 1 of 2
I
I
I
I
I
I
I
I
I
I
1 ii~
1 t ~ ~'
1 J~
1 Ii
I
I
z G' ~
1\ r~
1 0
It V)
. ~ I
I
~i
) 08 ~.
II. ) fl~
~ t'-'
q~ ~ . tf~
. "va
~ ~'fl
-:;a ~ ~ ,c 1.1 - *
. ~'" _ 1 l' Z.. ~
~ : . - ------." 1 ~ 'i- .....
~ j:J~\IIi31
\' ~ I"c
{ ~~ii ~~f.f
I J t ~ f ~L
"0 n.. ~ ....
",'Yi:i""
, "P .
-
~
f\1:
V
\.fIJ
,-l
~
t
~
\\
'"
-
f
.w ~ ~
~U~fFI~
r t ~ f\
~ ... '"
:71j ~} ..
. t, -I ~ ~
fJ,! i ~
l1:~ ~ iA '='
r ~ ~ f
? ~ '1
fif u 11
S : i Jl
~ 1" ~
~j! Jq
~:~~~l
. \A ~ ~
t t-C!'"
'{RGlffiE
~ t ~,~
~ ..t
~'S'toj
t' f ~ f'
l:f. :(
i?~
r--
, t~ -li1
L.:a I ~..J
~f~~
~pf"
} $: ~ )
"'O~ --..
~ir'
~ · i I
f-Pl-a
'')(~
.. \Ill
~ jl
\jJ' ,
3 ·
t
"
!P;t\,li
i r r ~,
~ a \0. N
\; . \\
Qi)~ -.
~ ~
~ flP~
i p-t-
Addendum No 1
. Page 2 of 2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
CONTRACT DOCUMENTS AND SPECIFICATIONS
FOR
AUGUSTA WATER SYSTEM IMPROVEMENTS
CHLORINE BOOSTER STATION
BOND PROJECT NO. lOBO
Augusta, Georgia
AUGUSTA-RICHMOND COUNTY COMMISSION
The Honorable Bob Young
Mayor
Betty Beard
Marion F. Williams
Barbara Sims
Richard Colclough
Bobby G. Hankerson
Andy Cheek
Tommy Boyles
Jimmy Smith
Williams H. Mays, ill
Don A. Grantham
Max Hicks
Director, Augusta Utilities Department
Cranston, Robertson & Whitehurst, P.C.
Engineers - Planners - Surveyors
Augusta, Georgia
November, 2004
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
TABLE OF CONTENTS
SECTION TITLE NO. OF PAGES
I Invitation for Bids 1
IB Instructions to Bidders 3
P Proposal 3
BB Bid Bond 2
NA Notice of Award 1
A Agreement 3
PB Performance and Payment Bonds 5
NP Notice to Proceed 1
GC-O Index to General Conditions 1
GC General Conditions 57
SC-O Index to Supplementary Conditions 1
SC Supplementary Conditions 7
TS-O Index to Technical Specifications 1
TS Technical Specifications 57
I
Invitation To Re-Bid
I
Sealed re-bids will be received at this office until 3:00 p.m., Wednesday, May 18, 2005:
Re-Bid #05-061A
Augusta Water System Improvements Chlorine Booster Station for Augusta Utilities Department
I
I
Re-BIDS will be received by Augusta, GA Commission hereinafter referred to as the OWNER at the offices of:
Geri A. Sams, Director
Procurement Department
530 Greene Street - Room 605
Augusta, Georgia 30911
706-821-2422
I
Re-BID documents may be obtained at the office of Augusta, GA Procurement Department, 530 Greene Street - Room 605, Augusta,
GA 30911. Copies maybe obtained upon payment of$50.00 (non-refundable) Documents may be examined by appointment only
during regular business hours at the offices of Augusta, GA Procurement Department.
I
I
A MANDATORY Pre-BID Conference will be held on Tuesday, April 26, 2005 at 10:00 a.m. in Room 605 of the Procurement
Department. All questions must be submitted in writing by Friday, April 29, 2004 @ 3:00 p.m. to the office of the Procurement
Department by fax at 706-821-2811 or by mail. No bid will be accepted by fax, all must be received by mail or hand delivered.
I
It is the wish of the Owner that minority businesses are given the opportunity to BID on the various parts of the work. This desire on
the part of the Owner is not intended to restrict or limit competitive bidding or to increase the cost of the work. The Owner supports a
healthy free market system that seeks to include responsible businesses and provide ample opportunity for business growth and
development.
I
No BID may be withdrawn for a period of 60 days after time has been called on the date of opening. A 10% Bid bond is required to be
submitted in a separate envelope so marked along with the bidders' qualifications; a 100% performance bond and a 100% payment
bond will be required for award.
I
I
Bidders will please note that the number of copies requested; all supporting documents including financial statements and references
and such other attachments that may be required by the bid invitation are material conditions of the bid. Anypackage found incomplete
or submitted late shall be rejected by the Procurement Office. Any bidder allegedly contending that he/she has been improperly
disqualified from bidding due to an incomplete bid submission shall have the right to appeal to the appropriate committee of the
Augusta Commission. Please mark BID number on the outside of the envelope.
I
Bidders are cautioned that sequestration of BID documents through any source other than the office of the Procurement Department is
not advisable. Acquisition of BID documents from unauthorized sources placed the bidder at the risk of receiving incomplete or
inaccurate information upon which to base his qualifications.
I
Augusta has a Link Deposit program designed to provide loans to eligible local Small, Minority and Women Owned Businesses. For
more information about this program Human Resources Department at 706-821-2303.
I
GERI A. SAMS, Procurement Director
I
Publish:
Augusta Chronicle
Augusta Focus
March 31, April 7, 14,21,2005
April 7, 2005
I
cc:
Tameka Allen
Yvonne Gentry
Max Hicks
Doug Cheek
Jim Rush
Augusta, GA Interim Deputy Administrator
Augusta, GA DBE Coordinator
Augusta, GA Utilities Department
Augusta, GA Utilities Department
CH2M Hill
I.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision October, 2001
SECTION m
INSTRUCTION TO BIDDERS
m-Ol
GENERAL
All proposals must be presented in a sealed envelope, addressed to the Owner. The
proposal must be filed with the Owner on or before the time stated in the invitation for bids. Mailed
proposals will be treated in every respect as though filed in person and will be subject to the same
requirements.
Proposals received subsequent to the time stated will be returned unopened. Prior to
the time stated any proposal may be withdrawn at the discretion of the bidder, but no proposal may
be withdrawn for a period of sixty (60) days after bids have been opened, pending the execution of
contract with the successful bidder.
m-02
EXAMINATION OF WORK
Each bidder shall, by careful examination, satisfy himself as to the nature and location
of the work, the conformation of the ground, the character, quality and quantity of the facilities
needed preliminary to and during the prosecution of the work, the general and local conditions, and
all other matters which can in any way affect the work or the cost thereof under the contract. No oral
agreement or conversation with any officer, agent, or employee of the Owner, either before or after
the execution of the contract, shall affect or modify any of the terms or obligations therein.
ill-03
ADDENDA AND INTERPRETATIONS
No interpretation of the meaning of plans, specifications or other prebid documents
will be made to any bidder orally.
Every request for such interpretation should be in writing addressed to the Director
of Augusta Utilities Department c/o Augusta Purchasing Department, 530 Greene Street, Room 605,
Augusta, Georgia 30911, and to be given consideration must be received at least five days prior to
the date fixed for the opening of bids. Any and all such interpretations and any supplemental
instructions will be in the form of written addenda to the specifications which, ifissued, will be sent
by certified mail with return receipt requested to all prospective bidders (at the respective addresses
furnished for such purposes), not later than three days prior to the date fixed for the opening of bids.
Failure of any bidder to receive any such addendum or interpretation shall not relieve such bidder
from any obligation under his bid as submitted. All addenda so issued shall become part of the
Contract Documents.
ill-04
PREPARATION OF BIDS
Bids shall be submitted on the forms provided and must be signed by the bidder or his
authorized representative. . Any corrections to entries made on bid forms should be initialed by the
person signing the bid.
IB-l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision October, 2001
Bidders must quote on all items appearing on the bid forms, unless specific directions
in the advertisement, on the bid form, or in the special specifications allow for partial bids. Failure
to quote on all items may disqualify the bid. When quotations on all items are not required, bidders
shall insert the words "no bid" where appropriate.
Alternative bids will not be considered unless specifically called for.
Telegraphic bids will not be considered. Modifications to bids already submitted will
be allowed if submitted by telegraph prior to the time fixed in the Invitation for Bids. Modifications
shall be submitted as such, and shall not reveal the total amount of either the original or revised bids.
Bids by wholly owned proprietorships or partnerships will be signed by all owners.
Bids of corporations will be signed by an officer ofthe firm and his signature attested by the secretary
thereof who will affix the corporate seal to the proposal.
NOTE: A 10% Bid Bond is required in all cases.
m-05
BASIS OF AWARD
The bids will be compared on the basis of unit prices, as extended, which will include
and cover the furnishing of all material and the performance of all labor requisite or proper, and
completing of all the work called for under the accompanying contract, and in the manner set forth
and described in the specifications.
Where estimated quantities are included in certain items of the proposal, they are for
the purpose of comparing bids. While they are believed to be close approximations, they are not
guaranteed. It is the responsibility of the Contractor to check all items of construction. In case of
error in extension of prices in a proposal, unit bid prices shall govern.
m-06
BIDDER'S QUALIFICATIONS
No proposal will be received from any bidder unless he can present satisfactory
evidence that he is skilled in work of a similar nature to that covered by the contract and has sufficient
assets to meet all obligations to be incurred in carrying out the work. He shall submit with his
proposal, sealed in a separate envelope, a FINANCIAL EXPERIENCE AND EQUIP:MENT
STATE:MENT, giving reliable information as to working capital available, plant equipment, and his
experience and general qualifications. The Owner may make such investigations as are deemed
necessary to determine the ability of the bidder to perform the work and the bidder shall furnish to
him all such additional information and data for this purpose as may be requested. The Owner
reserves the right to reject any bid if the evidence submitted by the bidder or investigation of him fails
to satisfy the Owner that such bidder is properly qualified to carry out the obligations ofthe contract
and to complete the work contemplated therein. Part of the evidence required above shall consist of
a list of the names and addresses of not less than five (5) firms or corporations for which the bidder
has done similar work.
IB-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision October, 2001
m-07
PERFORMANCE BOND
At the time of entering into the contract, the Contractor shall give bond to the Owner
for the use of the Owner and all persons doing work or furnishing skill, tools, machinery or materials
under or for the purpose of such contract, conditional for the payment as they become due, of all just
claims for such work, tools, machinery, skill and terms, for saving the Owner harmless from all cost
and charges that may accrue on account of the doing of the work specified, and for compliance with
the laws pertaining thereto. Said bond shall be for the amount of the contract satisfactory to the
Owner and authorized by law to do business in the State of Georgia.
Attorneys-in-fact who sign bonds must file with each copy thereof a certified and
effectively dated copy of the power of attorney.
m-08
REJECTION OF BIDS
These proposals are asked for in good faith, and awards will be made as soon as
practicable, provided satisfactory bids are received. The right is reserved, however to waive any
informalities in bidding, to reject any and all proposals, or to accept a bid other than the lowest
submitted if such action is deemed to be in the best interest of the Owner.
m-09
MINORITY AND ECONOMICALLY DISADVANTAGED BUSINESS
SUPPORT
It is the intent of the Augusta-Richmond County Commission to increase the
involvement of qualified minority and economically disadvantaged businesses in the contracted work
of County Government.
In an effort to support this intention, this project is offered to all qualified firms. The
bids will be evaluated based on qualifications, price and construction time. With all other items being
considered equal, the contract, if awarded will be awarded to a minority and economically
disadvantaged firm or a firm that has included such firms as subcontractors on this project.
The bidders are required to submit a statement of qualification for themselves, a list
of qualified subcontractors (including local vendors) and all minority or economically disadvantaged
firms with their bid package. If the firm does not fall into this category, no information is necessary.
IB-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION P
PROPOSAL
DATE: May 23, 2005
Gentlemen:
In compliance with your invitation for bids, the undersigned hereby proposes to furnish all
labor, equipment and materials, and to perform all work for the project referred to herein as:
AUGUSTA WATER SYSTEM IMPROVEMENTS
CHLORINE BOOSTER STATION
BOND PROJECT NO. 10110
in strict accordance with the Contract Documents and in consideration of the amounts shown on the
bid schedule attached hereto and totaling:
{),(E,. fl~. .$.ff'r p",,~ -rNOrl~AJ ,;.,~ !-Iu,ftJKeb,
~,~-FDve . ,and J, /100dolJars~
The undersigned hereby agrees that, upon written acceptance of this bid, he will within
10 days of receipt of such notice execute a formal contract agreement with the Owner, and that he
will provide the bond or guarantees required by the contract documents.
The undersigned hereby agrees that, if awarded the contract, he will commence the
work within Ten am calendar days after the date of written notice to proceed, and that he will
complete the work within Ninety (90) calendar days after the date of such notice.
The undersigned acknowledges receipt of the following addenda:
Addendum #1, May 10, 2005 & Addendum #2. May 16,200S
Enclosed is a bid guarantee, consisting of
in the amount of
'h:>n [ll=>rf'l=>nr of bid alilgYIlt
Respectfully submitted,
BRW Construction Group, LLC.
FlRM NAME
PO Box 1806 Savannah,GA.31402
BUSINESS ADDRESS.
ByG?L~ ~
Robert K. Beck
TITLE: President
P-I
I
I I
I l
I f
I I
I I
I
I
I
I
I
I
II
II
II
If
II
II
I
BID SCHEDULE AUGUSTA WATER SYSTEM IMPROVEMENTS
CHLORINE BOOSTER STATION
TO ACCOMPANY THE PROPOSAL OF BOND PROJECT NO. 10110
BIDDER:
BRW Construction LLC.
ADDRESS: PO Box 1806
Savannah, GA. 31402
ITEM NO.
1.
2,
3,
4.
5.
6.
7.
8.
9.
10.
11.
12.
DESCRIPTION. OUANTITY. UNIT & UNIT PRICE
Precast concrete building complete with accessories and
finishes as specified, installed complete
1 EA @ $ 40, S Sq..!!!..IEA
CLOR- TEC on-site sodium hypochlorite generation system,
complete as specified
Lump Sum
Electrical service and system wiring, complete
Lump Sum
System piping (includes all piping inside of building)
Lump Sum
111 copper water service, installed complete with service
saddle and valve
1 EA @ $ 3,S2Jtf.o lEA
3/4" PVC., sodium hypochlorite injection line, installed
compete with service saddle and valve suitable for 0.8%
sodium hypochlorite solution3 CZC:. ..
1 EA @ $ ,3c;.1J-"" lEA
311 diameter PVC drain pipe SDR 35, Depth 0' to 6',
including Type II bedding material, 411 floor drain and tie
to existing storm drop inlet
Lump Sum
411 thick concrete sidewalk
150 S.F. @ $
~
IS.F.
611 graded aggregate base & 211 asphyaving
350 S.Y. @ $ z.. 7~ IS.Y.
Subtotal
Crushed stone construction outleb. _
1 EA @ $ l:'/~ lEA
Inlet sediment trap '/(, So
2 EA @ $ lEA
Pipe bollards IiJO.
2 EA @ $ Z.()~ lEA
P-2
AMOUNT
cO
$ 4o,5Sf=-
.
$ '{"Si-<fOO
CID
$ IQ300-
$
3,BI8~
.
$
3S24~
.
.
$
~ 38S.J!SL
-
3, ,iflD-
$ ~1r
.-
$ '.5~
.
$ /4-1, 8lo/~
.
$
$
8qo~
$
I cr,.e
$
-
'11Z-
I ITEM NO.
II 13.
I I 14.
I I
I I
I
I
I
I
I
I
I
I
I
II
I'
I,
I,
I
DESCRIPTION. QUANTITY. UNIT & UNIT PRICE
Double 10' chain link: gate, installed co~ete
1 EA @ $ 2.,200--- lEA
Lump sum construction (includes but is not limited to the
items listed)
Mobilization, Demobilization
Bonds and Insurance
Traffic Control
Raise to Grade Valve Boxes
Miscellaneous Grading
Property Restoration and Permanent Grassing
Temporary Grassing (ifr~quired)
Silt Fence, Type itA"
Lump Sum $
Grand Total $
P-3
AMOUNT
8C
$ 2r2s~
-
16,81a--
cae.
1Y1, ~31-
I
I
I
SECTION llB
all) BOND
I
, BRW Construction
KNOW ALL MEN BY THESE I'RESENT.S, tlLat we, cite 0
G LLC Companion Propeny Ol
-~~P: .~ ___~_ - as Princ;pal. iUld Casualty Insurance Com,g'!!'.hty. 'Te hereby
I
I
held and firmly boond Uoto the Au~ust'-_ond County CommisoioQ af Augusta, Ceo:r" "
. . . Ten Percent of Bid amount, penal sum not to excee
Owner J/l the pCl1all>um 01
thirty thousand dollars
I
:lnd severally bind Clur!:c::lv~s. our heirs. executors, administrators, successors and alo"Signs.
tofthe paymtnl of which, well and trlJ!Ytobe ma.de, vve her~byjointly
Signed this
23rd
day of
May
2005,
"----.> -
I
I
AugU!>1i1-Richnmnd Couoly Commission of Augusta, Georgia, a certain aid, attached hereto and
The cl>ndiriollllflnt: above Llbligatioll is such iliat where:a:5 the PrincipaJ has submitted to the
ht:n:by mad\::. part ben~of(o entc:r into Ii contract in writing for AUGUSTA WATER SYSTEM
I
IMJ~ROV[MENTS> ClfL.ORINI!: .BOOSTER STATION, BOND PROJECT NO. JOllO, for
I
Augu:na. Gt:orgia. in accordance with plan:! and speci.fications of the AUb'llSta Utilities Department.
I
NOW. THEREFORE,
(.1)
If:;ilid Bid ,:{b(lll bl: rejected. or in the alternate,
I
I
(b) I r said Bid shall be: acctpLed and the Principal shall execulc ind deliver a contract in
Ihl.:: Foml of COntracl attached hereto (properly completed in accordance \lfith said
8id) and SJlafJ turnisb a bond for his faithful perforrnCUlcc of said contract, and forthe
payment of all perSons performing labor or furnishing materials in connection
thefewith. and shall in aU olher respects perform the ~ment created by the
acceptance of said Bid, thell this obligation shaJJ be void, ot&erwil>e the Sllme shall
remain in force and c:ffect; it beillg expressly understood and agreed that the liability
oj' the Surety for any Clnd all claims hereunder shaU, in no cvem, exceed the penal
amount of this obligation as herein stated.
I
I
lht: S\Jrely. for villuereceive,hereby stipulates and agrec:i: that lhe obliga.tions of said Surety
I
illld iL:i blind shall be il1llo ''''''''lY impnired or aft'ected by any extension of the time within which the
Own~r ma)' ar.;cept such Bid; and said Surety does hereby wltive notice of my such eXI~nsion.
I
8B~1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
iN WiTNESS WHl:.REOF, [he:: Principal and the Surety have hereunto set their hands and
thc;;e pre:>enl S [0 he ~ig['ed hy their properofticers, the day and ye~dirst set f"Orth above,
seills. and su<:h Clt"them a:: fire corporations h1\vc:; caused their corporate seals to be hereto affixed and
S:~Ill:d <Ind );~nJcd this _ _ 23~~ ,.' , __ day of
May
A.D. 20 _~~.
Wirnes's _(iJ~ .iJ. G?~
~nstruc~Group" L, LC
, .!'k ~ ~ jSeaJ)
(Principal)
At[l:.~1
_.....-. .--..--.-....
By Pre~~
(Title)
(Seal)
Witness
~~
.....--
Companion Property &
Casualty Insurance Company
(Seal)
(Surety)
A[t~,..~
BY.O _UJ/Ld.
(TItle)
Donald H. Gibbs, Attorney-in~Fact
BB-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
COMPANION PROPERTY & CASUAL TV INSURANCE COMPANY
p, O. Box 100165 (29202)
51 Clemson Road
Columbia, SC 29229
GENERAL POWER OF ATTORNEY
Know all men by these Presents, that the COMPANION PROPERTY & CASUALTY INSURANCE COMPANY had
made, Constituted and appointed, and by these presents does make, Constitute and appoint Andrew C. Heaner of
Atlanta, Georgia; 'Richard L. Shanahan of Atlanta, Georgia; Scott Stoltzner of Birmingham, Alabama; Arthur S.
Johnson of Atlanta, Georgia; Lenora N. Cape of Gainesville, Georgia; Mary F. Holland of Chamblee, Georgia;
James E. Feldner of West Lake, Ohio; Jeffrey L. Booth of Parma, Ohio; or Donald H. Gibbs of Atlanta, Georgia,
EACH as its true and lawful attomey for it and its name, place and stead to execute on behalf of the said company,
as surety, bonds, undertakings and contracts of suretyship to be given to all obliges provided that no bond or
undertaking or contract of suretyship executed under this authority shall exceed in amount oOhe sumof $1,OOQ,OOO
(One Million dollars).
This Power of Attorney is granted and is signed' and sealed by facsimile under and by the authority of the following
Resolution adopted pursuant to due authorization by the Executive Committee of the Board of Directors of the
COMPANION PROPERTY & CASUALTY INSURANCE COMPANY on the 27th day of August 2004.
RESOLVED, that the Chairman, President or any Vice President of the Company be, and that each or any of them
hereby is, authorized to execute Powers of Attorney qualifying the attorney named in the given Power of Attorney to
execute in behalf of the COMPANION PROPERTY & CASUALTY INSURANCE COMPANY bonds, undertakings
and all contracts of suretyship; and that any Secretary or any Assistant Secretary be, and that each or any of them
hereby is, authorized to attest the execution of any such Power of Attorney, and to attach thereto the seal of the
Company.
FURTHER RESOLVED, that the signature of such officers and the seal of the Company may be affixed to any such
Power of Attorney or to any certificate relating thereto by facsimile, and any such Power of Attorney of certificate
bearing such facsimile signatures or facsimile seal shall be valid and binding upon the Company when so affixed
and in the future, with respect to any bond undertaking or contract of suretyship to which it is attached.
In Witness Whereof, the COMPANION PROPERTY & CASUALTY INSURANCE COMPANY has caused its official
seal to be hereto affixed, and these presents to be signed by its President and attested by its Vice President this
27th day of August 2004.
Attest COMPJ\NIOIIrPRC;>PERTY ~~ALTY INSURANCE CO~ANy /J~
By:~m ~ tI..;
Charles M. Potok, President Curtis C. Stewart, Vice President & CFO
STATE OF SOUTH CAROLINA
COUNTY OF RICHLAND
On this '\ I-L day of S~~~b...,. . '2.ciJ4 . before me personally came the above named Offi~~"t~~;;:~"()~
who being by me duly swo ,did depose and say that he resides in Columbia, in the County of Richla~~f, ~~te:~~~9ittat';'".
Columbia; that he is the President of COMPANION PROPERTY & CASUALTY INSURANCE COMP~N'ft,;ttieAArpofatl?n""./;:~
descri~ed. in and whi~h executed the above instrum~nt; that he knows the seal of th~ said C?rporation; tP.at)Jhe,~~1 aflix~9}p-2 \
the said Instrument IS such corporate seal; that It was so affixed and that he SIgned hIS name th!ilre~ p,u~suaDt to-.dU7--,'f:
uth . ti ~ ~- - '" ".....!-
a onza on. ~ :')\:::::- / .~" .; ~~ ;
. (/J". 'k ~ Notary Public. state of BC. QuaOfied ;n R;chland County Comm;ssK>n Expires: \~.: 1.~.~.'<\~'0~/
~TATE OF SOUTH CAROLINA "::'J'?"","!J 0.'5 '.-.",.'
COUNTY OF RICHLAND' . ':"'i'...,"j!,....
I, the undersigned, an Officer of COMPANION PROPERTY & CASUALTY INSURANCE COMPANY, a South Carolina
Corporation, DO HEREBY CERTIFY that the foregoing and attached Power of Attorney remains in full force and has not been
revoked; and, furthermore, that the Resolution of the Executive Committee of the Board of Directors set forth in the Power of
:::~dn::,: foal:e CRy of Colomb;a. Dated the ;yti of ;l1~2c;J ~~d
Number 661 Curtis C. Stewart, Vice President & CF'O
I
NOTICE OF A WARD
I
I
DATE: 06/22/2005
CONTRACTOR: BRW Construction Group. LLC
I
ADDRESS: PO Box 1806
I
Savannah
City
GA 31402
State Zip Code
PROJECT:
Chlorine Booster Station
PROJECT NO: 20225
I
I
At a meeting of the Augusta Commission
you were awarded the Contract for the following Project:
held on (Date) 06/21/2005
I
Augusta Water System Improvements - Chlorine Booster Station
Enclosed please find 5
copies of the Contract Documents for your execution. Please complete the
I
paqes. affixinq siqnatures. dates. notary and/or corporate seals. etc. where necessary and return to this office
10 days from the date of this letter, excluding Legal Holidays.
I
The Certificate of Insurance must be complete.
I
Power of Attorney must be submitted in triplicate; an original and two copies is permissible.
Very truly yours,
Augusta Program Management Team
I
I
Cj~'P
James Rush
I
~:::::W~::.~~:4~ ~m ~esl.~~t
Contractor By Title
Please sign and return one copy of this Notice of Award Acknowledgement to:
Augusta Utilities Department
Attn: Program Managers
2005
I
I
I
360 Bay Street, Suite 180
Augusta, GA 30901
I
I
20225 JR 05 06 22 M NOA SRW CONST.DOC
I
I
I
I
I
I
I
I
I
I
II
I
I
I
I
I
I
I
I
SECTION A
AGREEMENT
THIS AGREEMENT, made on the 2pt of June, 2005, by and between
AUGUSTA, GEORGIA BY AND THROUGH THE AUGUSTA-RICHMOND COUNTY
COMMISSION, party of the first part, hereinafter called the OWNER, and BRW Construction
Group, LLC, party of the second part, hereinafter called the CONTRACTOR.
WITNESSETH, that the Contractor and the Owner, for the considerations
hereinafter named, agree as follows:
ARTICLE I - SCOPE OF THE WORK
The Contractor hereby agrees to furnish all of the materials and all of the
equipment and labor necessary, and to perform all of the work shown on the'plans described in
the specifications for the project entitled:
AUGUSTA WATER SYSTEM IMPROVEMENTS
CHLORINE BOOSTER STATION
BOND PROJECT NO. 10110
and in accordance with the requirements and provisions of the Contract Documents as defined in
the General and Special Conditions hereto attached which are hereby made a part of this
agreement.
ARTICLE II - TIME OF COMPLETION -- LIOUIDATED DAMAGES
The work to be performed under this Contract shall be commenced within ten QQ)
calendar days after the date of written notice by the Owner to the Contractor to proceed. The
work shall be completed within One Hundred Eighty (180) calendar days after the date of such
notice and with such extensions of time as are provided for in the General Conditions.
It is hereby understood and mutually agreed, by and between the Contractor and
the Owner, that the date of beginning, rate of progress and the time for completion of the work to
be done hereunder are ESSENTIAL CONDmONS of this Contract. Contractor agrees that said
work shall be prosecuted regularly, diligently, and uninterruptedly at such rate of progress as will
insure full completion there of within the time specified. It is expressly understood and agreed
by and between the Contractor and the Owner, that the time for the completion of the work
described herein is a reasonable time for the completion of the same, taking into consideration
the average climatic range and construction conditions prevailing in this locality.
IF THE CONTRACTOR SHALL NEGLECT, FAIL OR REFUSE TO
COMPLETE THE WORK WITHIN THE TIME HEREIN SPECIFIED, then the Contractor does
hereby agree, as a part of the consideration for the awarding of this contract, to pay to the Owner
the sum of Two Hundred Dollars ($200.00), not as a penalty, but as liquidated damages for such
breach of contract as hereinafter set forth, for each and every calendar day that the Contractor
shall be in default after the time stipulated in the contract for completing the work.
A-I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
The said amount is fixed and agreed upon by and between the Contractor and the
Owner because of the impracticability and extreme difficulty of fixing and ascertaining the actual
damages the Owner would, in such event, sustain, and said amounts shall be retained from time to
time by the Owner from current periodical estimates.
It is further agreed that time is of the essence of each and every portion of this
contract and the specifications wherein a definite portion and certain length of time is fixed for the
performance of any act whatsoever; and where under the contract an additional time is allowed
for the completion of any work, the new time limit fixed by extension shall be the essence of the
Contract.
ARTICLE III - PAYMENT
(A) THE CONTRACT SUM
The Owner shall pay to the Contractor for the performance of the Contract the
amount as stated in the Proposal and Schedule of Items. No variations shall be made in the
amount except as set forth in the specifications attached hereto.
(B) PROGRESS PAYMENTS
On no later than the fifth day of every month, the Contractor shall submit to the
Owner an estimate covering the percentage of the total amount of the Contract which has been
completed from the start of the job up to and including the last working day of the preceding
month, together with such supporting evidence as may be required by the Owner and/or the
Engineer. This estimate shall include only quantities in place and at the unit prices set forth in the
bid schedule.
On the vendor run following approval of the invoice for payment, the Owner shall
after deducting previous payments made, pay to the Contractor 90% of the amount of the
estimate on units accepted in place. The 10% retained percentage may be held by the Owner
until the final completion and acceptance of all work under the Contract.
ARTICLE IV - ACCEPTANCE AND FINAL PAYMENT
(A) Upon receipt of written notice that the work is ready for final inspection
and acceptance, the Engineer shall within 10 days make such inspection, and when he finds the
work acceptable under the Contract and the Contract fully performed he will promptly issue a
final certificate, over his own signature, stating that the work required by the Contract has been
completed and is accepted by him under the terms and conditions thereof, and the entire balance
found to be due the Contractor, including the retained percentage, shall be paid to the Contractor
by the Owner within 15 days after the date of said final certificate.
(B) Before final payment is due the Contractor shall submit evidence
satisfactory to the Engineer that all payrolls, material bills, and other indebtedness connected with
the work have been paid, except that in case of disputed indebtedness of liens of evidence of
payment of all such disputed amounts when adjudicated in cases where such payment has not
already been guaranteed by surety bond.
A-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
(C) The making and acceptance of the final payment shall constitute a waiver of
all claims by the Owner other than those arising from unsettled liens, from faulty work appearing
within 12 months after final payment, from requirements of the specifications, or from
manufacturers' guarantees. It shall also constitute a waiver of all claims by the Contractor except
those previously made and still unsettled.
(D) If after the work has been substantially completed, full completion thereof
is materially delayed through no fault of the Contractor, and the Engineer, so certifies, the Owner
shall upon certification of the Engineer, and without terminating the Contract, make payment of
the balance due for that portion of the work fully completed and accepted.
Each payment shall be made under the terms and conditions governIng final
payment, except that it shall not constitute a waiver of claims.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement in
three (3) counterparts, each of which shall be deemed an original, in the year and day first
mentioned above.
(SEAL)
/
ATTES~
iif7~
1 rk
'i/a.tf tJ. '7J1t>>ar.: .d~
Witness
(SEAL)
CONTRACTOR:
By ~~it~~
Address~. 0 ~o')(... 1 ~ () {p
ATTEST:
Secretary
~ iJ.@~
Witness
~auaW"\\'\a..k I ~ alt.!-O~
A-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION PB
PERFORMANCE BOND
(NOTE:
THIS BOND IS ISSUED SIMULTANEOUSLY WITH PAYMENT BOND ON
PAGE PB-3, IN FAVOR OF THE OWNER CONDITIONED FOR THE
PAYMENT OF LABOR AND MATERIAL.)
KNOW ALL MEN BY THESE PRESENTS:
That
as Principal,
hereinafter called Contractor, and
a corporation organized and existing under. the laws of the State of
with its principal office in the City of
, State of
, as
Surety, hereinafter called Surety, are held and firmly bound unto AUGUSTA, GEORGIA BY
AND THROUGH THE AUGUSTA-RICHMOND COUNTY COMMISSIQN as Obligee,
hereinafter called the Owner, in the penal amount of " Dollars
($ ) for the payment whereof Contractor and Surety bind' themselves, their heirs,
executors, administrators, successors, and assigns, jointly and severally, firmly by these presents
for the faithful performance of a certain written agreement.
WHEREAS, Contractor lias by said written agreement dated
entered into a contract with Owner for the c'onstruction of AUGUSTA WATER SYSTEM
IMPROVEMENTS, CHLORINE BOOSTER STATION, BOND PROJECT NO. 10110,
Augusta, Georgia, in accordance with the drawings and specifications issued by the Augusta
Utilities Department and the Augusta-Richmond County Commission, which contract is by
reference made a part hereof, and is hereinafter referred to as the CONTRACT.
NOW, THEREFORE, the condition of this obligation is such that, if Contractor
shall promptly and faithfully perform said CONTRACT, then this obligation shall be null and void;
otherwise it shall remain in full force and effect.
The Surety hereby waives notice of any alteration or extension of time made by the
"Owner.
Whenever Contractor shall be, and declared by Owner to be in default under the
CONTRACT, the Owner having performed Owner's obligations thereunder, the Surety may
promptly remedy the default, or shall promptly
(1) Complete the CONTRACT in accordance with its terms and conditions, or
(2) Obtain a bid or bids for completing the Contract in accordance with its terms and
conditions, and upon determination by Surety of the lowest responsible bidder, or,
if the Owner elects, upon determination by the Owner and the Surety jointly of the
lowest responsible bidder, arrange for a contract between such bidder and Owner,
and make available as Work progresses (even though there should be a default or a
succession of defaults under the' contract or contracts of completion arranged
PB-l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
under this paragraph) sufficient funds to pay the cost of completion less the
balance of the contract price; but not exceeding, including other costs and damages
for which the Surety may be liable hereunder, the amount set forth in the first
paragraph hereof. The term "balance of the contract price, II as used in this
paragraph, shall mean the total amount payable by Owner to Contractor under the
Contract and any amendments thereto, less the amount properly paid by Owner to
Contractor.
Any suit under this bond must be instituted before the expiration of two (2) years
from the date on which final payment under the CONTRACT falls due.
No right of action shall accrue on this bond to or for the use of any person or
corporation other than the Owner named herein or the heirs, executors, administrators or
successors of the Owner.
Signed and sealed this
day of
A.D. 20
Witness
(Seal)
(Contractor)
Attest
(Seal)
(Title)
By
Witness
(Seal)
(Surety)
Attest
(Seal)
(Title)
By
PB-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION PB
LABOR AND MATERIAL PAYMENT BOND
(NOTE:
THIS BOND IS ISSUED SIMULTANEOUSLY WITH PERFORMANCE
BOND ON PAGE PB-l, IN FAVOR OF THE OWNER CONDITIONED FOR
THE PERFORMANCE OF THE WORK.)
KNOW ALL MEN BY THESE PRESENTS:
That
as Principal,
hereinafter called Contractor, and
a corporation organized and existing under the laws of the State of
with its principal office in the City of
, State of
, as
Surety, hereinafter called Surety, are held and firmly bound unto AUGUSTA, GEORGIA BY
AND THROUGH THE AUGUSTA-RICHMOND COUNTY COMMISSION, as Obligee,
hereinafter called the Owner, for the use and benefit of claimants as hereinbelow defined in the
amount of
Dollars ($ ) for the payment
whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors,
and assigns, jointly and severally, firmly by these presents.
WHEREAS, Contractor has by written agreement dated
entered into a contract with Owner for the construction of AUGUSTA WATER SYSTEM
IMPROVEMENTS, CHLORINE BOOSTER STATION, BOND PROJECT NO. 10110, in
accordance with drawings and specifications issued by the Augusta Utilities Department and
Augusta-Richmond County Commission, which contract is by reference made a part hereof, and is
hereinafter referred to as the CONTRACT.
NOW, THEREFORE, the condition of this obligation is such that, if the
Contractor shall promptly make payment to all claimants as hereinafter defined, for all labor and
material used or reasonably required to use in the performance of the CONTRACT, then this
obligation shall be void; otherwise it shall remain in full force and effect, subject, however, to the
following conditions:
(1) A claimant is defined as one having a direct contract with the Contractor or with a
subcontractor of the Contractor for labor, material, or both, used or reasonably
required for use in the performance of the contract, labor and material being
construed as to include that part of water, gas, power, light, heat, oil, gasoline,
telephone service or rental of equipment directly applicable to the CONTRACT.
(2) The above named Contractor and Surety hereby jointly and severally agree with
the Owner that every claimant as herein defined, who has not been paid in full
before the expiration of a period of ninety (90) days after the date on which the
PB-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
(3)
(4)
last of such claimant's work or labor was done or performed, or materials were
furnished by such claimant, may sue on this bond for the use of such claimant,
prosecute the suit to final judgement for such sum or sums as may be justly due
claimant, and have execution thereon. The Owner shall not be liable for the
payment of any costs or expenses of any such suit.
No suit or action shall be commenced hereunder by any claimant,
(a) Unless claimant, other than one having a direct contract with the
Contractor, shall have given written notice to any two of the following:
The Contractor, the Owner, or the Surety above named, within ninety (90)
days after such claimant did or performed the last of the work or labor, or
furnished the last of the materials for which said claim is made, stating with
substantial accuracy the amount claimed and the name of the party to
whom the materials were furnished, or for whom the work or labor was
done or performed. Such notice shall be served by mailing the same by
registered mail or certified mail, postage prepaid, in an envelope addressed
to the Contractor, Owner or Surety, at any place where an office regularly
maintained for the transaction of business, or served in any manner in
which legal process may be served in the state in which the aforesaid
project is located, save that such service need not be made by a public
officer.
(b) After the expiration of one (1) year following the date on which Contractor
ceased work on said CONTRACT, it being understood, however, that if
any limitation embodied in this bond is prohibited by any law controlling
the construction hereof, such limitation shall be deemed to be amended so
as to be equal to the minimum period of limitation permitted by such law.
(c) Other than in a state court of competent jurisdiction in and for the county
or other political subdivision of the state in which the project, or any part
thereof, is situated, or in the United States District Court for the district in
which the project, or any part thereof, is situated, and not elsewhere.
The amount of this bond shall be reduced by and to the extent of any payment or
payments made in good faith hereunder, inclusive of the payment by Surety of
mechanics' liens which may be filed of record against said improvement, whether
or not claim for the amount of such lien be presented under and against this bond.
PB-4
I
I
I
I
SECTION NP
NOTICE TO PROCEED
~, CUST,
.:
e --c. NOTICE TO PROCEED
DATE:
TO:
I
I
I
Attn:
Address
City, State
PROJECT: Augusta Water System Improvements Chlorine Booster Station PROJECT NO: 10110
I
You are hereby notified to commence WORK in accordance with the Agreement dated
I
I
on or before
, and you are to complete the WORK within
Ninety (90)
consecutive calendar days thereafter. The date of completion of all WORK is therefore
I
I
Very truly yours,
Augusta Program Management Team
Project Engineer
I
I
I
I
Receipt of this NOTICE TO PROCEED is hereby acknowledged
This, the
day of
, 2004
Contractor:
By:
Title
Please sign and return one copy of this Notice to Proceed Acknowledgment to:
I
I
I
CH2M Hill (Attn: Program Management)
360 Bav Street: Suite 100
AUl!Usta, GA 30901
NP-l
I
I
I ARTICLE
I -01.
-02.
-03.
I -04.
-05.
-06.
I -07.
-08.
I -09.
-10.
-11.
I -12.
-13.
I -14.
-15.
-16.
I -17.
I
I
I
I
I
I
I
I
I
SECTION GC-O
INDEX TO GENERAL CONDITIONS
Definitions
Preliminary Matters
Contract Documents: Intent, Amending, Reuse
Availability of Lands, Physical Conditions, Reference Points
Bonds and Insurance
Contractor's Responsibilities
Other Work
Owner's Responsibilities
Professional's Status During Construction
Changes In The Work
Change of Contract Price
Change of Contract Time
Warranty and Guarantee; Tests and Inspections: Correction, Removal or
Acceptance of Defective Work
Payments to Contractor and Completion
Suspension of Work and Termination
Dispute Resolution
Miscellaneous
GC-o
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
GENERAL CONDITIONS
ARTICLE I--DEFINITIONS
Wherever used in these General Conditions or in the other Contract Documents the following
terms have the meanings indicated which are applicable to both the singular and plural thereof:
Addenda-Any changes, revisions of clarifications of the Contract Documents which have been
duly issued by COUNTY to prospective Bidders prior to the time of opening of Bids.
Agreement- The written agreement between OWNER and CONTRACTOR covering the Work to
be performed: other Contract Documents are attached to the Agreement and made a part thereof
as provided therein.
Application for Pcryment-The form accepted by PROFESSIONAL which is to be used by
CONTRACTOR in requesting progress or final payments and which is to include such supporting
documentation as is required by the Contract Documents.
Bid-The offer or proposal of the bidder submitted on the prescribed form setting forth the price(s)
for the Work to be performed.
Bonds-Bid, performance and payment bonds and other instruments of security furnished by
CONTRACTOR and its Surety in accordance with the Contract Documents.
Change Order--A document recommended by PROFESSIONAL, which is signed by
CONTRACTOR and OWNER and authorizes an addition, deletion or revision in the Work, or an
adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the
Agreement.
Contract Documents-The Agreement, Addenda (which pertain to the Contract Documents),
CONTRACTOR's Bid (including documentation accompanying the Bid and any post-Bid
documentation submitted prior to the Notice of Award) when attached as an exhibit to the
Agreement, the Bonds, these General Conditions, the Supplementary Conditions, the Plans,
Specifications and the Drawings as the same are more specifically identified in the Agreement,
Certificates of Insurance, Notice of Award, and Change Order duly delivered after execution of
Contract. together with all amendments, modifications and supplements issued pursuant to
paragraphs 3.4 and 3.5 or after the Effective Date of the Agreement.
Contract Price-The moneys payable by OWNER to CONTRACTOR under the Contract
Documents as stated in the Agreement (subject to the provisions of paragraph 11.9.1 in the case
of Unit Price Work).
Contract Time-The number of days (computed as provided in paragraph 17.2) or the date stated
in the Agreement for the completion of the Work.
CONTRACTOR-The person, firm or corporation with whom OWNER has entered into the
Agreement.
GC-l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
COUNlY-Richmond County, Georgia, or Augusta, Georgia, political subdivisions of the State of
Georgia, the Augusta-Richmond County Commission, and its authorized designees, agents, or
employees.
Day-Either a working day or calendar day as specified in the bid documents. If a calendar day
shall fall on a legal holiday that day will be omitted from the computation, Legal Holidays: New
Year's Day, Martin Luther King Day, Memorial Day, 4th of July, Labor Day, Veterans Day,
Thanksgiving Day and the following Friday, and Christmas Day.
Defective-An adjective which when modifying the word Work refers to Work that is
unsatisfactory, faulty or deficient, or does not conform to the Contract Documents, or does not
meet the requirements of any inspection, reference standard, test or approval referred to in the
Contract Documents, or has been damaged prior to PROFESSIONAL's recommendation of final
payment, unless responsibility for the protection thereof has been assumed by OWNER at
Substantial Completion in accordance with paragraph 14.8 or 14.10).
Drawings- The drawings which show the character and scope of the Work to be performed and
which have been prepared or approved by PROFESSIONAL and are referred to in the Contract
Documents.
Effective Date of the Agreement-The date indicated in the Agreement on which it becomes
effective, but if no such date is indicated it means the date on which the Agreement is signed by
the Mayor of the Augusta, Georgia.
Field Order-A written order issued by PROFESSIONAL that modifies Drawings and
Specifications, but which does not involve a change in the Contract Price or the Contract Time.
General Requirements-Sections of Division I of the Specifications.
Laws and Regulations: Laws or Regulations-Laws. rules, regulations, ordinances, codes and/or
orders.
Notice of Award-The written notice by OWNER to the apparent successful bidder stating that
upon compliance by the apparent successful bidder with the conditions precedent enumerated
therein, within the time specified, OWNER will sign and deliver the Agreement.
Notice to Proceed-A written notice given by OWNER to CONTRACTOR (with a copy to
PROFESSIONAL) fixing the date on which the Contract Time will commence to run and on
which CONTRACTOR shall start to perform CONTRACTOR'S obligations under the Contract
Documents.
OWNER- Augusta, Georgia, and the Augusta-Richmond County Commission.
Partial Utilization-Placing a portion of the Work in service for the purpose for which it is
intended for a related purpose) before reaching Substantial Completion for all the Work.
Professional- The Architectural/Engineering firm or individual or in-house licensed person
designated to perform the design and/or resident engineer services for the Work.
GC-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Project- The total construction of which the Work to be provided under the Contract Documents
may be the whole, or a part as indicated elsewhere in the Contract Documents.
Project Area-The area within which are the specified Contract Limits of the improvements
contemplated to be constructed in whole or in part under this Contract.
Project Manager-The professional in charge, serving COUNTY with architectural or engineering
services, his successor, or any other person or persons, employed by said COUNTY, for the
purpose of directing or having in charge the work embraced in this Contract.
Resident Project Representative-The authorized representative of PROFESSIONAL who IS
assigned to the site or any part thereof.
Shop Drawings-All drawings, diagrams, illustrations, schedules and other data which are
specifically prepared by or for CONTRACTOR to illustrate some portion of the Work and all
illustrations, brochures, standard schedules, performance charts, instructions, diagrams and other
information prepared by a Supplier and submitted by CONTRACTOR to illustrate material or
equipment for some portion of the Work.'
Specifications- Those portions of the Contract Documents consIstmg of written technical
descriptions of materials, equipment, construction systems, standards and workmanship as applied
to the Work and certain administrative details applicable thereto.
Subcontractor-An individual, firm or corporation having a direct contract with CONTRACTOR
or with any other SUBCONTRACTOR for the performance of a part of the Work at the site.
Substantial Completion- The Work (or a specified part thereof) has progressed to the point where,
in the opinion of PROFESSIONAL as evidenced by PROFESSIONAL's definitive certificate of
Substantial Completion, it is sufficiently complete, in accordance with the Contract Documents,
so that the Work (or specified part) can be used for the purposes for which it is intended, or if
there be no such certificate issued, when final payment is due in accordance with paragraph 14.13.
The terms "substantially complete II and "substantially completed II as applied to any Work refer to
Substantial Completion thereof. ,
Supplementary Conditions-The part of the Contract Documents which amends or supplements
these General Conditions.
Supplier-A manufacturer, fabricator, supplier, distributor, materialman or vendor.
Underground Facilities-All pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks,
tunnels or other such facilities or attachments, and any encasement containing such facilities which
have been installed underground to furnish any of the following services or materials, electricity,
gases, steam, liquid petroleum products, telephone or other communications, cable television,
sewage and drainage removal, traffic or other control systems or water.
Unit Price Work-Work to be paid for on the basis of unit prices.
GC-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Work- The entire completed construction or the various separately identifiable parts thereof
required to be furnished under the Contract Documents. Work is the result of performing
services, furnishing labor and furnishing and incorporating materials and equipment into the
construction, and furnishing documents, all as required by the Contract Documents.
Work Directive Change-A written directive to CONTRACTOR, issued on or after the Effective
Date of the Agreement and signed by OWNER and recommended by PROFESSIONAL,
ordering an addition, deletion or revision in the Work, or responding to differing or unforeseen
physical conditions under which the Work is to be performed as provided in paragraph 4.2 or 4.3
or to emergencies under paragraph 6.22. A Work Directive Change may not change the Contract
Price or the Contract Time, but is evidence that the parties expect that the change directed or
documented by a Work Directive Change will be incorporated in a subsequently issued Change
Order following negotiations by the parties as to its effect, if any, on the Contract Price or
Contract Time as provided in Article 10.
Written Amendment-A written amendment of the Contract Documents, signed by OWNER and
CONTRACTOR on or after the Effective Date of the Agreement and normally dealing with the
non-engineering or nontechnical rather than strictly Work-related aspects of the Contract
Documents.
GC-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 2-PRELIMINARY MATTERS
Delivery of Bonds:
2.1. When CONTRACTOR delivers the executed Agreements to OWNER,
CONTRACTOR shall also deliver to OWNER such Bonds as CONTRACTOR may be required
to furnish in accordance with these Contract Documents.
Copies of Documents:
,-
2.2. After the award of the Contract, OWNER shall furnish CONTRACTOR, at no cost,
one (1) complete set of the Contract Documents for execution of the work. Additional sets of the
project manual and drawings and/or individual pages or sheets of the project manual or drawings
will be furnished by COUNTY upon CONTRACTOR's request and at CONTRACTOR's
expense, which will be OWNER's standard charges for printing and reproduction.
Commencement of Contract Time, Notice to Proceed:
2.3. The Contract Time shall commence as established in the Notice to Proceed. A Notice
to Proceed may be given at any time after the Effective Date of the Contract.
Starting the Project:
2.4. CONTRACTOR shall begin the Work on the date the Contract Time commences.
No Work shall be done prior to the date on which the Contract Time commences. Any Work
performed by CONTRACTOR prior to date on which Contract Time commences shall be at the
sole risk of CONTRACTOR.
Before Starting Construction:
2.5. Before undertaking each part of the Work. CONTRACTOR shall carefully study and
compare the Contract Documents and check and verify pertinent figures shown thereon and all
applicable field measurements. CONTRACTOR shall promptly report in writing to
PROFESSIONAL any conflict, error, ambiguity, or discrepancy which CONTRACTOR may
discover and shall obtain a written interpretation or clarification from PROFESSIONAL before
proceeding with any Work affected thereby. CONTRACTOR shall be liable to OWNER for
failure to report any conflict, effort, ambiguity or discrepancy in the Contract Documents, if
CONTRACTOR knew or reasonably should have known thereof
2.6. Within ten days after the Effective Date of the Agreement unless otherwise specified
in the General Requirements), CONTRACTOR shall submit to PROFESSIONAL AND
PROJECT MANAGER for review:
2.6.1. an estimated progress schedule indicating the starting and completion dates of the
various stages of the Work:
2.6.2. a preliminary schedule of Shop Drawing and Sample submissions: and
GC-5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
2.6.3. a preliminary schedule of values for all of the Work which will include quantities
and prices of items aggregating the Contract Price and will subdivide the Work into component
parts in sufficient detail to serve as the basis for progress payments during construction. Such
prices will include an appropriate amount of overhead and profit applicable to each item of Work
which will be confirmed in writing by CONTRACTOR at the time of submission.
2.7. Before any Work at the site is started, CONTRACTOR shall deliver to OWNER,
with copies to each additional insured identified in the Supplementary Conditions, an original
policy or certified copies of each insurance policy (and other evidence of insurance which
COUNTY may reasonably request) which CONTRACTOR is required to purchase and maintain
in accordance with Article 5.
Pre-construction Conference:
2.8. Before any Work at the site is started, a conference attended by CONTRACTOR,
Project Manager, Professional and others as appropriate will be held to establish a working
understanding among the parties as to the Work and to discuss the schedules referred to in 2.6,
procedures for handling Shop Drawings and other submittals, processing applications for payment
and maintaining required records.
Finalizing Schedules:
2.9. At least ten days before submission of the first Application for Payment a conference
attended by CONTRACTOR, PROFESSIONAL and Project Manager and others as appropriate
will be held to finalize the schedules submitted in accordance with paragraph 2.6.
CONTRACTOR shall have an additional ten (10) calendar days to make corrections and
adjustments and to complete and resubmit the schedules. No progress payment shall be made to
CONTRACTOR until the schedules are submitted to and acceptable to Project Manager and
PROFESSIONAL as provided below. The finalized progress schedule will be acceptable to
Project Manager and PROFESSlONAL as providing an orderly progression of the Work to
completion within any specified Milestones and the Contract Time, but such acceptance will
neither impose on PROFESSIONAL responsibility for the sequencing, scheduling or progress of
the Work nor interfere with or relieve CONTRACTOR from full responsibility therefor, The
finalized schedule of Shop Drawing submissions and Sample submissions will be acceptable to
PROFESSIONAL as providing a workable arrangement for reviewing and processing the
submissions. CONTRACTOR's schedule of values shall be approved by PROFESSIONAL as to
form and substance.
CONTRACTOR, in addition to preparing an initially acceptable schedule, shall be
responsible for maintaining the schedule, including updating schedule. Schedule updates shall
include progression of work as compared to scheduled progress on work. Schedule updates shall
accompany each pay request.
GC-6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 3-CONTRACT DOCUMENTS; INTENT,
AMENDING, REUSE
Intent:
3.1. The Contract Documents comprise the entire agreement between OWNER and
CONTRACTOR concerning the Work. The Contract Documents are complementary: what is
called for by one is as binding as if called for by all. The Contract Documents will be construed in
accordance with the law of the State of Georgia.
3 .2. It is the intent of the Contract Documents to describe a functionally complete Proj ect
(or part thereot) to be constructed in accordance with the Contract Documents. Any Work,
materials or equipment that may reasonably be inferred from the Contract Documents or from
prevailing custom or trade usage as being required to produce the intended result will be supplied
whether or not specifically called for. When words or phrases which have a well-known technical
or construction industry or trade meaning are used to describe Work, materials or equipment,
such words shall be interpreted in accordance with that meaning.
3.3. Except as otherwise specifically stated in the Contract Documents or as may be
provided by amendment or supplement thereto issued by one of the methods indicated in 3.6 or
3.7, the provisions of the Contract Documents shall take precedence in resolving any conflict,
error, ambiguity or discrepancy between the provisions of the Contract Documents and the
provisions of any such standard, specification, manual, code or instruction (whether or not
specifically incorporated by reference in the Contract Documents ) and the provisions of any such
Laws or Regulations application to the performance of the Work (unless such an interpretation of
the provisions of the Contract Documents would result in violation of such Law or Regulation).
Clarifications and interpretations of the Contract Documents shall be issued by PROFESSIONAL
as provided in paragraph 9.4.
3.4. Reference to standards, specifications, manuals or codes of any technical society,
organization or association, or to the Laws or Regulations of any governmental authority,
whether such reference be specific or by implication, shall mean the latest standard, specification,
manual, code or Laws or Regulations in effect at the time of opening of Bids (or, on the Effective
Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in
the Contract Documents.
3.5. If, during the performance of the Work, CONTRACTOR discovers any conflict,
error, ambiguity or discrepancy within the Contract Documents or between the Contract
Documents and any provision of any such Law or Regulation applicable to the performance of the
Work or of any such standard, specification, manual or code or of any instruction of any Supplier
referred to in 6.7, CONTRACTOR shall so report to PROFESSIONAL in writing at once and
before proceeding with the Work affected thereby shall obtain a written interpretation or
clarification from PROFESSIONAL; however, CONTRACTOR shall not be liable to OWNER
or PROFESSIONAL for failure to report any conflict, error ambiguity or discrepancy in the
Contract Documents unless CONTRACTOR had actual knowledge thereof or should reasonablyshave known thereof.
GC-7
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Amending and Supplementing Contract Documents:
3 .6. The Contract Documents may be amended to provide for additions. deletions and
revisions in the Work or to modify the terms and conditions thereof in one or more of the
following ways:
3.6.1. a formal Written Amendment,
3.6.2. a Change Order (pursuant to paragraph 10.3), or
3.6.3. a Work Directive Change (pursuant to paragraph lOA).
As indicated in paragraphs 11.2 and 12.1, Contract Price and Contract Time may only be changed
by a Change Order or a Written Amendment.
3.7. In addition. the requirements of the Contract Documents may be supplemented, and
minor variations and deviations in the Work may be authorized, in one or more of the following
ways:
3.7.1. a Field Order (pursuant to paragraph 9.5).
3.7.2. PROFESSIONAL's approval ofa Shop Drawing or sample (pursuant to paragraphs
6.24 and 6.26), or
3.7.3. PROFESSIONAL's written interpretation or certification (pursuant to paragraph
9A).
Reuse of documents:
3.8. Neither CONTRACTOR nor any Subcontractor or Supplier or other person or
organization performing or furnishing any of the Work under a direct or indirect contract with
OWNER shall have or acquire any title to or ownership rights in any of the Drawings,
Specifications or other documents (or copies oil any thereof) prepared by or bearing the seal of
PROFESSIONAL or PROFESSIONAL's consultant; and they shall not reuse such Drawings,
Specifications or other documents (or copies of any thereof) on extensions of the Project or any
other project without written consent of OWNER and PROFESSIONAL and specific written
verification or adaptation by PROFESSIONAL.
GC-8
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 4-A V AILABILITY OF LANDS, PHYSICAL
CONDITIONS; REFERENCE POINTS
Availability of Lands:
4.1. OWNER shall furnish as indicated in the Contract Documents, the lands upon which
the Work is to be performed, rights-of-way and easements for access thereto, and such other
lands which are designated for the use of CONTRACTOR. Necessary easements or rights-of-
way will be obtained and expenses will be borne by OWNER. If CONTRACTOR and OWNER
are unable to agree on entitlement to or the amount or extent of any adjustments in the Contract
Price or the Contract Times as a result of any delay in OWNER's furnishing these lands, rights-of-
way or easements, the CONTRACTOR may make a claim therefor as provided in Articles 11 and
12. The CONTRACTOR shall provide for all additional lands and access thereto that may be
required for temporary construction facilities or storage of materials and equipment.
Physical Conditions:
4.2.1. Explorations and Reports: Reference is made to the Supplementary Conditions for
identification of those reports of explorations and tests of subsurface conditions at or contiguous
to the site that have been utilized in preparing the Contract Documents, and those drawings of
physical conditions in or relating to existing surface or subsurface structures at or contiguous to
the site (except Underground Facilities) that have been utilized in preparing the Contract
Documents.
4.2.2. CONTRACTOR may rely upon the general accuracy of the "technical data"
contained in such reports and drawings. Such "technical data" is identified in the Supplementary
Conditions, Except for such reliance on such "technical data, II CONTRACTOR may not rely upon
or make any claim against OWNER, PROFESSIONAL, or any of PROFESSIONAL's
Consultants with respect to:
4.2.2.1. the completeness of such reports and drawings for CONTRACTOR's purposes,
including, but not limited to, any aspects of the means, methods, techniques, sequences and
procedures of construction to be employed by CONTRACTOR and safety precautions and
programs incident thereto, or
4.2.2.2. other data, interpretations, opinions and information contained in such reports or
shown or indicated in such drawings, or
4.2.2.3. any CONTRACTOR interpretation of or conclusion drawn from any "technical
data" or any such data, interpretations, opinions or information.
4.2.3. If conditions are encountered, excluding existing utilities, at the site which are (1)
subsurface or otherwise concealed physical conditions which differ materially from those indicated
in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ
materially from those ordinarily found to exist and generally recognized as inherent in
construction activities of the character provided for in the Contract Documents, then
GC-9
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
CONTRACTOR shall give COUNTY notice thereof promptly before conditions are disturbed and
in no event later than 48 hours after first observance of the conditions.
4.2.4. The Project Manager and PROFESSIONAL shall promptly investigate such
conditions, and, if they differ materially and cause an increase or decrease in CONTRACTOR's
cost of, or time required for, performance of any part of the Work, the Project Manager and
PROFESSIONAL shall recommend an equitable adjustment in the Contract Price or Contract
Time, or both. If the Project Manager and PROFESSIONAL determines that the conditions at
the Site are not materially different from those indicated in the Contract Documents or are not
materially different from those ordinarily found and that no change in the terms of the Contract is
justified, the PROFESSIONAL shall notify CONTRACTOR of the determination in writing. The
Work shall be performed after direction is provided by the PROFESSIONAL.
Physical Conditions-Underground Facilities:
4.3.1. Shown or Indicated: The information and data shown or indicated in the Contract
Documents with respect to existing Underground Facilities at or contiguous to the site is based on
information and data furnished to OWNER or PROFESSIONAL by OWNERS of such
Underground Facilities or by others. Unless it is otherwise expressly provided in the
Supplementary Conditions:
4.3.1.1. OWNER and PROFESSIONAL shall not be responsible for the accuracy or
completeness of any such information or data: and
4.3.1.2. The cost of all of the following will be included in the Contract Price and
CONTRACTOR shall have full responsibility for reviewing and checking all such information and
data. for locating all Underground Facilities shown or indicated in the Contract Documents. for
coordination of the Work with the OWNERS of such Underground Facilities during construction.
for the safety and protection thereof as provided in paragraph 6.20 and repairing any damage
thereto resulting from the Work, the cost of all of which will be considered as having been
included in the Contract Price.
4.3.2. Not Shown or Indicated. If an Underground Facility is uncovered or revealed at or
contiguous to the site which was not shown or indicated in the Contract Documents and which
CONTRACTOR could not reasonably have been expected to be aware of, CONTRACTOR
shall, promptly after becoming aware thereof and before performing any Work affected thereby
except in an emergency as permitted by paragraph 6.22), identify the owner of such Underground
Facility and give written notice thereof to that owner and to OWNER and PROFESSIONAL.
PROFESSIONAL will promptly review the Underground Facility to determine he extent to
which the Contract Documents should be modified to reflect and document the consequences of
the existence of the Underground Facility, and the Contract Documents will be amended or
supplemented to the extent necessary. During such time, CONTRACTOR shall be responsible
for the safety and protection of such Underground Facility as provided in paragraph 6.20.
CONTRACTOR shall be allowed an increase in the Contract Price or an extension of the
Contract Time, or both, to the extent that they are attributable to the existence of any
Underground Facility that was not shown or indicated in the Contract Documents and which
CONTRACTOR could not reasonably have been expected to be aware of. If the parties are
GC-I0
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
unable to agree as to the amount or length thereof, CONTRACTOR may make a claim therefor
as provided in Articles 11 and 12.
Reference Points:
4.4. OWNER shall provide Engineering surveys to establish reference points for
construction which in PROFESSIONAL's judgment are necessary to enable CONTRACTOR to
proceed with the Work. CONTRACTOR shall be responsible for laying out the Work (unless
otherwise specified in the General Requirements), shall protect and preserve the established
reference points and shall make no changes or relocations without the prior written approval of
OWNER. CONTRACTOR shall report to PROFESSIONAL whenever any reference point is
lost or destroyed or requires relocation because of necessary changes in grades or locations, and
shall be responsible for the accurate replacement or relocation of such reference points by
professionally qualified personnel.
Asbestos, PCBs, Petroleum, Hazardous Waste or Radioactive Material:
4.5 COUNTY shall be responsible for any Asbestos, PCBs, Petroleum, Hazardous Waste
or Radioactive Material uncovered or revealed at the site which was not shown or indicated in
Drawings or Specifications or identified in the Contract Documents to be within the scope of the
Work and which may present a substantial danger to persons or property exposed thereto in
connection with the Work at the site. COUNTY shall not be responsible for any such materials
brought to the site by CONTRACTOR, Subcontractor, Suppliers or anyone else for whom
CONTRACTOR is responsible.
4.6 CONTRACTOR shall immediately: (i) stop all work in connection with such
hazardous condition and in any area affected thereby (except in an emergency as required by
6.22), and (ii) notify OWNER and PROFESSIONAL (and thereafter confirm such notice in
writing). OWNER shall promptly consult with PROFESSIONAL concerning the necessity for
OWNER to retain a qualified expert to evaluate such hazardous condition or take corrective
action, if any, CONTRACTOR shall not be required to resume Work in connection with such
hazardous condition or in any such affected area until after OWNER has obtained any required
permits related thereto and delivered to CONTRACTOR special written notice (i) specifying that
such condition and any affected area is or has been rendered safe for the resumption of Work, or
(ii) specifying any special conditions under which such Work may be resumed safely. If OWNER
and CONTRACTOR cannot agree as to entitlement to or the amount or extent of an adjustment,
if any, in Contract Price or Contract Times as a result of such Work stoppage or such special
conditions under which Work is agreed by CONTRACTOR to be resumed, either party may make
a claim therefor as provided in Articles 11 and 12.
4.7 If after receipt of such special written notice, CONTRACTOR does not agree to
resume such Work based on a reasonable belief it is unsafe, or does not agree to resume such
Work under such special conditions, then CONTRACTOR may order such portion of the Work
that is in connection with such hazardous conditions or in such affected area to be deleted from
the Work. If COUNTY and CONTRACTOR cannot agree as to entitlement to or the amount or
extent of an adjustment, if any, in Contract Price or Contract Times as a result of deleting such
portion of the Work, then either party may make a claim therefor as provided in Articles 11 and
GC-ll
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 5-BONDS AND INSURANCE
Performance and Other Bonds:
5.1. CONTRACTOR shall furnish performance and payment Bonds, each in an amount at
least equal to the Contract Price as Security for the faithful performance and payment of all
CONTRACTOR's obligations under the Contract Documents. These Bonds shall remain in effect
at least until one year after the date when final payment becomes due, except as otherwise
provided by Law or Regulation or by the Contract Documents. CONTRACTOR shall also
furnish such other Bonds as are required by the Supplementary Conditions. All Bonds shall be in
the forms prescribed by Law or Reputation or by the Contract Documents and be executed by
such sureties as are named in the current list of "Companies Holding Certificates of Authority as
Acceptable Sureties on Federal Bonds, and as Acceptable Reinsuring Companies" as published in
Circular 570 (amended) by the Audit Staff Bureau of Accounts, U.S. Treasury Department. All
Bonds signed by an agent must be accompanied by a certified copy of the authority to act.
Licensed Sureties and Insurers; Certificates of Insurance
5.2.1 All bonds and insurance required by the Contract Documents to be purchased and
maintained by CONTRACTOR shall be obtained from surety or insurance companies that are duly
licensed or authorized in the State of Georgia to issue bonds or insurance policies for the limits
and coverages so required. All bonds signed by an agent must be accompanied by a certified copy
of authority to act. Such surety and insurance companies shall also meet such additional
requirements and qualifications as may be provided in the Supplementary Conditions.
5.2.2. CONTRACTOR shall deliver to OWNER, with copies to each additional insured
identified in 5.3, an original or a certified copy of the complete insurance policy for each policy
required, certificates of insurance (and other evidence of insurance requested by OWNER or any
other additional insured) which CONTRACTOR is required to purchase and maintain in
accordance with 5.3.
5.2.3. If the surety on any Bond furnished by CONTRACTOR is declared a bankrupt or
becomes insolvent or its right to do business is terminated in any state where any part of the
Project is located or it ceases to meet the requirements of paragraph 5.1. CONTRACTOR shall
within five days thereafter substitute another Bond and Surety, both of which must be acceptable
to OWNER.
CONTRACTOR's Liability Insurance:
5.3. CONTRACTOR shall purchase and maintain such comprehensive general liability and
other insurance as is appropriate for the Work being performed and furnished and as will provide
protection from claims set forth below which may arise out of or result from CONTRACTOR's
performance and furnishing of the Work and CONTRACTOR's other obligations under the
Contract Documents, whether it is to be performed or furnished by CONTRACTOR, by any
Subcontractor, by anyone directly or indirectly employed by any of them to perform or furnish any
of the Work, or by anyone for whose acts any of them may be liable:
GC-13
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 200 I
5.3.1. Claims under workers' or workmen's compensation. disability benefits and other
similar employee benefit acts;
5.3.2. Claims for damages because of bodily injury, occupational sickness or disease, or
death of CONTRACTOR's employees;
5.3.3. Claims for damages because of bodily injury, sickness or disease, or death of any
person other than CONTRACTOR's employees;
5.3.4. Claims for damages insured by personal injury liability coverage which are sustained
(a) by any person as a result of an offense directly or indirectly related to the employment of such
person by CONTRACTOR, or (b) by any other person for any other reason;
5.3 .5. Claims for damages, other than to the Work itself, because of injury to or
destruction of tangible property wherever located, including loss of use resulting therefrom;
5.3.6. Claims arising out of operation of Laws or Regulations for damages because of
bodily injury or death of any person or for damage to property; and
5.3.7. Claims for damages because of bodily injury or death of any person or property
damage arising out of the ownership, maintenance or use of any motor vehicle.
The insurance required by this paragraph 5.3 shall include the specific coverages and be written
for not less than the limits ofliability and coverages provided in the Supplementary Conditions, or
required by law, whichever is greater. The comprehensive general liability insurance shall include
completed operations insurance. All of the policies of insurance so required to be purchased and
maintained lot the certificates or other evidence thereof) shall contain a provision or endorsement
that the coverage afforded will not be canceled, materially changed or renewal refused until at
least thirty days' prior written notice has been given to OWNER, PROGRAM MANAGER, and
PROFESSIONAL by certified mail. All such insurance shall remain in effect until final payment
and at all times thereafter when CONTRACTOR may be correcting, removing or replacing
defective Work in accordance with paragraph 13.12. In addition, CONTRACTOR shall maintain
such completed operations insurance for at least two years after final payment and furnish
OWNER with evidence of continuation of such insurance at final payment and one veal thereafter.
Contractual Liability Insurance:
5.4. The comprehensive general liability insurance required by paragraph 5.3 will include
contractual liability insurance applicable to CONTRACTOR's obligations under paragraphs 6.32
and 6.33.
Owner's Liability Insurance:
5.5. OWNER shall be responsible for purchasing and maintaining OWNER's own liability
insurance, and/or Risk Retention Program, and, at OWNER's option, may purchase and maintain
such insurance as will protect OWNER against claims which may arise from operations under the
Contract Documents.
GC-14
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Property Insurance:
5.6. Unless otherwise provided in the Supplementary Conditions, OWNER shall purchase
and maintain property insurance upon the Work at the site to the full insurable value thereof
(subject to such deductible amounts as may be provided in the Supplementary Conditions or
required by Laws and Regulations). This insurance shall include the interests of OWNER,
CONTRACTOR, Subcontractors, PROGRAM MANAGER, PROFESSIONAL and
PROFESSIONAL's consultants in the Work, all of whom shall be listed as insureds or additional
insured parties, shall insure against the perils of fire and extended coverage and shall include "all
risk" insurance for physical loss and damage including theft, vandalism and malicious mischief,
collapse and water damage, and such. other perils as may be provided in the Supplementary
Conditions, and shall include damages, losses and expenses arising out of or resulting from any
insured loss or incurred in the repair or replacement of any insured property (including but not
limited to fees and charges of PROFESSIONALs, architects, attorneys and other
PROFESSIONALs). If not covered under the "all risk" insurance or otherwise provided in the
Supplementary Conditions, CONTRACTOR shall purchase and maintain similar property
insurance on portions of the Work stored on and off the site or in transit when such portions of
the Work are to be included in an Application for Payment.
5.7. OWNER shall purchase and maintain such boiler and machinery insurance or
additional property insurance as may be required by the Supplementary Conditions or Laws and
Regulations which will include the interests of OWNER, CONTRACTOR, Subcontractors,
PROFESSIONAL AND PROFESSIONAL's consultants in the Work, all of whom shall be listed
as insured or additional insured parties.
5.8. All the policies of insurance (or the certificates or other evidence thereof) required to
be purchased and maintained by OWNER in accordance with paragraphs 5.6 and 5.7 will contain
a provision or endorsement that the coverage afforded will not be canceled or materially changed
or renewal refused until at least thirty days prior written notice has been given to CONTRACTOR
by certified mail and will contain waiver provisions in accordance with paragraph of 5 .11.2.
5.9. OWNER shall not be responsible for purchasing and maintaining any property
insurance to protect the Interests of CONTRACTOR, Subcontractors or others in the Work to
the extent of any deductible amounts that are provided in the Supplementary Conditions. The risk
of loss within the deductible amount, will be borne by CONTRACTOR, Subcontractor or others
suffering any such loss and if any of them wishes property insurance coverage within the limits of
such amounts, each may purchase and maintain it at the purchaser's own expense.
5.10. If CONTRACTOR requests in writing that other special insurance be included in
the property insurance policy, OWNER shall, if possible, include such insurance, and the cost
thereof will be charged to CONTRACTOR by appropriate Change Order or Written Amendment.
Prior to commencement of the Work at the site, OWNER shall in writing advise CONTRACTOR
whether or not such other insurance has been procured by OWNER.
Waiver of Rights:
5.11.1. OWNER and CONTRACTOR waive all rights against each other for all losses
and damages caused by any of the perils covered by the policies of insurance provided in response
GC-I5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
to paragraphs 5.6 and 5.7 and other property insurance applicable to the Work, and also waive all
such rights against the Subcontractors, PROFESSIONAL, PROFESSIONAL's consultants and all
other parties named as insureds in such policies for losses and damages so caused. As required by
paragraph 6.11. each subcontract between CONTRACTOR and a Subcontractor will contain
similar waiver provisions by the Subcontractor in favor of OWNER, CONTRACTOR,
PROFESSIONAL, PROFESSIONAL's consultants and all other parties named as insureds. None
of the above waivers shall extend to the rights that any of the insured parties may have to the
proceeds of insurance held by OWNER as trustee or otherwise payable under any policy so
issued.
5.11.2. OWNER and CONTRACTOR intend that policies provided in response to
paragraphs 5.6 and 5.7 shall protect all of the parties insured and provide primary coverage for all
losses and damages caused by the perils covered thereby. Accordingly, all such policies shall con-
tain provisions to the effect that in the event of payment of any loss or damage the insurer will
have no rights of recovery against any of the parties named as insureds additional insureds, and if
the insurers require separate waiver forms to be signed by PROFESSIONAL or PROF-
ESSIONAL's consultant OWNER will obtain the same, and if such waiver forms are required of
any Subcontractor, CONTRACTOR will obtain the same.
Receipt and Application of Proceeds:
5. 12. Any insured loss under the policies of insurance required by paragraphs 5.6 and 5.7
will be adjusted with OWNER and made payable to OWNER as trustee for the insureds, as their
interests may appear, subject to the requirements of any applicable mortgage clause and of
paragraph 5.13. OWNER shall deposit in a separate account any money so received, and shall
distribute it in accordance with such agreement as the parties in interest may reach. If no other
special agreement is reached the damaged Work shall be repaired or replaced, the moneys so
received applied on account thereof and the Work and the cost thereof covered by an appropriate
Change Order or Written Amendment.
Receipt and Application of Insurance Proceeds
5.13. OWNER as trustee shall have power to adjust and settle any loss with the insurers
unless one of the parties in interest shall object in writing within fifteen days after the occurrence
of loss to OWNER's exercise of this power. If such objection be made, OWNER as trustee shall
make settlement with the insurers in accordance with such agreement as the parties in interest may
reach. If required in willing by any party in interest, OWNER as trustee shall, upon the occurrence
of an insured loss, give bond for the proper performance of such duties.
Acceptance of Insurance:
5.14. If OWNER has any objection to the coverage afforded by or other provisions of the
insurance required to be purchased and maintained by CONTRACTOR in accordance with
paragraphs 5.3 and 5.4 on the basis of its not complying with the Contract Documents, OWNER
shall notify CONTRACTOR in writing thereof within ten days of the date of delivery of such
certificates to OWNER in accordance with paragraph 2.7. If CONTRACTOR has any objection
to the coverage afforded by or other provisions of the policies of insurance required to be
purchased and maintained by OWNER in accordance with paragraphs 5.6 and 5.7 on the basis of
their not complying with the Contract Documents, CONTRACTOR shall notify OWNER in
GC-16
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
writing thereof within ten days of the date of delivery, of such certificates to CONTRACTOR in
accordance with paragraph 2.7. OWNER and CONTRACTOR shall each provide to the other
such additional information in respect of insurance provided by each as the other may reasonably
request. Failure by OWNER or CONTRACTOR to give any such notice of objection within the
time provided shall constitute acceptance of such insurance purchased by the other as complying
with the Contract Documents.
Partial Utilization-Property Insurance:
5.15. If OWNER finds it necessary to occupy or use a portion or portions of the Work
prior to Substantial Completion of all the Wode, such use or occupancy may be accomplished in
accordance with paragraph 14.10; provided that no such use or occupancy shall commence before
the insurers providing the property insurance have acknowledged notice thereof and in writing
effected the changes in coverage necessitated thereby. The insurers providing the property insur-
ance shall consent by endorsement on the policy or policies, but the property insurance shall not
be canceled or lapse on account of any such partial use or occupancy.
Indemnification
5.16.1. CONTRACTOR shall indemnify and hold harmless COUNTY, PROGRAM
MANAGER, and its employees and agents from and against al11iabi1ities, claims, suits, demands,
damages, losses, and expenses, including attorneys' fees, arising out of or resulting from the
performance of its Work, provided that any such liability, claim, suit, demand, damage, loss, or
expense (a) is attributable to bodily injury, sickness, disease or death, or injury to or destruction of
tangible property, including the loss of use resulting therefrom and (b) is caused in whole or in
part by an act or omission of CONTRACTOR, any Subcontractor, anyone directly or indirectly
employed by and of them, or anyone for whose acts any of them may be liable, whether or not it is
caused in whole or in part by the negligence or other fault of a party indemnified hereunder.
5.16.2. In any and all claims against COUNTY or any of its agents or employees by any
employee of CONTRACTOR, any SUBCONTRACTOR, anyone directly or indirectly employed
by any of them, or anyone for whose acts any of them may be liable, the indemnification
obligation under the previous paragraph shall not be limited in any way as to the amount or type
of damages, compensation or benefits payable by or for CONTRACTOR or any
SUBCONTRACTOR under workmen's compensation acts, disability benefit acts, or other
employee benefit acts.
5.16.3. CONTRACTOR shall indemnify and hold harmless COUNTY and anyone directly
or indirectly employed by it from and against all claims, suits, demands, damages, losses expenses
(including attorney's fees) arising out of any infringement or patent or copyrights held by others
and shall defend all such claims in connection with any alleged infringement of such rights.
GC-17
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 6--CONTRACTOR'S RESPONSffiILITIES
6.1. CONTRACTOR shall supervise and direct the Work competently and efficiently,
devoting such attention thereto and applying such skills and expertise as may be necessary to
perform the Work in accordance with the Contract Documents. CONTRACTOR shall be solely
responsible for the means, methods, techniques, sequences and procedures of construction, but
CONTRACTOR shall not be responsible for the negligence of others in the design or specification
of a specific means, method, technique, sequence or procedure of construction which is shown or
indicated in and expressly required by the Contract Documents. CONTRACTOR shall be
responsible to see that the finished Work complies accurately with the Contract Documents.
6.2. CONTRACTOR shall keep on the Work at all times during its progress a competent
resident superintendent, who shall not be replaced without whiten notice to OWNER and
PROFESSIONAL except under extraordinary circumstances. The superintendent will be
CONTRACTOR's representative at the site and shall have authority to act on behalf of CON-
TRACTOR. All communications to the superintendent shall be as binding as if given to
CONTRACTOR.
Labor. Materials and Equipment:
6.3. CONTRACTOR shall provide competent, suitably qualified personnel to survey and
layout the Work and perform construction as required by the Contract Documents.
CONTRACTOR shall at all times maintain good discipline and order at the site. Except in
connection with the safety or protection of persons or the Work or property at the site or adjacent
thereto, and except as otherwise indicated in the Contract Documents, all Work at the site shall be
performed during regular working hours, and CONTRACTOR will not permit evening work or
the performance of Work on Saturday, Sunday or any legal holiday without OWNER's written
consent given after prior written notice to PROFESSIONAL.
6.4. Unless otherwise specified in the General Requirements, CONTRACTOR shall
furnish and assume full responsibility for all materials, equipment, labor, transportation,
construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone,
water, sanitary facilities, temporary facilities and all other facilities and incidentals whether
temporary or permanent necessary for the execution, testing, initial operation, and completion of
the Work as required by the Contract Documents.
6.5. All materials and equipment shall be of good quality and new, except as otherwise
provided m the Contract Documents. If required by PROFESSIONAL, CONTRACTOR shall
furnish satisfactory evidence (including reports of required tests) as to the kind and quality of
materials and equipment. All materials and equipment shall be applied, installed, connected,
erected, used, cleaned and conditioned in accordance with the instructions of the applicable
Supplier except as otherwise provided in the Contract Documents; but no provision of any such
instructions will be effective to assign to PROFESSIONAL, or any of PROFESSIONAL's
consultants, agents or employees, any duty or authority to supervise or direct the furnishing or
performance of the Work or any duty or authority to undertake responsibility contrary to the
provisions of paragraph 9.14 or 9. 15.
GC-18
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Adjusting Progress Schedule:
6.6. CONTRACTOR shall submit to PROFESSIONAL for acceptance to the extent
indicated in paragraph 2.9) adjustments in the progress schedule to reflect the impact thereon of
new developments; these will conform generally to the progress schedule then in effect and
additionally will comply with any provisions of the General Requirements applicable thereto.
Substitutes or "Or-Equal" Items:
6.7. 1. Whenever materials or equipment are specified or described in the Contract
Documents by using the name of a proprietary item or the name of a particular Supplier the
naming of the item is intended to establish the type, function and quality required. Unless the
name is followed by words indicating that no substitution is permitted, materials or equipment of
other Suppliers may be accepted by PROFESSIONAL if sufficient information is submitted by
CONTRACTOR to allow PROFESSIONAL to determine that the material or equipment
proposed is equivalent or equal to that named. The procedure for review by PROFESSIONAL
will include the following as supplemented in the General Requirements. Requests for review of
substitute items of material and equipment will not be accepted by PROFESSIONAL from anyone
other than CONTRACTOR. If CONTRACTOR wishes to furnish or use a substitute item of
material or equipment, CONTRACTOR shall make written application to PROFESSIONAL for
acceptance thereof, certifying that the proposed substitute will perform adequately the functions
and achieve the results called for by the general design, be similar and of equal substance to that
specified and be suited to the same use as that specified. The application will state that the
evaluation and acceptance of the proposed substitute will not prejudice CONTRACTOR's
achievement of Substantial Completion on time, whether or not acceptance of the substitute for
use in the Work will require a change in any of the Contract Documents (or in the provisions of
any other direct contract with OWNER for work on the Project) to adapt the design to the
proposed substitute and whether or not incorporation or use of the substitute in connection with
the Work is subject to payment of any license fee or royalty. All variations of the proposed
substitute from that specified will be identified in the application and available maintenance, repair
and replacement service will be indicated. The application will also contain an itemized estimate of
all costs that will result directly or indirectly from acceptance of such substitute, including costs of
redesign and claims of other contractors affected by the resulting change, all of which shall be
considered by PROFESSIONAL In evaluating the proposed substitute, PROFESSIONAL may
require CONTRACTOR to furnish at CONTRACTOR's expense additional data about the
proposed substitute.
6.7.2. If a specific means, method, technique, sequence or procedure of construction is
indicated in or required by the Contract Documents, CONTRACTOR may furnish or utilize a
substitute means, method, sequence, technique or procedure of construction acceptable to
PROFESSIONAL, if CONTRACTOR submits sufficient information to allow PROFESSIONAL
to determine that the substitute proposed is equivalent to that indicated or required by the
Contract Documents. The procedure for review by PROFESSIONAL will be similar to that
provided in paragraph 6.7.1 as applied by PROFESSIONAL and as may be supplemented in the
General Requirements.
6.7.3. PROFESSIONAL will be allowed a reasonable time within which to evaluate each
proposed substitute. PROFESSIONAL will be the sole judge of acceptability and no substitute
GC-19
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
will be ordered, installed or utilized without PROFESSIONAL's prior written acceptance which
will be evidenced by either a Change Order or an approved Shop Drawing. OWNER may require
CONTRACTOR to furnish at CONTRACTOR's expense a special performance guarantee or
other surety with respect to any substitute. PROFESSIONAL will record time required by
PROFESSIONAL and PROFESSIONAL's consultants in evaluating substitutions proposed by
CONTRACTOR and in making changes in the Contract Documents occasioned thereby. Whether
or not PROFESSIONAL accepts a proposed substitute. CONTRACTOR shall reimburse
OWNER for the charges of PROFESSIONAL and PROFESSIONAL's consultants for evaluating
each proposed substitute.
Concerning Subcontractors. Suppliers and Others:
6.8.1. CONTRACTOR shall not employ any Subcontractor, Supplier or other person or
organization (including those acceptable to OWNER and PROFESSIONAL as indicated in
paragraph 6.8.2). whether initially or as a substitute, against whom OWNER or
PROFESSIONAL may have reasonable objection. CONTRACTOR shall not be required to
employ any Subcontractor, Supplier or other person or organization to furnish or perform any of
the Work against whom CONTRACTOR has reasonable objection.
6.8.2. If the Supplementary Conditions require the identity of certain Subcontractors,
Suppliers or other persons or organizations including those who are to furnish the principal items
of materials and equipment} to be submitted to OWNER in advance of the specified date prior to
the Effective Date of the Agreement for acceptance by OWNER and PROFESSIONAL and if
CONTRACTOR has submitted a list thereof in accordance with the Supplementary Conditions,
OWNER's or PROFESSIONAL's acceptance (either in writing or by falling to make written
objection thereto by the date indicated for acceptance or objection In the bidding documents or
the Contract Documents} of any such Subcontractor, Supplier or other person or organization so
identified may be revoked on the basis of reasonable objection after due Investigation, in which
case CONTRACTOR shall submit an acceptable substitute, the Contract Price will be increased
by the difference ,n the cost occasioned by such substitution and an appropriate Change Order
will be issued or Written Amendment signed. No acceptance by OWNER or PROFESSIONAL of
any such Subcontractor, Supplier or other person or organization shall constitute a waiver of any
right of OWNER or PROFESSIONAL to reject defective Work.
6.9. CONTRACTOR shall be fully responsible to OWNER and PROFESSIONAL for all
acts and omissions of the Subcontractors, Suppliers and other persons and organizations per-
forming or furnishing any of the Work under a direct or indirect contract with CONTRACTOR
just as CONTRACTOR is responsible for CONTRACTOR's own acts and omissions. Nothing in
the Contract Documents shall create any contractual relationship between OWNER or
PROFESSIONAL and any such Subcontractor, Supplier or other person or organization, nor
shall it create any obligation on the part, of OWNER or PROFESSIONAL to payor to see to the
payment of any moneys due any such Subcontractor, Supplier or other person or organization
except as may otherwise be required by Laws and Regulations.
6.10. The divisions and sections of the Specifications and the identifications of any
Drawings shall not control CONTRACTOR in dividing the Work among Subcontractors or
Suppliers or delineating the Work to be performed by any specific trade.
GC-20
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
6.11. All Work performed for CONTRACTOR by a Subcontractor will be pursuant to an
appropriate agreement between CONTRACTOR and the Subcontractor which specifically binds
the Subcontractor to the applicable terms and conditions of the Contract Documents for the
benefit of OWNER and PROFESSIONAL and contains waiver provisions as required by
paragraph 5. 11. CONTRACTOR shall pay each Subcontractor a just share of any insurance
moneys received by CONTRACTOR on account of losses under policies issued pursuant to
paragraphs 5.6 and 5.7.
Patent Fees and Royalties:
6.12. CONTRACTOR shall pay all license fees and royalties and assume all costs incident
to the use in the performance of the Work or the incorporation in the Work of any invention,
design, process, product or device which is the subject of patent rights or copyrights held by
others. CONTRACTOR Shall indemnify and hold harmless OWNER and PROFESSIONAL and
anyone directly or indirectly employed by either of them from and against all claims, damages,
losses and expenses including attorneys' fees and court and arbitration costs arising out of any
infringement of patent rights or copyrights incident to the use in the performance or the Work or
resulting from the incorporation in the Work of any invention, design, process, product or device
not specified in the Contract Documents, and shall defend all such claims in connection with any
alleged infringement of such rights.
Permits:
6.13. CONTRACTOR shall obtain and pay for all construction permits, licenses,
governmental charges and inspection fees, and all public utility charges which are applicable and
necessary for the execution of the Work. All permit costs shall be included in the base bid.
Permits, if any that are provided and paid for by OWNER are listed in the Supplementary
Conditions. Any delays associated with the permitting process will be considered for time
extensions only and no damages or additional compensation for delay will be allowed.
Laws and Regulations:
6.14.1. CONTRACTOR shall give all notices and comply with all Laws and Regulations
applicable to furnishing and performance of the Work. Except where otherwise expressly required
by applicable Laws and Regulations, neither OWNER nor PROFESSIONAL shall be responsible
for monitoring CONTRACTOR's compliance with any Laws or Regulations.
6.14.2. If CONTRACTOR observes that any of the Contract Documents are contradictory
to such laws, rules, and regulations, it will notify the Project Manager promptly in writing. Any
necessary changes shall then be adjusted by an appropriate Change Order. If CONTRACTOR
performs any Work that it knows or should have known to be contrary to such laws, ordinances,
rules, and regulations and without such notice to the Project Manager, it shall bear all related
costs.
GC-21
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Taxes:
6.15. CONTRACTOR shall pay all sales, consumer, use and other similar taxes required
to be paid by CONTRACTOR in accordance with the Laws and Regulations of the place of the
Project which are applicable during the performance of the Work.
Use of Premises:
6.16. CONTRACTOR shall confine construction equipment, the storage of materials and
equipment and the operations of workers to the Project site and land and areas identified in and
permitted by the Contract Documents and other land and areas permitted by Laws and
Regulations, rights-of-way, permits and easements. CONTRACTOR shall not unreasonably
encumber the premises with construction equipment or other materials or equipment. Any loss or
damage to CONTRACTOR's or any Subcontractor's equipment is solely at the risk of
CONTRACTOR. CONTRACTOR shall assume full responsibility for any damage to any such
land or area, or to the owner or occupant thereof or of any land or areas contiguous thereto,
resulting from the performance of the . Work. Should any claim be made against OWNER or
PROFESSIONAL by any such owner or occupant because of the performance of the Work,
CONTRACTOR shall promptly attempt to settle with such other party by agreement or otherwise
resolve the claim by arbitration or at law. CONTRACTOR shall to the fullest extent permitted by
Laws and Regulations, indemnify and hold OWNER harmless from and against all claims,
damages, losses and expenses (including, but not limited to, fees of PROFESSIONALs,
architects, attorneys and other professionals and court and arbitration costs) arising directly,
indirectly or consequentially out of any action, legal or equitable, brought by any such other party
against OWNER to the extent based on a claim arising out of CONTRACTOR's performance of
the Work.
6.17. During the progress of the Work, CONTRACTOR shall keep the premises free
from accumulations of waste materials, rubbish and other debris or contaminates resulting from
the Work. At the completion of the Work CONTRACTOR shall remove all waste materials,
rubbish and debris from and about the premises as well as all tools, appliances, construction
equipment and machinery, and surplus materials, and shall leave the site clean and ready for
occupancy by OWNER. CONTRACTOR shall restore to original condition all property not
designated for alteration by the Contract Documents.
6.18. CONTRACTOR shall not load nor permit any part of any structure to be loaded in
any manner that will endanger the structure, nor shall CONTRACTOR subject any pan of the
Work or adjacent property to stresses or pressures that will endanger them.
Record Documents:
6.19. Contractor shall keep at the site and in good order one record copy of the Contract
Documents and all Drawings and Specifications. These documents shall be annotated on a
continuing basis to show all changes made during the construction process. These shall be
available to PROFESSIONAL and the Project Manager and shall be submitted with the
Application for Final Payment.
GC-22
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Safety and Protection:
6.20. CONTRACTOR shall be responsible for initiating, maintaining and supervising all
safety precautions and programs in connection with the Work. CONTRACTOR shall assume all
risk of loss for stored equipment or materials, irrespective of whether CONTRACTOR has
transferred the title of the stored equipment or materials to OWNER. CONTRACTOR shall take
all necessary precautions for the safety of, and shall provide the necessary protection to prevent
damage, injury or loss to:
6.20.1. all employees on the Work and other persons and organizations who may be
affected thereby:
6.20.2. all the Work and materials and equipment to be incorporated therein, whether in
storage on or off the site; and
6.20.3. other property at the site or adjacent thereto, including trees, shrubs, lawns,
walks, pavements, roadways, structures, utilities and Underground Facilities not designated for
removal, relocation or replacement in the course of construction.
CONTRACTOR shall comply with all applicable Laws and Regulations of any public body having
jurisdiction for the safety of persons or property or to protect them from damage, injury or loss;
and shall erect and maintain all necessary safeguards for such safety and protection.
CONTRACTOR shall notify OWNERS of adjacent property and of Underground Facilities and
utility OWNERS when prosecution of the Work may affect them, and shall cooperate with them
in the protection, removal, relocation and replacement of their property. All damage, injury or
loss to any property referred to in paragraph 6.20.2 or 6.20.3 caused, directly or indirectly, in
whole or in part, by CONTRACTOR, any Subcontractor, Supplier or any other person or
organization directly or indirectly employed by any of them to perform or furnish any the Work or
anyone for whose acts any of them may be liable, shall be remedied by CONTRACTOR (except
damage or loss attributable to the fault of Drawings or Specifications or to the acts or omissions
of OWNER or PROFESSIONAL or anyone employed by either of them or anyone for whose acts
either of them may be liable, and not attributable, directly or indirectly, in whole or in part, to the
fault or negligence of CONTRACTOR). CONTRACTOR's duties and responsibilities for the
safety and protection of the Work shall continue until such time as all the Work is completed and
PROFESSIONAL has issued a notice to OWNER and CONTRACTOR in accordance, with
paragraph 14.13 that the Work is acceptable (except as otherwise expressly provided In
connection with Substantial Completion).
6.21. CONTRACTOR shall designate a responsible member of its organization whose
duty shall be the prevention of accidents at the site. This person shall be CONTRACTOR's
superintendent unless otherwise designated in writing by CONTRACTOR to the Project
Manager.
Emergencies:
6.22. In emergencies affecting the safety or protection of persons or the Work or
property at the site or adjacent thereto, CONTRACTOR, without special instruction or
authorization from PROFESSIONAL or OWNER, is obligated to act to prevent threatened
GC-23
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
damage, injury or loss. CONTRACTOR shall give PROFESSIONAL prompt written notice if
CONTRACTOR believes that any significant changes in the Work or variations from the Contract
Documents have been caused thereby. If PROFESSIONAL determines that a change In the
Contract Documents is required because of the action taken in response to ari emergency, a Work
Directive Change or Change Order be issued to document the consequences of the changes or
variations.
6.22.1. CONTRACTOR shall immediately notify PROFESSIONAL of all events involving
personal injuries to any person on the Site, whether or not such person was engaged in the
construction of the Proj ect, and shall file a written report on such person( s) and any other event
resulting in property damage of any amount within five (5) days of the occurrence.
6.22.2. If PROFESSIONAL determines that a change in the Contract Documents is
required because of the action taken by CONTRACTOR in response to such an emergency, a
Change Order will be issued to document the consequences of such action.
Shop Drawings and Samples:
6.23. After checking and verifying all field measurements, CONTRACTOR shall
promptly submit to PROFESSIONAL for approval, in accordance with the accepted schedule of
submittals, all submittals and samples required by the Contract Documents. All submittals and
samples shall have been checked by and stamped with the approval of CONTRACTOR and
identified as PROFESSIONAL may require. The data shown on or with the submittals will be
complete with respect to dimensions, design criteria, materials and any other information
necessary to enable PROFESSIONAL to review the submittal as required. At the time of each
submission, CONTRACTOR shall give notice to PROFESSIONAL of all deviations that the
submittal or sample may have from the requirements of the Contract Documents.
6.24. PROFESSIONAL shall review and approve submittals and samples. Professional's
review and approval shall be only for conformance with the design concept of the Project and
compliance with the information given in the Contract Documents. The approval of a separate
item as such will not indicate approval of the assembly in which the item functions.
CONTRACTOR will make any corrections required by PROFESSIONAL and resubmit the
required number of corrected copies until approved. CONTRACTOR's stamp of approval on any
submittal or sample shall constitute its representation to PROFESSIONAL and County that
CONTRACTOR has determined and verified all quantities, dimensions, field construction criteria,
materials, catalog numbers, and similar data, and that each submittal or sample has been reviewed
or coordinated with the requirements of the Work and the Contract Documents.
6.24.1. No Work requiring a submittal or sample submission shall commence until the
submission has been approved by PROFESSIONAL. A copy of each approved submittal and
each approved sample shall be kept in good order by CONTRACTOR at the site and shall be
available to PROFESSIONAL and County staff. Any delays associated with the submittal
process will be considered for time extensions only, and no damages or additional compensation
for delay will be allowed.
6.25.1. Before submission of each Shop Drawing or sample CONTRACTOR shall have
determined and verified all quantities, dimensions, specified performance criteria, installation
GC-24
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
requirements, materials, catalog numbers and similar data with respect thereto and reviewed or
coordinated each Shop Drawing or sample with other Shop Drawings and samples and with the
requirements of the Work and the Contract Documents.
6.25.2. At the time of each submission, CONTRACTOR shall give PROFESSIONAL
specific written notice of each variation that the Shop Drawings or samples may have from the
requirements of the Contract Documents, and, in addition, shall cause a specific notation to be
made on each Shop Drawing submitted to PROFESSIONAL for review and approval of each
such variation.
6.26. PROFESSIONAL will review and approve with reasonable promptness Shop
Drawings and samples, but PROFESSIONAL's review and approval will be only for conformance
with the design concept of the Project and for compliance with the information given in the
Contract Documents and shall not extend to means, methods, techniques, sequences or
procedures of construction (except where a specific means, method, technique, sequence or
procedure of construction is indicated in or required by the Contract Documents) or to safety
precautions or programs incident thereto. The review and approval of a separate item as such will
not indicate approval of the assembly in which the item functions.
6.27. No Work requiring a submittal or sample submission shall commence until the
submission has been approved by PROFESSIONAL. A copy of each approved submittal and
each approved sample shall be kept in good order by CONTRACTOR at the site and shall be
available to PROFESSIONAL and Project Managery staff. Any delays associated with the
submittal process will be considered for time extensions only, and no damages or additional
compensation for delay will be allowed.
6.28. PROFESSIONAL's approval of submittals or samples shall not relieve
CONTRACTOR from responsibility for any variation from the requirements of the Contract
Documents unless CONTRACTOR has in writing called PROFESSIONAL's attention to each
such variation at the time of submission and the Project Manager has given written approval to
the specific deviation; any such approval by PROFESSIONAL shall not relieve CONTRACTOR
from responsibility for errors or omissions in the submittals.
6.29. Where a shop drawing or sample is required by the Contract Documents or the
schedule of shop drawings and sample submissions accepted by PROFESSIONAL as required,
any related work performed prior to Professional's review and approval of the pertinent submittal
will be at the sole expense and responsibility of Contractor.
Continuing the Work:
6.30. CONTRACTOR shall carry on the Work and adhere to the progress schedule
during all disputes or disagreements with OWNER. No Work shall be delayed or postponed pend-
ing resolution of any disputes or disagreements, except as permitted by paragraph 15.6 or as
CONTRACTOR and OWNER may otherwise agree in wilting.
GC-25
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Cleaning Up:
6.31. CONTRACTOR shall maintain the site free from accumulations of waste materials,
rubbish, and other debris or contaminates resulting from the work on a daily basis or as required.
At the completion of the work, CONTRACTOR shall remove all waste materials, rubbish, and
debris from the site as well as all tools, construction equipment and machinery, and surplus
materials and will leave the Site clean and ready for occupancy by OWNER. All disposal shall be
in accordance with applicable laws and regulations. In addition to any other rights available to
OWNER under the Contract Documents, CONTRACTOR's failure to maintain the site may
result in withholding of any amounts due CONTRACTOR. CONTRACTOR will restore to
original condition those portions of the site not designated for alteration by the Contract
Documents.
Indemnification:
6.32. To the fullest extent permitted by Laws and Regulations CONTRACTOR shall
indemnify and hold harmless OWNER and PROFESSIONAL and their consultants, agents and
employees from and against all claims, damages, losses and expenses, direct, indirect or
consequential (including but not limited to fees and charges of PROFESSIONALs, architects,
attorneys and other PROFESSIONALs and court and arbitration costs) arising out of or resulting
from the performance of the Work, provided that any such claim, damage, loss or expense (a)is
attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible
property (other than the Work itself) including the loss of use resulting therefrom and (b) is
caused in whole or in pan by any negligent act or omission of CONTRACTOR, any
Subcontractor, any person or organization directly or indirectly employed by any of them to
perform or furnish any of the Work or anyone for whose acts any of them may be liable,
regardless of whether or not it is caused in part by a party indemnified hereunder or arises by or is
imposed by Law and Regulations regardless of the negligence of any such party.
6.33. In any and all claims against OWNER or PROFESSIONAL or any of their
consultants, agents or employees by any employee of CONTRACTOR, any Subcontractor, any
person or organization directly or indirectly employed by any of them to perform or furnish any of
the Work or anyone for whose acts any of them may be liable, the indemnification obligation
under paragraph 6.32 shall not be limited in any way by any limitation on the amount or type of
damages, compensation or benefits payable by or for CONTRACTOR or any such Subcontractor
or other person or organization under workers' or workmen's compensation acts. disability benefit
acts or other employee benefit acts.
6.34. The obligations of CONTRACTOR under paragraph 6.32 shall not extend to the
liability of PROFESSIONAL, PROFESSIONAL's consultants, agents or employees arising out of
the preparation or approval of maps, drawings, opinions, reports, surveys, Change Orders,
designs or specifications,
GC-26
I
I
I
I
I'
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 7---0THER WORK
Related Work at Site:
7.1. OWNER may perform other work related to the Project at the site by OWNER's
own forces, have other work performed by ailed OWNERS or let other direct contracts therefor
which shall contain General Conditions similar to these. If the fact that such other work is to be
performed was not noted in the Contract Documents, written notice thereof will be given to
CONTRACTOR prior to starting any such other work: and, if CONTRACTOR believes that such
performance will involve additional expense to CONTRACTOR or requires additional time and
the parties are unable to agree as to the extent thereof. CONTRACTOR may make a claim
therefor as provided in Articles 11 and 12.
7.1.2. CONTRACTOR shall afford each utility owner and other contractor who is a party
to such a direct contract for OWNER, if OWNER is performing the additional work with
OWNER's employees)proper and safe access to the site and a reasonable opportunity for the
introduction and storage of materials and equipment and the execution of such work, and shall
properly connect and coordinate the Work with theirs. CONTRACTOR shall do all cutting, fitting
and patching of the Work that may be required to make its several pans come together properly
and integrate with such other work. CONTRACTOR shall not endanger any work'of others by
cutting, excavating or otherwise altering their work and will only cut or alter their work with the
written consent of PROFESSIONAL and the others whose work will be affected. The duties and
responsibilities of CONTRACTOR under this paragraph are for the benefit of such utility owners
and other contractors to the extent that there are. comparable provisions for the benefit or'
CONTRACTOR in said direct contracts between OWNER and such utility owners and other
contractors.
7.2. If any part of CONTRACTOR's Work depends for proper execution or results upon
the work of any such other contractor or utility owner (or OWNER), CONTRACTOR shall
inspect and promptly report to PROFESSIONAL in writing any delays, defects or deficiencies in
such work that render it unavailable or unsuitable for such proper execution and results.
CONTRACTOR's failure so to report will constitute an acceptance of the other work as fit and
proper for integration with CONTRACTOR's Work except for latent or nonapparent defects and
deficiencies in the other work.
Coordination:
7.4. If OWNER contracts with others for the performance of other work on the Project at
the site, the person or organization who will have authority and responsibility for coordination of
the activities among the various prime contractors will be identified in the Supplementary
Conditions, and the specific matters to be covered by such authority and responsibility will be
itemized, and the extent of such authority and responsibilities will be provided, in the
Supplementary Conditions. Unless otherwise provided in the Supplementary Conditions, neither
OWNER nor PROFESSIONAL shall have any authority or responsibility in respect of such
coordination.
GC-27
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 8---0WNER'S RESPONSmILITIES
8.1. Except as otherwise provided in these General Conditions, COUNTY shall issue all
communications to CONTRACTOR through the Project Manager or PROFESSIONAL.
8.2. In case of termination of the employment of PROFESSIONAL, OWNER shall
appoint a PROFESSIONAL against whom CONTRACTOR makes no reasonable objection,
whose status under the Contract Documents shall be that of the former PROFESSIONAL. Any
dispute in connection with such appointment shall be subject to arbitration.
8.3. OWNER shall furnish the data required of OWNER under the Contract Documents
promptly and shall make payments to CONTRACTOR promptly after they are due as provided in
paragraphs 14.4 and 14.13.
8.4. OWNER's duties in respect of providing lands and easements and providing
Engineering surveys to establish reference points are set forth in paragraphs 4.1 and 4.4. Para-
graph 4.2 refers to OWNER's identifying and making available to CONTRACTOR copies of
reports of explorations and tests of subsurface conditions at the site and in existing structures
which have been utilized by PROFESSIONAL in preparing the Drawings and Specifications.
8.5. OWNER's responsibilities in respect of purchasing and maintaining liability and
property insurance are set forth in paragraphs 5.5 through 5.8.
8.6. OWNER is obligated to execute Change Orders as indicated in paragraph 10.3.
8.7. OWNER's responsibility in respect of certain inspections, tests and approvals is set
forth in paragraph 13.4.
8.8. In connection with OWNER's right to stop Work or suspend Work, see paragraphs
13.10 and 15.1. Paragraph 15.2 deals with OWNER's right to terminate services of CON-
TRACTOR under certain circumstances.
GC-28
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 9---PROFESSIONAL'S STATUS DURING
CONSTRUCTION
Owner's Representative:
9.1. PROFESSIONAL will be OWNER's representative during the construction period.
The duties and responsibilities and the limitations of authority of PROFESSIONAL as OWNER's
representative during construction are set forth in the Contract Documents and shall not be
extended without written consent of OWNER and PROFESSIONAL.
Visits to Site:
9.2. PROFESSIONAL will make visits to the site at intervals appropriate to the various
stages of construction to observe the premises and quality of the executed Work and to deter-
mine, in general, if the Work is proceeding in accordance with the Contract Documents.
PROFESSIONAL will not be required to make exhaustive or continuous on-site inspections to
check the quality or quantity of the Work. PROFESSIONAL's efforts will be directed toward
providing for OWNER a greater degree of confidence that the completed Work will conform to
the Contract Documents. On the basis of such visits and on-site observations as an experienced
and qualified design PROFESSIONAL. PROFESSIONAL will keep OWNER informed of the
progress of the Work and will endeavor to guard OWNER against defects and deficiencies in the
Work.
Project Representation:
9.3. If OWNER and PROFESSIONAL agree, PROFESSIONAL will furnish a Resident
Project Representative to assist PROFESSIONAL in observing the performance of the Work. The
duties, responsibilities and limitations of authority of any such Resident Project Representative
and assistants will be as provided in the Supplementary Conditions. If OWNER designates
another agent to represent OWNER at the site who is not PROFESSIONAL's agent or employee,
the duties, responsibilities and limitations of authority of such other person will be as provided in
the Supplementary Conditions.
Clarifications and Interpretations:
9.4. PROFESSIONAL shall issue such written clarifications or interpretations of the
Contract Documents (in the form of Drawings or otherwise) as may be determined necessary, or
as reasonably requested by CONTRACTOR, which shall be consistent with or reasonably
inferable from the overall intent of the Contract Documents. If CONTRACTOR believes that a
written clarification and interpretation entitles it to an increase in the Contract Price, and/or
Contract Time, CONTRACTOR may make a claim as provided for in Articles 11 or 12.
GC-29
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Decisions on Disputes:
9.11. PROFESSIONAL will be the initial interpreter of the requirements of the Contract
Documents and judge of the acceptability of the Work thereunder. Claims, disputes and other
matters relating to the acceptability of the Work or the interpretation of the requirements of the
Contract Documents pertaining to the performance and furnishing of the Work and claims under
Articles 11 and 12 in respect of changes m the Contract Price or Contract Time will be referred
initially to PROFESSIONAL in writing with a request for a formal decision in accordance with
this paragraph, which PROFESSIONAL will render in writing within a reasonable time, Written
notice of each such claim, dispute and other matter will be delivered by the claimant to
PROFESSIONAL and the other party to the Agreement promptly (but in no event later than
thirty days after the occurrence of the event giving rise thereto, and written supporting data will
be submitted to PROFESSIONAL and the other party within sixty days after such occurrence
unless PROFESSIONAL allows an additional period of time to ascertain more accurate data in
support of the claim.
9. 12. When functioning as interpreter and judge under paragraphs 9.10 and 9.11,
PROFESSIONAL will not show partiality to OWNER or CONTRACTOR and will not be liable
in connection with any interpretation or decision rendered in good faith in such capacity. The
rendering of a decision by PROFES SIONAL pursuant to paragraphs 9.10 and 9.11 with respect
to any, such claim, dispute or other matter (except any which have been waived by the making. or
acceptance of final payment as provided in paragraph 14. 16) will be a condition precedent to any
exercise by OWNER or CONTRACTOR of such rights or remedies as either may otherwise have
under the Contract Documents or by Laws or Regulations in respect of any such claim, dispute or
other matter.
Limitations on PROFESSIONAL's Responsibilities:
9.13. Neither PROFESSIONAL's authority to act under this Article or elsewhere in the
Contract Documents, nor any decision made in good faith to exercise such authority shall give rise
to any duty or responsibility of PROFESSIONAL to CONTRACTOR, any Subcontractor, any of
their agents or employees.
9.14. PROFESSIONAL shall not be responsible for the construction means, methods,
techniques, sequences, or procedures or the safety precautions and programs used.
PROFESSIONAL shall not be responsible for CONTRACTOR's failure to perform the Work in
accordance with the Contract Documents.
9.15. PROFESSIONAL shall not be responsible for the acts or OIlllSSlons of
CONTRACTOR, any Subcontractors, any agents or employees, or any other persons performing
any of the Work.
GC-31
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Authorized Variations in Work:
9.5. PROFESSIONAL may authorize minor variations in the Work from the requirements
of the Contract Documents which do not involve an adjustment in the Contract Price or the
Contract Time and are consistent with the overall intent of the Contract Documents. These may
be accomplished by a Field Order and will be binding on OWNER, and also on CONTRACTOR
who shall perform the Work involved promptly. If CONTRACTOR believes that a Field Order
justifies an increase in the Contract Price or an extension of the Contract Time and the parties are
unable to agree as to the amount or extent thereof CONTRACTOR may make a claim therefor as
provided in Article 11 or 12.
Rejecting Defective Work:
9.6. PROFESSIONAL will have authority to disapprove or reject Work which
PROFESSIONAL believes to be defective, and will also have authority to require special
inspection or testing of the Work as provided in paragraph 13.9, whether or not the Work is
fabricated, installed or completed.
Shop Drawings, Change Orders and Payments:
9.7. In connection with PROFESSIONAL's responsibility for Shop Drawings and
samples, see paragraphs 6.23 through 6.29 inclusive.
9.8. In connection with PROFESSIONAL's responsibilities as to Change Orders, see
Articles 10, 11 and 12.
9.9. In connection with PROFESSIONAL's responsibilities in respect of Applications for
Payment, etc., see Article 14.
Determinations for Unit Prices:
9.10. PROFESSIONAL will determine the actual quantities and classifications of Unit
Price Work performed by CONTRACTOR. PROFESSIONAL will review with CONTRACTOR
PROFESSIONAL's preliminary determinations on such matters before rendering a written
decision thereon (by recommendation of an Application for Payment or otherwise). PROF-
ESSIONAL's written decisions thereon will be final and binding upon OWNER and
CONTRACTOR, unless, within ten days after the date of any such decision, either OWNER or
CONTRACTOR delivers to the other party to the Agreement and to PROFESSIONAL written
notice of intention to appeal from such a decision.
GC-30
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE lO--CHANGES IN THE WORK
10.1. Without invalidating the Contract, OWNER may at any time or from time to time
order additions, deletions, or revisions in the Work. The Project Manager shall provide
CONTRACTOR with a proposal request, identifying the Work to be added, deleted or revised.
Upon receipt, CONTRACTOR shall promptly submit a written proposal for the changed work
prepared in accordance with Articles 11 and 12. If the proposal request calls only for the deletion
of Work, the Project Manager may order the partial suspension of any Work related to the
proposed deletion, in which case CONTRACTOR must cease performance as directed;
CONTRACTOR shall not be entitled to claim lost profits on deleted work. All changed Work
shall be executed under the applicable conditions of the Contract Documents.
10.2. Additional Work performed by CONTRACTOR without authorization of a Change
Order will not entitle CONTRACTOR to an increase in the Contract Price or an extension of the
Contract Time, except in the case of an emergency as provided in Article 7. The effect of this
paragraph shall remain paramount and shall prevail irrespective of any conflicting provisions
contained in these Contract Documents.
10.3. Upon agreement as to changes in the Work to be performed, Work performed in an
emergency as provided in Article 6, and any other claim of CONTRACTOR for a change in the
Contract Time or the Contract Price, PROFESSIONAL will prepare a written Change Order to
be signed by PROFESSIONAL and CONTRACTOR and submitted to OWNER for approval.
lOA. In the absence of an agreement as provided in 11.1.3, OWNER may, at its sole
discretion issue a Work Directive Change to CONTRACTOR. Pricing of the Work Directive
Change will be in accordance with Section 12.1.3. The Work Directive Change will specify a
price, and if applicable a time extension, determined to be reasonable by OWNER. If
CONTRACTOR fails to sign such Work Directive Change, CONTRACTOR may submit a claim
in accordance with Articles 11 and 12, but CONTRACTOR shall nevertheless be obligated to
fully perform the work as directed by the Construction Change Directive.
10.5. CONTRACTOR shall proceed diligently with performance of the Work as directed
by O\VNER, regardless of pending claim actions, unless otherwise agreed to in writing.
10.6. If notice of any change affecting the general scope of the Work or the provisions of
the Contract Documents (including, but not limited to, Contract Price or Contract Time) is
required by the provisions of any Bond to be given to a surety, the giving of any such notice will
be CONTRACTOR's responsibility, and the amount of each applicable Bond will be adjusted
accordingly.
GC-32
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE ll-CHANGE OF CONTRACT PRICE
11.1. The Contract Price constitutes the total compensation (subject to written authorized .
adjustments) payable to CONTRACTOR for performing the Work. All duties, responsibilities
and obligations assigned to or undertaken by CONTRACTOR shall be at CONTRACTOR's
expense without change in the Contract Price.
11.2. The Contract Price may only be changed by a Change Order or by a Written
Amendment. Any claim for an increase or decrease in the Contract Price shall be based on written
notice delivered by the party making the claim to the other party and to PROFESSIONAL
promptly (but in no event later than thirty days) after the occurrence of the event giving rise to the
claim and stating the general nature of the claim. Notice of the amount of the claim with
supporting data shall be delivered within sixty days after such occurrence (unless
PROFESSIONAL allows an additional period of time to ascertain more accurate data in support
of the claim and shall be accompanied by claimant's written statement that the amount claimed
covers all known amounts (direct, indirect and consequential) to which the claimant is entitled as
a result of the occurrence of said event. All claims for adjustment in the Contract Price shall be
determined by PROFESSIONAL in accordance with paragraph 9.11 if OWNER and
CONTRACTOR cannot otherwise agree on the amount involved. No claim for an adjustment in
the Contract Price will be valid if not submitted in accordance with this paragraph 11.2.
11.3. The value of any Work covered by a Change Order or of any claim for an
adjustment in the Contract Price will be determined by the following procedures:
11.3.1. Designated Unit Price (Field Measure) CONTRACTOR and OWNER recognize
and acknowledge that the quantities shown for those items designated in the Bid Proposal as unit
price items are approximations prepared by OWNER for bid purposes and that the actual
compensation payable to CONTRACTOR for the utilization of such items is based upon the
application of unit prices to the actual quantities of items involved as measured in the field and
required to complete the Work as originally defined in the Contract Documents.
11.3.2. When it is determined by OWNER that an addition, deletion, or revision to the
Work as defined in these Contract Documents is required and affects the quantities required for
items designed in the Bid Proposal as unit price items, CONTRACTOR and OWNER agree that
the compensation payable to CONTRACTOR for such unit price items shall be adjusted
accordingly by a Change Order based upon the application of the appropriate unit prices shown in
the Bid Proposal to the quantity of the unit price item required to complete the Work as defined in
the Contract Documents.
11.3.3. Other Unit Prices. For items not designated in the bid proposal as unit prices,
OWNER and CONTRACTOR may establish unit prices as agreed on by Change Order.
11.3.4. Lump Sum. When it is determined by OWNER that an addition, deletion or
revision to the Work is required which results in a change in Work designated in the Bid Proposal
as a lump sum item, the amount of increase or decrease in the lump sum price shall be established
by mutual agreement of the parties.
GC-33
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
11.3.5. If the pricing methods specified in 11.3 are inapplicable, or if the parties are
unable to agree on a price for the changed work, a reasonable price for the same shall be
established by OWNER in accordance with 11.4 and 11.5. OWNER shall then process a
unilateral Change Order, specifying the said reasonable price, in accordance with 11.4 through
11.6. CONTRACTOR shall perform the Work as directed in the Change Order.
11.3.6. Failure on the part of CONTRACTOR to construct any item to plan or authorized
dimensions within the specification tolerances shall result in: reconstruction to acceptable
tolerances at no additional costs to OWNER; acceptance at no pay; or acceptance at reduced final
pay quantity or reduced unit price, all at the discretion of OWNER. Determinations of aggregate
monetary change for items identified as lump sum quantities shall be made by OWNER based
upon an analysis of the scope of CONTRACTOR's failure to construct to plan or authorized
dimensions.
Cost of the Work:
11.4. The term Cost of the Work means the sum of all costs necessarily incurred and paid
by CONTRACTOR in the proper performance of the Work. Except as otherwise may be agreed
to in writing by OWNER, such costs shall be in amounts no higher than those prevailing in the
locality of the Project, shall include only the following items and shall not include any of the costs
itemized in paragraph 11.5:
11.4.1. Payroll costs for employees in the direct employ of CONTRACTOR in the
performance of the Work under schedules of job classifications agreed upon by OWNER and
CONTRACTOR. Payroll costs for employees not employed full time on the Work shall be
apportioned on the basis of their time spent on the Work. Payroll costs shall include, but not be
limited to, salaries and wages plus the cost of fringe benefits which shall include social security
contributions, unemployment, excise and payroll taxes, workers' or workmen's compensation,
health and retirement benefits, bonuses, sick leave, vacation and holiday pay applicable thereto.
Such employees shall include superintendents and foremen at the site. The expenses of performing
Work after regular working hours, on Saturday, Sunday or legal holidays, shall be included in the
above to the extent authorized by OWNER.
11.4.2. Cost of all materials and equipment furnished and incorporated in the Work,
including costs of transportation and storage thereof, and Suppliers' field services required in
connection therewith. All cash discounts shall accrue to CONTRACTOR unless OWNER
deposits funds with CONTRACTOR with which to make payments, in which case the cash
discounts shall accrue to OWNER. Trade discounts, rebates and refunds and all returns from sale
of surplus materials and equipment shall accrue to OWNER, and CONTRACTOR shall make
provisions so that they may be obtained.
11.4.3. Payments made by CONTRACTOR to the Subcontractors for Work performed
by Subcontractors. If required by OWNER. CONTRACTOR shall obtain competitive bids from
Subcontractors acceptable to CONTRACTOR and shall deliver such bids to OWNER who then
determine, with the advice of PROFESSIONAL, which bids will be accepted. If a subcontract
provides that the Subcontractor is to be paid on the basis of Cost of the Work Plus a Fee, the
Subcontractor's Cost of the Work shall be determined in the same manner as CONTRACTOR's
GC-34
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Cost of the Work. All subcontracts shall be subject to the other provisions of the Contract
Documents insofar as applicable.
11.4.4. Costs of special consultants (including but not limited to PROFESSIONAL's
architects, testing laboratories, surveyors, attorneys and accountants) employed for services
specifically related to the Work.
11.4.5. Supplemental costs including the following:
11.4.5.1. The proportion of necessary transportation, travel and subsistence expenses of
CONTRACTOR's employees incurred in discharge of duties connected with the Wark.
11.4.5.2. Cost, including transportation and maintenance, of all materials, supplies,
equipment, machinery, appliances, office and temporary facilities at the site and hand tools not
owned by the workers, which are consumed in the performance of the Work, and cost less market
value of such items used but not consumed which remain the property of CONTRACTOR.
11.4.5.3. Rentals of all construction equipment and machinery and the pans thereof
whether rented from CONTRACTOR or others in accordance with rental agreements approved
by OWNER with the advice of PROFESSIONAL, and the costs of transportation, loading,
unloading, installation, dismantling and removal thereof---all in accordance with terms of said
rental agreements. The rental of any such equipment, machinery or parts shall cease when the use
thereof is no longer necessary for the Work.
11.4.5.4. Sales, consumer, use or similar taxes related to the Work, and for which
CONTRACTOR is liable, imposed by Laws and Regulations.
11.4.5.5. Deposits lost for causes other than negligence of CONTRACTOR, any
Subcontractor or anyone directly or indirectly employed by any of them or for whose acts any of
them may be liable, and royalty payments and fees for permits and licenses.
11.4.5.6. Losses and damages (and related expenses), not compensated by insurance or
otherwise, to the Work or otherwise sustained by CONTRACTOR in connection with the
performance and furnishing of the Work (except losses and damages within the deductible
amounts of property insurance established by OWNER in accordance with paragraph 5.6). pro-
vided they have resulted from causes other than the negligence of CONTRACTOR, any
Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of
them may be liable. Such losses shall include settlements made with the written consent and
approval of OWNER. No such losses, damages and expenses shall be included in the Cost of the
Work for the purpose of determining CONTRACTOR's Fee. If, however, any such loss or
damage requires reconstruction and CONTRACTOR is placed in charge thereof,
CONTRACTOR shall be paid for services a fee proportionate to that stated in paragraph 11.6.2.
11.4.5.7. The cost of utilities, fuel and sanitary facilities at the site.
11.4.5. 8. Minor expenses such as telegrams, long distance telephone calls, telephone
service at the site, expressage and similar petty cash items in connection the Work.
GC-35
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
11.4.5.9. Cost of premiums for additional Bonds and insurance required because of
changes in the Work and premiums of property insurance coverage within the limits of the
deductible amounts established by OWNER in accordance with paragraph 5.6.
11.5. The term Cost of the Work shall not include any of the following:
11.5.1. Payroll costs and other compensation of CONTRACTOR's officers, executives,
principals (of partnership and sole proprietorships), general managers, PROFESSIONALs,
architects, estimators, attorneys, auditors, accountants, purchasing and contracting agents,
expediters, timekeepers, clerks and other personnel employed by CONTRACTOR whether at the
site or in CONTRACTOR's principal or a branch office for general administration of the Work
and not specifically included in the agreed upon schedule of job classifications referred to in para-
graph 11.4. 1 or specifically covered by paragraph 11.4. 4--all of which are to be considered
administrative costs covered by CONTRACTOR's Fee.
11.5.2. Expenses of CONTRACTOR's principal area branch offices other than
CONTRACTOR's office at the site.
11.5.3. Any part of CONTRACTOR's capital expenses, including interest on
CONTRACTOR'S capital used for the Change Order Work and charges against CONTRACTOR
for delinquent payments.
11.5.4. Cost of premiums for all Bonds and for all insurance whether or not
CONTRACTOR is required by the Contract Documents to purchase and maintain the same
(except for the cost of premiums covered by subparagraph 11.4.5.9 above).
11.5.5. Costs due to the negligence of CONTRACTOR, any Subcontractor, or anyone
directly or indirectly, employed by any of them or for whose acts any of them may be liable,
including but not limited to, the correction of defective Work, disposal of materials or equipment
wrongly supplied and making good any damage to property.
11.5.6. Other overhead or general expense costs of any kind and the costs of any item not
specifically and expressly included in paragraph 11.4.
GC-36
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
CONTRACTOR's Fee:
11.6. CONTRACTORls Fee allowed to CONTRACTOR for overhead and profit shall be
determined as follows:
11.6.1. a mutually acceptable fixed fee; or if none can be agreed upon,
11.6.2. a fee based on the following percentages of the various portions orl the Cost of
the Work:
11.6.2.1. for costs incurred under paragraphs 11.4.1 and 11.4.2, CONTRACTORls Fee
shall be fifteen percent:
11.6.2.2. for costs incurred under paragraph 11.4.3, CONTRACTORls Fee shall five
percent; and if a subcontract is on the basis of Cost of the Work Plus a Fee, the maximum
allowable to CONTRACTOR on account of overhead and profit of all Subcontractors shall be
fifteen percent:
11.6.2.3. no fee shall be payable on the basis of costs itemized under paragraphs 11.4.4,
11.4.5 and 11.3:
11.6.2.4. the amount of credit to be allowed by CONTRACTOR to OWNER for any
such change which results in a net decrease in cost will be the amount of the actual net decrease
plus a deduction in CONTRACTOR's Fee by an amount equal to ten percent of the net decrease:
and
11.6.2.5. when both additions and credits are involved in anyone change, the adjustment
in CONTRACTOR's Fee shall be computed on the basis of the net change in accordance with
paragraphs 11.6.2.1 through 11.6.2.4, inclusive.
11.7. For all changes, CONTRACTOR shall submit an itemized cost breakdown, together
with supporting data in such detail and form as prescribed by the Project Manager. When a credit
is due, the amount of credit to be allowed by CONTRACTOR to OWNER for any such change
which results in a net decrease in cost will be the amount of the actual net decrease in direct cost
as determined by the Project Manager, plus the applicable reduction in overhead and profit.
When both additions and credits are involved in any change, the combined overhead and profit
shall be calculated on the basis of the next change, whether an increase or decrease. In any event,
the minimum detail shall be an itemization of all man-hours required by discipline/trade with the
unit cost per man-hour and total labor price, labor burden, equipment hours and rate for each
piece of equipment, material by units of measure and price per unit, other costs specifically
itemized, plus the overhead and profit markup.
GC-37
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Cash Allowances:
11.8. It is understood that CONTRACTOR has included in the Contract Price all
allowances so named in the Contract Documents and shall cause the Work so covered to be done
by such Subcontractors or Suppliers and for such sums within the limit of the allowances as may
be acceptable to PROFESSIONAL, CONTRACTOR agrees that:
11.8.1. The allowances include the cost to CONTRACTOR (less any applicable trade
discounts) of materials and equipment required by the allowances to be delivered at the site, and
all applicable taxes; and
11.8.2. CONTRACTOR's costs for unloading and handling on the site, labor, installation
costs, overhead, profit and other expenses contemplated for the allowances have been included in
the Contract Price and not in the allowances. No demand for additional payment on account of
any thereofwill be valid.
Prior to final payment, an appropriate Change Order will be issued as recommended by
PROFESSIONAL to reflect actual amounts due CONTRACTOR on account of Work covered by
allowances, and the Contract Price shall be correspondingly adjusted.
Unit Price Work:
11.9.1. Where the Contract Documents provide that all or part of the Work is to be Unit
Price Work, initially the Contract Price will be deemed to include for all Unit Price Work an
amount equal to the sum of the established unit prices for each separately identified item of Unit
Price Work times the estimated quantity of each item as indicated in the Agreement. The
estimated quantities of items of Unit Price Work are not guaranteed and are solely for the purpose
of comparison of Bids and determining an initial Contract Price. Determinations of the actual
quantities and classifications of Unit Price Work performed by CONTRACTOR will be made by
PROFESSIONAL in accordance with Paragraph 9.10.
11.9.2. Each unit price will be deemed to include an amount considered by
CONTRACTOR to be adequate to cover CONTRACTOR's overhead and profit for each sep-
arately identified item.
11.9.3. Where the quantity of any item of Unit Price Work performed by
CONTRACTOR differs materially and significantly from the estimated quantity of such item
indicated in the Agreement and there is no corresponding adjustment with respect to any other
item of Work and if CONTRACTOR believes that CONTRACTOR has incurred additional
expense as a result thereof, CONTRACTOR may make a claim for an increase in the Contract
Price in accordance with Article 11 if the parties are unable to agree as to the amount of any such
Increase.
GC-38
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 12--CHANGE OF CONTRACT TIME
12.1. The Contract Time may only be changed by a Change Order. Any request for an
extension in the Contract Time shall be made in writing and delivered to PROFESSIONAL and
Project Manager within seven (7) calendar days of the occurrence first happening and.resulting in
the claim. Written supporting data will be submitted to PROFESSIONAL and Project Manager
within fifteen (15) calendar days after such occurrence unless the Project Manager allows
additional time. All claims submitted by CONTRACTOR for adjustments to the Contract Time
must set forth in detail the reasons for and causes of the delay and clearly indicate why the subject
delay was beyond CONTRACTOR's control or fault.
12.2. If CONTRACTOR is delayed at any time in the performance, progress,
commencement, or completion of the Work by any act or neglect of OWNER or
PROFESSIONAL, or by an employee of either, or by any separate CONTRACTOR employed by
OWNER, or by changes ordered in the Work, or by labor disputes, fire, unavoidable casualties,
utility conflicts which could not have been identified or foreseen by CONTRACTOR using
reasonable diligence, or any causes beyond CONTRACTOR's control or fault, then the Contract
Time shall be extended by Change Order for such reasonable time as OWNER may determine.
CONTRACTOR shall be entitled to an extension of time for such causes only for the number of
days of delay which OWNER may determine to be due solely to such causes and only to the
extent such occurrences actually delay the completion of the Work and then only if
CONTRACTOR shall have strictly complied with all the requirements of the Contract
Documents. Provided, however, notwithstanding anything in the Contract Documents to the
contrary, no interruption, interference, inefficiency, suspension or delay in the performance,
progress, commencement or completion of the Work for any cause whatsoever, including those
for which OWNER or PROFESSIONAL may be responsible in whole or in part, shall relieve
CONTRACTOR of its duty to perform or give rise to any right to damages or additional
compensation from OWNER. CONTRACTOR's sole and exclusive remedy against OWNER for
interruption, interference, inefficiency, suspension or delay of any aspect of the Work shall be the
right to seek an extension to the Contract Time in accordance with the procedures set forth
herein.
GC-39
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 13--W ARRANTY AND GUARANTEE; TESTS AND INSPECTIONS:
CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK
Warranty and Guarantee:
13.1. CONTRACTOR warrants and guarantees to OWNER that all materials and
equipment will be new unless otherwise specified and that all work will be of good quality,
performed in a workmanlike manner, free from faults or defects, and in accordance with the
requirements of the Contract Documents and any inspections, tests, or approvals referred to in
this Article. All unsatisfactory Work, all faulty Work and all Work not conforming to the
requirements of the Contract Documents or such inspections, tests, approvals, or all applicable
building, construction and safety requirements shall be considered defective. Notice of all defects
shall be given to CONTRACTOR by PROFESSIONAL. All defective work, whether or not in
place, may be rejected, corrected, or accepted as provided in this Article.
Access to Work:
13.2. For the duration of the Work, PROFESSIONAL and its representatives, other
designated representatives of OWNER, and authorized representatives of any regulatory agency
shall at all times be given access to the Work. CONTRACTOR shall provide proper facilities for
such access and observation of the Work and also for any inspection or testing by others.
Tests and Inspections:
13.3. If the Contract Documents, laws, ordinances, rules, regulations or orders of any
public authority having jurisdiction require any Work to specifically be inspected, tested, or
approved by someone other than CONTRACTOR, CONTRACTOR shall give PROFESSIONAL
timely notice of readiness therefore.
13.4. The testing firm(s) (if assigned by OWNER to this Work) and all such inspections,
tests, or approvals provided for by OWNER shall be identified in writing by PROFESSIONAL to
CONTRACTOR. All other inspections, tests or approvals shall be at CONTRACTOR's expense
including additional expenses for inspection and tests required as a result of delays by
CONTRACTOR or hours worked in excess of 40 hours per week. For all required inspections,
tests, and approvals on any Work prepared, performed, or assembled away from the site,
CONTRACTOR will furnish PROFESSIONAL with the required Certificates of Inspection,
testing, or approval. All such tests will be in accordance with the methods prescribed by the
American Society for Testing and Materials or such other applicable organizations as may be
required by law or the Contract Documents. Materials or Work in place that fail to pass
acceptability tests shall be retested at the direction of PROFESSIONAL and at CONTRACTOR's
expense.
13.5. All inspections, tests or approvals other than those required by Laws or Regulations
of any public body having jurisdiction shall be performed by organizations acceptable to OWNER
and CONTRACTOR (or by PROFESSIONAL if so specified).
13.6. If any Work (including the work of others) that is to be inspected, tested or
approved is covered without written concurrence of PROFESSIONAL, it must, if requested by
GC-40
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
PROFESSIONAL, be uncovered for observation. Such uncovering shall be at CONTRACTOR's
expense unless CONTRACTOR has given PROFESSIONAL timely notice of CONTRACTOR's
intention to cover the same and PROFESSIONAL has not acted with reasonable promptness in
response to such notice.
13.7. Neither observations by PROFESSIONAL or Project Manager nor inspections,
tests, or approvals by persons other than CONTRACTOR shall relieve CONTRACTOR of its
obligations to perform the Work in accordance with the requirements of the Contract Documents.
Uncovering Work:
13.8. If any Work required to be inspected, tested or approved is covered prior thereto
without the prior written approval of PROFESSIONAL, or if any Work' is covered contrary to the
request of PROFESSIONAL, the Work shall, if requested by PROFESSIONAL, be uncovered
for observation, inspection, testing or approval and replaced at CONTRACTOR's expense.
13.9. If PROFESSIONAL considers it necessary or advisable that covered Work be
observed by PROFESSIONAL or inspected or tested by others. CONTRACTOR, at
PROFESSIONAL's request, shall uncover, expose or otherwise make available for observation,
inspection or testing as PROFESSIONAL may require, that portion of the Work in question,
furnishing all necessary labor, material and equipment. If it is found that such Work is defective,
CONTRACTOR shall bear all direct, and consequential costs of such uncovering, exposure,
observation, inspection and testing and of satisfactory reconstruction, (including but not limited to
fees and charges of PROFESSIONALs, architects, attorneys and other PROFESSIONALs), and
OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are
unable to agree as to the amount thereof, may make a claim therefor as provided in Article 11. If,
however, such Work is not found to be defective, CONTRACTOR shall be allowed an increase in
the Contract Price, or an extension of the Contract Time, or both, directly attributable to such
uncovering, exposure, observation, inspection, testing and reconstruction; and, if the parties are
unable to agree as to the amount or extent thereof, CONTRACTOR may make a claim therefor as
provided in Articles 11 and 12.
Owner May Stop the Work:
13.10. When Work is defective or when CONTRACTOR fails to supply sufficient skilled
workmen or suitable materials or equipment, or make prompt payments to Subcontractors for
labor, materials, or equipment, or if CONTRACTOR violates any provisions of these Contract
Documents, OWNER may order CONTRACTOR to stop the Work until the cause for such order
has been eliminated. However, this right of OWNER to stop the Work shall not give rise to any
duty on the part of OWNER to exercise this right for the benefit of CONTRACTOR or any other
party. CONTRACTOR shall have no right to claim an increase in the Contract Price or Contract
Time or other damages for a stop work order under this paragraph.
Correction or Removal of Defective Work:
13 .11. When directed by PROFESSIONAL, CONTRACTOR shall promptly, without
cost to OWNER and as specified by PROFESSIONAL, either correct the defective Work
whetner fabricated, installed, or completed, or remove it from the site and replace it with non
GC-4l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
defective Work. If CONTRACTOR does not correct such defective Work or remove and replace
such defective Work within a reasonable time, all as specified in a written notice from
PROFESSIONAL, OWNER may have the deficiency corrected. All direct and indirect costs of
such correction shall be paid by CONTRACTOR or deducted from payment to CONTRACTOR.
CONTRACTOR will also bear the expense of correcting or removing and replacing all Work of
others destroyed or damaged by the correction, removal, or replacement of the defective Work.
One Year Correction Period:
13.12. If, after approval offinal payment and prior to the expiration of one year after the
date of substantial completion or such longer period of time as may be prescribed by law or by the
terms of any applicable special guarantee required by the Contract Documents, any Work or
materials are found to be defective, incomplete, or otherwise not in accordance with the Contract
Documents, CONTRACTOR shall promptly, without cost to OWNER and in accordance with
OWNER's written instructions, either correct such defective Work, or if it has been rejected by
OWNER, remove it from the Site and replace it with non-defective Work. If CONTRACTOR
does not promptly comply with the terms of such instructions, OWNER may have the defective
Work corrected, removed, or replaced. All direct, indirect and consequential costs of such
removal and replacement (including but not limited to fees and charges of engineers, architects,
attorneys and other PROFESSIONALs) will be paid by CONTRACTOR.
Acceptance of Defective Work:
13.13. If, instead of requiring correction or removal and replacement of defective Work,
OWNER (and, prior to PROFESSIONAL's recommendation of final payment, also
PROFESSIONAL) prefers to accept it, OWNER may do so. CONTRACTOR shall bear all
direct, indirect and consequential costs attributable to OWNER's evaluation of and determination
to accept such defective Work (such costs to be approved by PROFESSIONAL as to
reasonableness and to include but not be limited to fees and charges of PROFESSIONALs,
architects, attorneys and other PROFESSIONALs). If any such acceptance occurs prior to
PROFESSIONAL's recommendation of final payment, a Change Order will be issued
incorporating the necessary revisions in the Contract Documents with respect to the Work and
OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the panics are
unable to agree as to the amount thereof. OWNER may make a claim therefor as provided in
Article 11. If the acceptance occurs after such recommendation, an appropriate amount will be
paid by CONTRACTOR to OWNER.
OWNER May Correct Defective Work:
13.14. If CONTRACTOR fails within a reasonable time after written notice of
PROFESSIONAL to proceed to correct and to correct defective Work or to remove and replace
rejected Work as required by PROFESSIONAL in accordance with paragraph 13.11, or if
CONTRACTOR fails to perform the Work in accordance with the Contract Documents, or if
CONTRACTOR falls to comply with any other provision of the Contract Documents, OWNER
may, after seven days' written notice to CONTRACTOR, correct and remedy any such deficiency.
In exercising the rights and remedies under this paragraph OWNER shall proceed expeditiously,
to the extent necessary to complete corrective and remedial action, OWNER may exclude
CONTRACTOR from all or part of the site, take possession of all or part of the Work, and
GC-42
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
suspend CONTRACTOR's services related thereto, take possession of CONTRACTOR's tools,
appliances, construction equipment and machinery at the site and incorporate in the Work all
materials and equipment stored at the site or for which OWNER has paid CONTRACTOR but
which are stored elsewhere. CONTRACTOR shall allow OWNER, OWNER's representatives,
agents and employees such access to the site as may be necessary to enable OWNER to exercise
the rights and remedies under this paragraph. All direct, indirect and consequential costs of
OWNER in exercising such rights and remedies will be charged against CONTRACTOR in an
amount approved as to reasonableness by PROFESSIONAL, and a Change Order will be issued
incorporating the necessary revisions in the Contract Documents with respect to the Work, and
OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are
unable to agree as to the amount thereof, OWNER may make a claim therefor as provided in
Article 11. Such direct, indirect and consequential costs will include but not be limited to fees and
charges of PROFESSIONALs, architects, attorneys and other PROFESSIONALs, all court costs
and all costs of repair and replacement of work of others destroyed or damaged by correction,
removal or replacement of CONTRACTOR's defective Work. CONTRACTOR shall not be
allowed an extension of the Contract Time because of any delay in performance of the Work
attributable to the exercise by OWNER of OWNER's rights and remedies hereunder.
Neglected Work by CONTRACTOR
13 .15. If CONTRACTOR neglects to execute the Work in accordance with the Contract
Documents, including any requirements of the progress schedule, PROFESSIONAL may direct
CONTRACTOR to submit a recovery plan and take specific corrective actions including, but not
limited to, employing additional workmen, and/or equipment, and working extended hours and
additional days, all at no cost to OWNER in order to put the Work back on schedule. If
CONTRACTOR fails to correct the deficiency or take appropriate corrective action, OWNER
may terminate the contract or CONTRACTOR's right to proceed with that portion of Work and
have the Work done by others. The cost of completion under such procedure shall be charged
against CONTRACTOR. A Change Order shall be issued incorporating the necessary revisions in
the Contract Documents, including an appropriate reduction in the Contract Price. If the
payments due CONTRACTOR are not sufficient to cover such amount, CONTRACTOR shall
pay the difference to OWNER.
13 .16. Should CONTRACTOR work overtime, weekends or holidays to regain the
schedule, all costs to OWNER of associated inspection, construction management and resident
PROFESSIONALs shall be identified to CONTRACTOR and the Contract Price reduced by a
like amount via Change Order.
GC-43
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
best of PROFESSIONAL's knowledge, information and belief, the quality' of the Work is in
accordance with the Contract Documents subject to an evaluation of the Work as a functioning
whole prior to or upon Substantial Completion, to the results of any subsequent tests called for in
the Contract Documents, to a final determination of quantities and classifications for Unit Price
Work under paragraph 9. 10. and to any other qualifications stated in the recommendatiofr"'-: and
that CONTRACTOR is entitled to payment of the amount recommended. However, by
recommending any such payment PROFESSIONAL will not thereby be deemed to have
represented that exhaustive or continuous on-site inspections have been made to check the quality
or the quantity of the Work beyond the responsibilities specifically assigned to PROFESSIONAL
in the Contract Documents or that there may not be other matters or issues between the parties
that might entitle CONTRACTOR to be paid additionally by OWNER or OWNER to withhold
payment to CONTRACTOR.
14.6. PROFESSIONAL's recommendation of final payment will constitute an additional
representation by PROFESSIONAL to OWNER that the conditions precedent to CONTRAC-
TOR's being entitled to final payment as set forth in paragraph 14.13 have been fulfilled.
14.7. PROFESSIONAL may refuse to recommend the whole or any part of any payment
if, in PROFESSIONAL's opinion, it would be incorrect to make such representations to OWNER.
PROFESSIONAL may also refuse to recommend any such payment, or, because of subsequently
discovered evidence or the results of subsequent inspections or tests, nullify any such payment
previously recommended, to such extent as may be necessary in PROFESSIONAL's opinion to
protect OWNER from loss because:
14.7.1. the Work is defective, or completed Work has been damaged requiring correction
or replacement.
14.7.2. the Contract Price has been reduced by Written Amendment or Change Order.
14.7.3. OWNER has been required to correct defective Work or complete Work in
accordance with paragraph 13. 14. or
14.7.4. of PROFESSIONAL's actual knowledge of the occurrence of any of the events
enumerated in paragraphs 15.2.1 through 15.2.9 inclusive.
OWNER may refuse to make payment of the full amount recommended by PROFESSIONAL
because claims have been made against OWNER on account of CONTRACTOR's performance or
furnishing of the Work or Liens have been filed in connection with the Work or there are other
items entitling OWNER to a set-off against the amount recommended, but OWNER must give
CONTRACTOR immediate written notice (with a copy to PROFESSIONAL) stating the reasons
for such action.
GC-45
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 14-PAYMENTS TO CONTRACTOR AND COMPLETION
Schedule of Values:
14.1. The schedule of values established as provided in 2.9 will serve as the basis for
progress payments and will be incorporated into a form of application for Payment acceptable to
Project Manager. Progress payments on account of Unit Price Work will be based on the number
of units completed.
Application for Progress Payment:
14.2. At least twenty (20) calendar days before the date established for each progress
payment (but not more often than once a month), CONTRACTOR shall submit to
PROFESSIONAL for review an application for Payment filled out and signed by CONTRACTOR
covering the work completed as of the date of the application and accompanied by such
supporting documentation as is required by the Contract Documents. If payment is requested on
the basis of materials and equipment not incorporated in the Work but delivered and suitably
stored at the site or at another location agreed to in writing, the Application for Payment shall
also be accompanied by a bill of sale, invoice or other documentation warranting that OWNER
has received the materials and equipment free and clear of all liens and evidence that the materials
and equipment are covered by appropriate property insurance and other arrangements to protect
OWNER's interest therein, all of which will be satisfactory to OWNER. Payment is subject to a
ten percent (10%) retainage that will be held until the final payment or acceptance by OWNER
The amount of retainage with respect to progress payments will be as stipulated in the Agreement.
CONTRACTOR's Warranty of Title:
14.3. CONTRACTOR warrants and guarantees that title to all Work, materials and
equipment covered by any Application for Payment, whether incorporated in the Project or not,
will pass to OWNER no later than the time of payment free and clear of all Liens.
Review of Applications for Progress Payment:
14.4. PROFESSIONAL will, within ten (10) calendar days after receipt of each
Application for Payment, either indicate in writing a recommendation of payment and present the
application to OWNER, or return the application to CONTRACTOR indicating in writing
PROFESSIONAL's reasons for refusing to recommend payment. In the latter case,
CONTRACTOR may make the necessary corrections and resubmit the application. OWNER
shall, within thirty-one calendar days of presentation to him of the application for payment with
PROFESSIONAL's recommendation of the amount for payment, pay CONTRACTOR amount
recommended.
14.5. PROFESSIONAL's recommendation of any payment requested in an Application
for Payment will constitute a representation by PROFESSIONAL to OWNER, based on PROF-
ESSIONAL's on-site observations of the Work in progress as an experienced and qualified design
PROFESSIONAL and on PROFESSIONAL's review of the Application for Payment and the
accompanying data and schedules that the Work has progressed to the point indicated; that, to the
GC-44
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Substantial Completion:
14.8. When CONTRACTOR considers the entire Work ready for its intended use
CONTRACTOR shall notify OWNER and PROFESSIONAL in writing that the entire Work is
substantially complete (except for items specifically listed by CONTRACTOR as incomplete) and
request that PROFESSIONAL issue a certificate of Substantial Completion. Within a reasonable
time thereafter, OWNER, CONTRACTOR and PROFESSIONAL shall make an inspection of the
Work to determine the status of completion. If PROFESSIONAL does not consider the Work
substantially complete, PROFESSIONAL will notify CONTRACTOR in writing giving the
reasons therefor. If PROFESSIONAL considers the Work substantially complete,
PROFESSIONAL will prepare and deliver to OWNER a tentative certificate of Substantial
Completion which shall fix the date of Substantial Completion. There shall be attached to the
certificate a tentative list of items to be completed or corrected before final payment. OWNER
shall have seven days after receipt of the tentative certificate during which to make written
objection to PROFESSIONAL as to any provisions of the certificate or attached list. If, after
considering such objections. PROFESSIONAL concludes that the Work is not substantially
complete, PROFESSIONAL will within fourteen days after submission of the tentative certificate
to OWNER notify CONTRACTOR in writing. stating the reasons therefor. If, after consideration
of OWNER's objections, PROFESSIONAL considers the Work substantially complete,
PROFESSIONAL will within said fourteen days execute and deliver to OWNER and
CONTRACTOR a definitive certificate of Substantial Completion (with a revised tentative list of
items to be completed or corrected) reflecting such changes from the tentative certificate as
PROFESSIONAL believes justified after consideration of any objections from OWNER. At the
time of delivery of the tentative certificate of Substantial Completion PROFESSIONAL will
deliver to OWNER and CONTRACTOR a written recommendation as to division of
responsibilities pending final payment between OWNER and CONTRACTOR with respect to
security, operation, safety, maintenance, heat, utilities, insurance and warranties. Unless OWNER
and CONTRACTOR agree otherwise in wilting and so inform PROFESSIONAL prior to
PROFESSIONAL's issuing the definitive certificate of Substantial Completion,
PROFESSIONAL's aforesaid recommendation will be binding on OWNER and CONTRACTOR
until final payment.
14.9. OWNER shall have the right to exclude CONTRACTOR from the Work after the
date of Substantial Completion, but OWN ER shall allow CONTRACTOR reasonable access to
complete or correct items on the tentative list.
Partial Utilization:
14.10. Use by OWNER at OWNER's option of any substantially completed part of the
Work which (i) has specifically been identified in the Contract Documents, or (ii) OWNER,
PROFESSIONAL, and CONTRACTOR agree constitutes a separately functioning and usable
part of the Work that can be used by OWNER for its intended purpose without significant
interference with CONTRACTOR's performance of the remainder of the Work, may be
accomplished prior to Substantial Completion of all the Work subject to the following.
14.10.1. OWNER at any time may request CONTRACTOR in writing to permit OWNER
to use any such part of the Work which OWNER believes to be ready for its intended use and
substantially complete. If CONTRACTOR agrees, CONTRACTOR will certify to OWNER and
GC-46
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
PROFESSIONAL that said part of the Work is substantially complete and request
PROFESSIONAL to issue a certificate of Substantial Completion for that part of the Work.
CONTRACTOR at any time may notify, OWNER and PROFESSIONAL in writing that
CONTRACTOR considers any such part of the Work ready for its intended use and substantially
complete and request PROFESSIONAL to issue a certificate of Substantial Completion for that
part of the Work. Within a reasonable time after either such request, OWNER, CONTRACTOR
and PROFESSIONAL shall make an inspection of that part of the Work to determine its status of
completion. If PROFESSIONAL does not consider that part of the Work to be substantially
complete, PROFESSIONAL will notify. OWNER and CONTRACTOR in writing giving the
reasons therefor. If PROFESSIONAL considers that part o(the Work to be substantially
complete, the provisions of paragraphs 14.8 and 14.9 will apply with respect to certification of
. Substantial Completion of that part of the Work and the division of responsibility in respect
thereof and access thereto.
14.10.2. OWNER may at any time request CONTRACTOR in writing to permit OWNER
to take over operation of any such part of the Work although it is not substantially complete. A
copy of such request will be sent to PROFESSIONAL and within a reasonable time thereafter
OWNER, CONTRACTOR and PROFESSIONAL shall make an inspection of that part of the
Work to determine its status of completion and will prepare a list of the items remaining to be
completed or corrected thereon before final payment. If CONTRACTOR does not object in writ-
ing to OWNER and PROFESSIONAL that such part of the Work is not ready for separate
operation by OWNER, PROFESSIONAL will finalize the list of items to be completed or
corrected and will deliver such list to OWNER and CONTRACTOR together with a written
recommendation as to the division of responsibilities pending final payment between OWNER and
CONTRACTOR with respect to security, operation, safety, maintenance, utilities, insurance,
warranties and guarantees for that part of the Work which will become binding upon OWNER
and CONTRACTOR at the time when OWNER takes over such operation (unless they shall have
otherwise agreed in writing and so informed PROFESSIONAL). During such operation and prior
to Substantial Completion of such part of the Work, OWNER shall allow CONTRACTOR
reasonable access to complete or correct items on said list and to complete other related Work.
14. 10.3. No occupancy or separate operation of part of the Work will be accomplished
prior to compliance with the requirements of paragraph 5. 15 in respect of property insurance.
14.10.4. OWNER, may at its discretion, reduce the amount of retainage subject to
Beneficial Occupancy.
Final Inspection:
14.11. Upon written notice from CONTRACTOR that the entire Work or an agreed
portion thereof is complete, PROFESSIONAL will make a final inspection with OWNER and
CONTRACTOR and will notify CONTRACTOR in writing of all particulars in which this
inspection reveals that the Work is incomplete or defective. CONTRACTOR shall immediately
take such measures as are necessary to remedy such deficiencies.
GC-47
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Final Application for Payment:
14.12. After CONTRACTOR has completed all such corrections to the satisfaction of
PROFESSIONAL and OWNER and delivered in accordance with the Contract Documents all
maintenance and operating instructions, schedules, guarantees, bonds, certificates or other
evidence of insurance required by 5.2, certificates of inspection, marked-up record documents and
other documents, CONTRACTOR may make application for final payment following the
procedure for progress payments. The final Application for Payment shall be accompanied
(except as previously delivered) by: (i) all documentation called for in the Contract Documents,
including but not limited to the evidence of insurance required, (ii) consent of the surety, if any, to
final payment, and (iii) complete and legally effective releases or waivers (satisfactory to
OWNER) of all liens arising out of or filed in connection with the Work. In lieu of such releases
or waivers of liens and as approved by County, CONTRACTOR may furnish receipts or release in
full and an affidavit of CONTRACTOR that (i) the releases and receipts include all labor,
services, material and equipment for which a lien could be filed, and (ii) all payrolls, material and
equipment bills and other indebtedness connected with the Work for which OWNER or
OWNER's property might in any way be responsible have been paid or otherwise satisfied. If any
Subcontractor or supplier fails to furnish such a release or receipt in full, CONTRACTOR may
furnish a bond or other collateral satisfactory to OWNER to indemnify OWNER against any lien.
14.12.1. No application for final payment will be accepted by OWNER until approved as-
built documents by CONTRACTOR are accepted and approved by PROFESSIONAL.
14,12.2. Notwithstanding any other provision of these contract documents to the
contrary, OWNER and PROFESSIONAL are under no duty or obligation whatsoever to any
vendor, materials provider, Subcontractor, laborer or other party to ensure that payments due and
owing by CONTRACTOR to any of them are or will be made. Such parties shall rely only on
CONTRACTOR's surety bonds for remedy of nonpayment by him. CONTRACTOR agrees to
defend and resolve all claims made by Subcontractors, indemnifying OWNER and
PROFESSIONAL for all claims arising from or resulting from Subcontractor or supplier or
material men or laborer services in connection with this project.
14.12.3. General Indemnity: CONTRACTOR shall indemnify OWNER and
PROFESSIONAL for any damages sustained including lost profits resulting from
CONTRACTOR's failure or refusal to perform the work required by these contract documents.
Final Payment and Acceptance:
14.13. If, on the basis of PROFESSIONAL's observation of the Work during
construction and final inspection, and PROFESSIONAL's review of the final Application for
Payment and accompanying documentation as required by the Contract Documents,
PROFESSIONAL is satisfied that the Work has been completed and CONTRACTOR's other
obligations under the Contract Documents have been fulfilled, PROFESSIONAL will, within ten
(10) working days after receipt of the final Application for Payment, indicate in writing
PROFESSIONAL's recommendation of payment and present the Application to OWNER for
payment. At the same time PROFESSIONAL will also give written notice to OWNER and
CONTRACTOR that the Work is acceptable subject to the provisions of 14.6. Otherwise,
PROFESSIONAL will return the application to CONTRACTOR, indicating in writing the reasons
GC-48
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
for refusing to recommend final payment, in which case CONTRACTOR shall make the necessary
corrections and resubmit the Application. After the presentation to OWNER of the application
and accompanying documentation, in appropriate form and substance and with
PROFESSIONAL's recommendation and notice of acceptability, the amount recommended by
PROFESSIONAL will become due and will be paid by OWNER to CONTRACTOR.
14,14. If, through no fault of CONTRACTOR, final completion of the Work is
significantly delayed and if PROFESSIONAL so confirms, OWNER shall, upon receipt of
CONTRACTOR's final Application for Payment and recommendation of PROFESSIONAL, and
without terminating the Agreement, make payment of the balance due for that portion of the
Work fully completed and accepted. If the remaining balance to be held by OWNER for Work
not fully completed or corrected is less than the retainage stipulated in the Contract, and if bonds
have been furnished as required in Article 5, the written consent of the surety to the payment of
the balance due for that portion of the Work fully completed and accepted shall be submitted by
CONTRACTOR to PROFESSIONAL with the application for such payment. Such payment shall
be made under the terms and conditions governing final payment, except that it shall not
constitute a waiver of claims.
CONTRACTOR's Continuing Obligation:
14.15. CONTRACTOR1s obligation to perform and complete the Work in accordance
with the Contract Documents shall be absolute. Neither recommendation of any progress or final
payment by PROFESSIONAL, nor the issuance of a certificate of Substantial Completion, nor
any payment by OWNER to CONTRACTOR under the Contract Documents, nor any use or
occupancy of the Work or any part thereof by OWNER, nor any act of acceptance by OWNER
nor any failure to do so, nor any review and approval of a Shop Drawing or sample submission,
nor the issuance of a notice of acceptability by PROFESSIONAL pursuant to paragraph 14.13.
nor any correction of defective Work by OWNER will constitute an acceptance of Work not in
accordance with the Contract Documents or a release of CONTRACTOR1s obligation to perform
the Work in accordance with the Contract Documents (except as provided in paragraph 14.16).
Waiver of Claims:
14.16. The making and acceptance of final payment will constitute:
14.16.1. A waiver of all claims by OWNER against CONTRACTOR, except claims
arising from unsettled liens, from defective Work appearing after final inspection pursuant to
14.11 from failure to comply with the Contract Documents or the terms of any special guarantees
specified therein, or from CONTRACTOR's continuing obligations under the Contract
Documents; and
14.16.2. A waiver of all claims by CONTRACTOR against OWNER other than those
previously made in writing and still unsettled.
GC-49
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 15--SUSPENSION OF WORK AND
TERMINATION
Owner May Suspend Work:
15.1. OWNER may, at any time and without cause, suspend the Work or any portion
thereof for a period of not more than ninety days by notice in wilting to CONTRACTOR and
PROFESSIONAL which will fix the date on which Work will be resumed. CONTRACTOR shall
resume the Work on the date so fixed. CONTRACTOR shall be allowed an adjustment in the
Contract Price or an extension of the Contract Time, or both, directly attributable to any
suspension if CONTRACTOR makes an approved claim therefor as provided in Articles 11
and 12.
Termination For Cause:
15.2. Upon the occurrence of any one or more of the following events:
15.2. 1. if CONTRACTOR commences a voluntary case under any chapter of the
Bankruptcy Code (Title 11, United States Code), as now or hereafter in effect, or if
CONTRACTOR takes any equivalent or similar action by filing a petition or otherwise under any
other federal or state law in effect at such time relating to the bankruptcy or insolvency;
15.2.2. if a petition is filed against CONTRACTOR under any chapter of the Bankruptcy
Code as now or hereafter in effect at the time of filing, or if a petition is filed seeking any such
equivalent or similar relief against CONTRACTOR under any other federal or state law in effect
at the time relating to bankruptcy or insolvency;
15.2.3. if CONTRACTOR makes a general assignment for the benefit of creditors;
15.2.4. if a trustee, receiver, custodian or agent of CONTRACTOR is appointed under
applicable law or under contract, whose appointment or authority to take charge of property of
CONTRACTOR is for the purpose of enforcing a Lien against such property or for the purpose
of general administration of such property for the benefit of CONTRACTOR's creditors;
15.2.5. if CONTRACTOR admits in writing an inability to pay its debts generally, as they
become due;
15.2.6. if CONTRACTOR fails to perform the Work in accordance with the Contract
Documents (including, but not limited to, failure to supply sufficient skilled workers or suitable
materials or equipment or failure to adhere to the progress schedule established under paragraph
2.9 as revised from time to time);
15.2.7. if CONTRACTOR disregards Laws or Regulations of any public body having
jurisdiction;
15.2.8. if CONTRACTOR disregards the authority of PROFESSIONAL; or
15.2.9. if CONTRACTOR otherwise violates in any substantial way any provisions of the
Contract Documents,
GC-50
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
OWNER may, after giving CONTRACTOR (and the surety, if there be one) seven days' written
notice and to the extent permitted by Laws and Regulations, terminate the services of
CONTRACTOR, exclude CONTRACTOR from the site and take possession of the Wark and of
all CONTRACTOR's tools, appliances, construction equipment and machinery at the site and use
the same to the full extent they could be used by CONTRACTOR (without liability to
CONTRACTOR for trespass or conversion), incorporate in the Work all materials and equipment
stored at the site or for which OWNER has paid CONTRACTOR but which are stored elsewhere,
and finish the Work as OWNER may deem expedient. In such case CONTRACTOR shall not be
entitled to receive any further payment until the Work is finished. If the unpaid balance of the
Contract Price exceeds the direct, indirect and consequential costs of completing the Work
(including but not limited to fees and charges of PROFESSIONALs, architects, attorneys and
other PROFESSIONALs and court and arbitration costs) such excess will be paid to
CONTRACTOR If such costs exceed such unpaid balance, CONTRACTOR shall pay the
difference to OWNER. Such costs incurred by OWNER will be approved as to reasonableness by
PROFESSIONAL and incorporated in a Change Order, but when exercising any rights or
remedies under this paragrapn OWNER shall not be required to obtain the lowest price for the
Work performed.
15.3. In the event OWNER terminates the contract for cause and it is subsequently
judicially determined that there was no cause for termination, the termination for convenience
provision will be the means for disposition of the balance of the contract obligations.
Termination for Convenience
15.4. Upon seven working days' written notice to CONTRACTOR and
PROFESSIONAL, OWNER may, without cause and without prejudice to any other right or
remedy of OWNER, elect to terminate the Contract. In such case, CONTRACTOR shall be paid
(without duplication of any items):
15.4.1. For completed and acceptable Work executed in accordance with the Contract
Documents prior to the effective date of termination, including fair and reasonable sums for
overhead and profit on such Work;
15.4.2. For expenses sustained prior to the effective date of termination in performing
services and furnishing labor, materials or equipment as required by the Contract Documents in
connection with uncompleted Work, plus fair and reasonable sums for overhead and profit on
such expenses;
15.4.3. For all claims, costs, losses and damages incurred in settlement of terminated
contracts with Subcontractors, suppliers and others; and
15.4.4. For reasonable expenses directly attributable to termination.
CONTRACTOR shall not be paid on account of loss of anticipated profits or revenue or other
economic loss arising out of or resulting from such termination.
15.5. Where CONTRACTOR's services have been so terminated by OWNER, the
termination will not affect any rights or remedies of OWNER against CONTRACTOR then
GC-51
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
existing or which may thereafter accrue. Any retention or payment of moneys due
CONTRACTOR by OWNER will not release CONTRACTOR from liability.
CONTRACTOR May Stop Work or Terminate:
15.6. If through no act or fault of CONTRACTOR, the Work is suspended for a period
of more than ninety calendar days by OWNER or under an order of court or, other public
authority, or PROFESSIONAL fails to act on any Application for Payment within thirty days after
it is submitted or OWNER fails for thirty-one days to pay CONTRACTOR any sum finally
determined to be due, then CONTRACTOR may upon seven working days' written notice to
OWNER and PROFESSIONAL and provided OWNER or PROFESSIONAL did not remedy
such suspension or failure within that time, terminate the Agreement and recover from OWNER
payment on the same terms as provided in 15.2. In lieu ofterminating the Agreement and without
prejudice to any other right or remedy, if PROFESSIONAL has failed to act on an Application for
Payment within thirty days after it is submitted, or OWNER has failed for thirty-one days after it
is submitted, or OWNER has failed for thirty-one calendar days to pay CONTRACTOR any sum
finally determined to be due, CONTRACTOR may upon seven day's written notice to OWNER
and PROFESSIONAL stop the Work until payment of all such amounts due CONTRACTOR,
including interest thereon. The provisions of this paragraph are not intended to preclude
CONTRACTOR from making claim under Articles 11 and 12 for an increase in Contract Price or
Contract Times or otherwise for expenses or damage directly attributable to CONTRACTOR's
stopping Work as permitted by this paragraph. The provisions of this paragraph shall not relieve
CONTRACTOR of the obligations under paragraph 6.30 to carry on the Work in accordance
with the progress schedule and without delay during disputes and disagreements with OWNER
GC-52
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 16--DISPUTE RESOLUTION
16. 1. All disputes arising under this Contract or its interpretation whether involving law
or fact or both, or extra work, and all claims for alleged breach of contract shall within ten (10)
working days of the commencement of the dispute be presented by CONTRACTOR to OWNER
for decision. All papers pertaining to claims shall be filed in quadruplicate. Such notice need not
detail the amount of the claim but shall state the facts surrounding the claim in sufficient detail to
identify the claim, together with its character and scope. In the meantime, CONTRACTOR shall
proceed with the Work as directed. Any claim not presented within the time limit specified in this
paragraph shall be deemed to have been waived, except that if the claim is of a continuing
character and notice of the claim is not given within ten (10) working days of its commencement,
the claim will be considered only for a period commencing ten (10) working days prior to the
receipt by OWNER of notice thereof Each decision by OWNER will be in writing and will be
mailed to CONTRACTOR by registered or certified mail, return receipt requested, directed to his
last known address.
16.2 All claims, disputes and other matters in question between OWNER and
CONTRACTOR arising out of, or relating to, the Contract Documents or the breach thereof shall
be decided under Georgia Law in the Superior Court of Richmond County, Georgia.
CONTRACTOR by execution of the Contract consents to jurisdiction and venue in the Superior
Court of Richmond County, Georgia, and waives any right to contest same.
GC-53
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
ARTICLE 17-MISCELLANEODS
Giving Notice:
17.1. Whenever any provision of the Contract Documents requires the giving of written
notice, it will be deemed to have been validly given if delivered in person to the individual or to a
member of the firm or to an officer of the corporation for whom it is intended, or if delivered at or
sent by registered or certified mail, postage prepaid, to the last, business address known to the
giver of the notice.
Computation of Time:
17.2.1. When any period oftime is referred to in the Contract Documents by days, it will
be computed to exclude the first and include the last day of such period. If the last day of any
such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the
applicable jurisdiction, such day will be omitted from the computation.
17.2.2. A calendar day of twenty-four hours measured from midnight to the next midnight
shall constitute a day.
General:
17.3. Should OWNER or CONTRACTOR suffer injury or damage to person or property
because of any error, omission or act of the other party or of any of the other party's employees or
agents or others for whose acts the other party is legally liable, claim should be made in writing to
the other party within a reasonable time of the first observance of such injury or damage. The
provisions of this paragraph 17.3 shall not be construed as a substitute for or a waiver of the pro-
visions of any applicable statute of limitations or repose.
17.4. The duties and obligations imposed by these General Conditions and the rights and
remedies available hereunder to the parties hereto, and, in particular but without limitation, the
warranties, guarantees and obligations imposed upon CONTRACTOR by paragraphs 6.32, 13.1,
13.12, 13.14, 14.3 and 15.2 and all of the rights and remedies available to OWNER and
PROFESSIONAL thereunder, are in addition to, and are not to be construed in any way as a
limitation of, any rights and remedies available to any or all of them which are otherwise imposed
or available by Laws or Regulations, by special warranty or guarantee or by other provisions of
the Contract Documents, and the provisions of this paragraph will be as effective as if repeated
specifically in the Contract Documents in connection with each particular duty, obligation, right
and remedy to which they apply. All representations, warranties and guarantees made in the
Contract Documents will survive final payment and termination or completion of the Agreement.
17.5. CONTRACTOR shall keep adequate records and supporting documentation
applicable to this Work and Contract. Said records and documentation shall be retained by
CONTRACTOR for a minimum offive (5) years from the date offmal completion or termination
of this Contract. OWNER shall have the right to audit, inspect, and copy all such records and
documentation as often as OWNER deems necessary during the period of the Contract and for a
period of five (5) years thereafter provided, however, such activity shall be conducted only during
normal business hours. OWNER, during this period of time, shall also have the right to obtain a
GC-54
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
copy of and otherwise inspect any audit made at the direction of CONTRACTOR as concerns the
aforesaid records and supporting documentation.
17.6. The Contract Documents are intended by the Parties to, and do, supersede any and
all provisions of the Georgia Prompt Pay Act, O.C.G.A. Section 13-11-1, et seq. In the event any
provision of the Contract Documents are inconsistent with any provision of the Prompt Pay Act,
this provision of the Contract Documents shall control.
17.7. Notwithstanding any provision of the law to the contrary, the parties agree that no
interest shall be due Contractor on any sum held as retainage pursuant to the Contract Documents
and CONTRACTOR specifically waives any claim to same.
Substitutions:
17.8.Notwithstanding any provisiOn of these general conditions, there shall be no
substitutions of materials that are not determined to be equivalent to those indicated or required in
the contract documents without an amendment to the contract.
Sanitary Sewer Overflow Prevention:
17.9. Procedures to Prevent Overflows During Sanitary Sewer Construction
17.9.1 The CONTRACTOR is hereby notified that the discharge of any untreated
wastewater to waters of the State is a violation of Georgia Water Quality Regulations and is
prohibited.
17.9.2 The CONTRACTOR will submit an Emergency Response Plan prior to
beginning work. This plan will include a list of key personnel with 24-hour contact information
who will respond during an emergency situation. The ERP will include estimates of mobilization
time for a response crew to arrive onsite. Any changes to the Emergency Response Plan will be
submitted to the RESIDENT PROJECT REPRESENTATIVE prior to implementation.
17.9.3 In the event bypass pumping is required to facilitate new sewer construction,
bypassing plans and supporting calculations must be submitted to the Augusta Utilities
Department for review prior to establishment of the bypass. All bypass systems will include
complete redundancy in pumping systems, if failure of the primary pumping system could result in
a discharge of untreated wastewater to waters of the State.
17.9.4 Bypass pumping will be monitored continuously by a person knowledgeable in
pump operation and maintenance, if the failure of the bypass pump could result in the discharge of
untreated wastewater to waters of the State.
17.CJ.5 In the event of a discharge of untreated wastewater, the CONTRACTOR will
take the following actions:
Take immediate steps to eliminate or IDllliIDlze the discharge of untreated
wastewater.
GC-55
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August, 2001
Immediately notify the Utilities Department dispatcher (706.796.5000) and the
RESIDENT PROJECT REPRESENTATIVE (contact information will be
provided at the preconstruction conference).
Maintain a chronicle of relevant information regarding the incident including
specific actions taken by the CONTRACTOR and estimates of the discharge
volume.
17.9.6 The RESIDENT PROJECT REPRESENTATIVE will coordinate notification of
the Georgia Environmental Protection Division (800.241.4113) and the Augusta Emergency
Management Agency if appropriate. r
17.9.7 If, in the opinion of the RESIDENT PROJECT REPRESENTATIVE and the
Owner, the CONTRACTOR is not responding to an emergency situation in an appropriate
manner, the Utilities Department will undertake necessary actions to abate an overflow situation.
The cost of these actions will be the responsibility of the CONTRACTOR.
17.9.8 Following a discharge of untreated wastewater, a downstream inspection will be
conducted by the Utilities Department to assess potential mitigation measures that may be
required of the CONTRACTOR
PROGRAM MANAGER:
17.10 The PROGRAM MANAGER for the project is CH2M HILL, 2822 Central
Avenue, Augusta, GA 30909.
The presence or duties of PROGRAM MANAGER's personnel at the construction site, whether
as onsite representatives or otherwise, do not make PROGRAM MANAGER or PROGRAM
MANAGER's personnel in any way responsible for those duties that belong to OWNER and/or
the CONTRACTOR or other entities, and do not relieve the CONTRACTOR or any other entity
of their obligations, duties, and responsibilities, including, but not limited to, all construction
methods, means, techniques" sequences, and procedures necessary for coordinating and
completing all portions of the construction work in accordance with the construction Contract
Documents and any health and safety precautions required by such construction work.
"
PROGRAM MANAGER and PROGRAM MANAGER's personnel have no authority to exercise
any control over any construction contractor or other entity or their employees in connection with
their work or any health or safety precautions and have no duty of inspecting, noting, observing,
correcting, or reporting on health or safety deficiencies of the CONTRACTOR(s) or other entity
or any other persons at the site except PROGRAM MANAGER's own personnel.
The presence of PROGRAM MANAGER's personnel at the construction site is for the purpose
of providing to OWNER a greater degree of confidence that the completed construction work
will conform generally to the construction documents and that the integrity of the design concept
as reflected in the construction documents has been implemented and preserved by the
construction contractor(s). PROGRAM MANAGER neither guarantees the performance of the
construction contractor(s) nor assumes responsibility for construction contractor's failure to
perform work in accordance with the construction documents.
GC-56
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION
SC-Ol.
SC-02.
SC-03.
SC-04.
SC-05.
SC-06.
SC-07.
SC-08.
SC-09.
SC-lO.
SC-ll.
SC-12.
SC-13.
SC-14.
SC-15.
SC-16.
SC-17.
SC-18.
SC-19.
SC-20.
SC-21.
SC-22.
SC-23.
SECTION SC-O
INDEX TO SUPPLEMENTARY CONDITIONS
Scope of the Work
List of Drawings
Bonds
Contractor's Liability Insurance
Protection of the Environment
Temporary Toilets
Plans and Specifications Furnished
Record Drawings
Shop Drawings
Existing Structures
Salvage Material
Referenced Specifications
Construction Order and Schedule
Consulting Engineers
Inspection and Testing of Work
Georgia Prompt Pay Act
City Acceptance
Disputes
Specified Materials
Interest Not Earned on Retainage
Basis of Payment
Compliance with Laws, Codes, Regulations, Etc.
Equivalent Materials
SC-O-l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION SC
SUPPLEMENTARY CONDITIONS
-01. SCOPE OF THE WORK:
The project referred to in the Agreement shall consist of the following major
elements or portion thereof as outlined in each contract.
The construction and installation of the cw.orine booster station, appurtenances
and site improvements at the Morgan Road ground storage tank site.
-02. LIST OF DRAWINGS:
The following drawings, prepared by Cranston, Robertson & Whitehurst, P.C.
comprise the plans for the project.
SHEET NO.
1.
2.
3.
4.
5.
TITLE
DATE
ORIGINAL REVISED
11/05/04
11/05/04
11/05/04
11/05/04
11/05/04
6.
7.
8.
Cover Sheet
Detailed Estimate
Site Plan
Sodium Hypochlorite System Floor Plan
Sodium HypocW.orite System Process and
Instrumentation Diagram
Building Plan and Elevations
Building Sections and Details
Miscellaneous Details
11/05/04
11/05/04
11/05/04
-03. BONDS:
The Contractor will include in the lump sum payment for Lump Sum Construction
the cost of his performance and payment bonds.
-04. CONTRACTOR'S LIABILITY INSURANCE:
Insurance shall be written with limits of liability shown below or as required by
law, whichever is greater.
Commercial General Liability (per occurrence) Each Occurrence
General Aggregate
Products
Personal & Adv Injury
Fire Damage
Automobile Liability (any auto) Combined Single Limit
$1,000,000
$2,000,000
$2,000,000
$1,000,000
$500,000
$1,000,000
SC-l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Excess Liability (any auto) Each Occurrence
Workers Compensation
Employer Liability
$5,000,000
Statutory Limits
$1,000,000
-05. PROTECTION OF THE ENVIRONMENT:
The Contractor will carefully schedule his work so that a minimum amount of the
exposed earth will be subject to erosion by rainfall or wind, and he will provide means satisfactory
to the Engineer to minimize the transportation of silt and other deleterious material from the
project area onto adjacent properties or into adjacent water courses.
All chemicals used during project construction or furnished for project operation,
whether herbicide, pesticide, disinfectant, polymer, reactant or of other classification, mush show
approval of either EP A or USDA. Use of all such chemicals and disposal of residues shall be in
conformance with printed instructions.
-06. TEMPORARY TOILETS:
Contractor shall provide temporary toilet facilities on the site for workmen
employed in the construction work. Toilets shall be adequate for the number of men employed
and shall be maintained in a clean and sanitary condition. Workmen shall be required to use only
these toilets. At completion of the work, toilets used by Contractor shall be removed and
premises left in the condition required by the Contract.
-07. PLANS AND SPECIFICATIONS FURNISHED: .
The Contractor will be furnished, free of charge, by the Owner up to five (5) sets
of direct black line prints together with a like number of complete bound specifications for
construction purposes. Additional sets of plans and/or specifications will be furnished to the
Contractor at the cost of reproduction upon his written request.
-08. RECORD DRAWINGS:
The Contractor will maintain in his office one complete set of drawings (including
any supplemental sketches) pertaining to the project upon which, at the end of each day's work
any deviations from the construction lines shown thereon and all changes ordered by the Engineer
will be shown accurately in red pencil. If necessary, supplemental drawings will be made to show
details of deviations or changes, and these will be kept with the marked set. The drawings will be
available to the Engineer for inspection during construction and at the completion of construction.
Prior to submitting his estimate for final payment, as-built drawings are to be prepared and
submitted by the contractor to the engineer. As-built drawings shall include tap locations and
manholes located to a minimum of two separate surface features.
-09.
SHOP DRAWINGS:
The Contractor shall submit to the Engineer for his review shop drawings, cuts,
diagrams, bar lists, steel details, control logic diagrams and other descriptive data on every item,
where shown on the drawings or specified herein. The Contractor shall check all submittals and
so indicate on each copy thereof.
SC-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Five copies of such shop drawings. shall be submitted to the Engineer before
ordering any equipment or materials. Submittals which have not been checked by the Contractor
will not be reviewed by the Engineer. Reviews by the Engineer of submittals will cover only
general conformity with the project requirements, while responsibility for detailed conformity shall
remain with the Contractor. The Contractor will be notified by mail of the results of the submittal
reviews within ten (10) days of the receipt by the Engineer thereof.
-10. EXISTING STRUCTURES:
Where sidewalks, street signs, private signs, walls, sidewalks, fences, pipelines,
etc. are removed in accomplishing the work, each and every item will be replaced in the same or
better manner or condition than that in which it was before construction began. The Contractor
will protect and hold harmless the Owner from any suit, action, or dispute whatever arising from
the Contractor's work adjacent to private property.
-11.
SALVAGE MATERIAL:
All existing installations to be removed, including but not limited to masonry and
concrete rubble, asphalt, pipe, etc. will be disposed of at an approved location by the Contractor.
-12. REFERENCED SPECIFICATIONS:
Where specifications or standards of trade organizations and other groups are
referenced in these specifications, they are made as much a part of these specifications as if the
entire standard or specification were reprinted herein. The inclusion of the latest edition or
revision of the referenced specification or standard is intended.
-13. CONSTRUCTION ORDER AND SCHEDULE:
A. The Contractor shall be responsible for the detailed order, schedule, and
methods of construction activities within the general guidelines specified
for maintenance and protection of highway and pedestrian, traffic; utility
lines; drainage ways; adjacent properties; and as otherwise specified.
B. After notice to proceed and prior to the first payment on the contract the
Contractor shall submit the following for review:
(1) Breakdown of contract price into units of cost for each item
required to complete the total work; this breakdown will be the
basis for judging the percentage complete at any time.
(2) A bar chart showing the Contractor's order of construction.
-14. CONSULTING ENGINEERS:
The Owner has engaged consulting engineers to assist the Director of Utilities,
defined herein as the Engineer, by preparing plans and specifications for the work and by
providing certain services during the bidding and construction phases of the project. The
consulting engineer, Cranston, Robertson & Whitehurst, P. C. are authorized to represent the
Director of Utilities within the limits of the various duties delegated and assigned to the firm by
SC-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
the Director. Nevertheless the Director of Utilities! remains the final authority hereunder and is
the "Engineer" as used, throughout the Contract Documents. The Program Manager for the'
project is CH2M Hill, 360 Bay Street, Suite 100, Augusta, Georgia 30901. The Program
Manager's representative on the site will serve as the Resident Project Representative (RPR) for
the proj ect.
The presence or duties of Program Manager's personnel at the construction site,
whether as onsite representatives or otherwise, do not make Program Manager or Program
Manager's personnel in any way responsible for those duties that belong to Owner and/or the
Contractor or other entities, and do not relieve the Contractor or any other entity of their
obligations, duties, and responsibilities, including, but not limited to, all construction methods,
means, techniques, sequences, and procedures necessary for coordinating and completing all
portions of the construction work in accordance with the construction Contract Documents and
any health and safety precautions required by such construction work.
Program Manager and Program Manager's personnel have no authority to exercise
any control over any construction contractor or other entity or their employees in connection with
their work or any health or safety precautions and have no duty of inspecting, noting, observing,
correcting, or reporting on health or safety deficiencies of the Contractor( s) or other entity or any
other persons at the site except Program Manager's own personnel.
The presence of Program Manager's personnel at the construction site is for the
purpose of providing to Owner a greater degree of confidence that the completed construction
work will conform generally to the construction documents and that the integrity of the design
concept as reflected in the construction documents has been implemented and preserved by the
construction contractor(s). Program Manager neither guarantees the performance of the
construction contractor( s) nor assumes responsibility for construction contractor's failure to
perform work in accordance with the construction documents.
For this Agreement only, construction sites include places of manufacture for
materials incorporated into the construction work, and construction contractors include
manufacturers or materials incorporated into the construction work.
-15.
INSPECTION AND TESTING OF WORK
The Owner shall provide sufficient competent engmeenng personnel for the
technical observation and testing of the work.
The Engineer and his representatives shall at all times have access to the work
whenever it is in preparation or progress, and the Contractor shall provide proper facilities for
such access, and for inspections.
Inspectors shall have the power to stop work on account of a workman's
incompetency, drunkenness, or willful negligence or disregard of orders. An inspector may stop
the work entirely if there is not a sufficient quantity of suitable and approved materials or
equipment on the ground to carry it out properly or for any good and sufficient cause. Inspectors
may not accept on behalf of the Owner any material or workmanship which does not conform
fully to the requirements of the contract and they shall give no orders or directions under any
possible circumstances not in accordance with the Specifications. The Contractor shall furnish the
inspector with all required assistance to facilitate thorough inspection or the culling over or
SC-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
removal of defective materials or for any other purpose requiring discharge of their duties for
which service no additional allowance shall be made. The inspector shall, at all times, have full
permission to take samples of the materials that mayor may not be used in the work.
Any inspection provided by the Engineers is for the purpose of determining
compliance with provisions of the contract specifications and is in no way a guarantee of the
methods or appliances use by the Contractor, nor for the safety of the job.
If the specifications, the Engineer's instructions, laws, ordinances, or any public
authority require any work to be specially tested or approved, the Contractor shall give the
Engineer timely notice of its readiness for inspection, and if the inspection is by an authority other
than the Engineer, of the date fixed for such inspection. Inspections by the Engineer shall be
made promptly, and where practicable at the source of supply. If any work should be covered up
without review or consent of the Engineer, it must, if required by the Engineer, be uncovered for
examination and properly restored at the Contractor's expense.
Re-examination of any work may be ordered by the Engineer, and, if so ordered,
the work must be uncovered by the Contractor. If such work is found to be in accordance with
the Contract Documents, the Owner shall pay the cost of re-examination and replacement. If such
work is not in accordance with the Contract Documents, the Contractor shall pay such cost.
The Owner will employ a qualified materials testing laboratory, hereinafter referred
to as the Laboratory, to monitor more fully on the Owner's behalf the quality of materials and
work, and to perform such tests as may be required under the Contract Documents as conditions
for acceptance of materials and work. The Laboratory will be solely responsible to and paid
separately by the Owner. The timing of the work of the Laboratory will be coordinated by the
Engineer through his duly authorized inspector.
The Owner will bear the cost of testing a particular material or area of the work
once. Where retesting is required following corrective measures or under other circumstances,
the Contractor shall reimburse the Owner for the cost of additional testing.
-16.
GEORGIA PROMPT PAY ACT:
This Agreement is intended by the Parties to, and does, supersede any and all
provisions of the Georgia Prompt Pay Act, O.C.G.A. Section 13-11-1, et seq. In the event any
provision of this Agreement is inconsistent with any provision of the Prompt Pay Act, the
provision of this Agreement shall control.
-17.
CITY ACCEPTANCE:
Notwithstanding any other obligations of the Contractor, he shall complete the
work to the full satisfaction of the Augusta Utilities Department and the Engineer. This provision
shall not relieve the Contractor of his responsibilities for guarantees.
-18.
DISPUTES:
All claims, disputes and other matters in question between the Owner and the
Contractor arising out of or relating to, the Agreement, or the breach thereof, shall be decided in
the Superior Court of Richmond County, Georgia. The Contractor, by executing this Agreement,
SC-5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
specifically consents to venue in Richmond County and waives any right to contest the venue in
the Superior Court of Richmond County, Georgia.
-19.
SPECIFIED MATERIALS:
Attention is drawn to the specification of certain brands or manufacturers of
construction materials on the drawings. Unless the phrase "or equal" appears in the specification
thereon, no substitution or deviation from the product specified will be allowed.
Notwithstanding any provision of the general conditions, there shall be no
substitution of materials that are not determined to be equivalent to those indicated or required in
the contract documents without an amendment to the contract.
-20. INTEREST NOT EARNED ON RETAINAGE:
Notwithstanding any provision of the law to the contrary, the parties agree that no
interest shall be due to the Contractor on any sum held as retainage pursuant to this Agreement
and Contractor specifically waives any claim to same.
-21. BASIS OF PAYMENT:
As explained in the section "Instructions to Bidders" and paragraphs 11.91, 11.92
and 11.93 of the General Conditions, payment for all items of construction will be made at the
total of the actual number of units installed at the unit prices stated in the Bid Schedule to the
Proposal. Partial payments will be made based on the actual number of units of work completed
during the month and in-place at the unit prices stated in the Bid Schedule.
-22.
COMPLIANCE WITH LAWS. CODES. REGULATIONS. ETC.:
Supplementing the provision of the GENERAL CONDITIONS, the successful
bidder awarded this contract by signing the contract acknowledges the following, however, this is
not to be construed as all inclusive or being these only:
1. Underground Gas Pipe Law:
The Contractor signing the contract acknowledges that he is fully aware of the
contents and requirements of "Georgia Laws 1969, Pages 50 and the following,
and any amendments and regulations pursuant thereto", and the Contractor shall
comply therewith.
2. High Voltage Act:
The Contractor by signing the contract acknowledges that he is fully aware of the
contents and requirements of "Act No. 525, Georgia law 1960, and any
amendments thereto, and Rules and Regulations of the commissioner of Labor
pursuant thereto" (the preceding requirements within quotation marks being
hereinafter referred to as the "high voltage act"), and the Contractor shall comply
therewith. The signing of Contract shall also confirm on behalf of the Contractor
that he:
SC-6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
a. has visited the premises and has taken into consideration the location of all
electrical power lines on and adjacent to all areas onto which the contract
documents require to permit the Contract either to work, to store
materials, or to stage operations, and
b. that the Contractor has obtained from the Owner of the aforesaid electric
power lines advice in writing as to the amount of voltage carried by the
aforesaid lines.
The Contractor agrees that he is the "person or persons responsible for the
work to be done" as referred to in the high voltage act and that accordingly
the Contractor is solely "responsible for the completion of the safety
measures which are required by Section 3 of the high voltage act before
proceeding with any work." The Contractor agrees that prior to the
completion of precautionary measures required by the high voltage act he
will neither bring nor permit the bringing of any equipment onto the site (or
onto any area or areas onto which the contract documents require or
permit the Contractor to work, to store materials, or to stage operations)
with which it is possible to come within eight feet of any high voltage line
or lines pursuant to operations arising out of performance of the Contract.
The foregoing provisions apply to power lines located ( a) on the site and
(b) on any area or areas onto which the contract documents require or
permit the Contractor either to work, to store materials, or to stage
operations, or ( c) within working distance for equipment or materials,
being used on (a) and (b) above. These provisions of the Contract do not
limit or reduce the duty of the Contractor otherwise owed to the Owner, to
other parties, or to both. The Contractor agrees that the foregoing
provisions supplement provisions of the General Conditions. The
Contractor agrees and acknowledges that any failure on his part to adhere
to the high voltage act shall not only be a violation of law but shall also be
a breach of contract and specific violation of the provisions of the General
Conditions which pertains to safety precautions.
3. Occupational Safetv & Health Act:
The Contractor by signing the contract acknowledges that he is fully aware of the
provisions of the Williams-Steiger Occupational Safety and Health Act of 1970
and he shall comply therewith.
-23. EOUIV ALENT MATERIALS:
Notwithstanding any ,provision of the general conditions, there shall be no
substitution of materials that are not determined to be equivalent to those indicated or required in
the contract documents without an amendment to the contract.
SC-7
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-O
INDEX TO TECHNICAL SPECIFICATIONS
SECTION TITLE NO. OF PAGES
TS-l Clearing and Grubbing 1
TS-2 Grading 4
TS-3 Excavation and Backfilling 4
TS-4 Water Distribution System 12
TS-5 Erosion Control Measures 2
TS-6 Grassing (Bermuda) 2
TS-7 On-Site Sodium Hypochlorite Generation System 16
TS-8 Pre-Assembled Precast Concrete Storage Building 5
TS-9 Electrical 3
TS-I0 Concrete Construction 2
TS-l1 Graded Aggregate Base Course 1
TS-12 Bituminous Paving 3
TS-13 Measurement and Payment 2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-l
CLEARING AND GRUBBING
-01.
SCOPE:
Clearing and grubbing shall consist of the removal and disposal of all trees, brush,
stumps, logs, grass, weeds, roots, decayed vegetable matter, posts, fences, stubs, rubbish and all other
objectionable matter resting on or protruding through the original ground surface and occurring
within the construction limits or rights-of-way of any excavation, borrow area, or embankment.
-02.
CONSTRUCTION METHODS:
1. CLEARING: Clearing shall consist of the felling and cutting up, or the trimming of trees, and
the satisfactory disposal of the trees and other vegetation together with the down timber,
snags, brush and rubbish occurring within the areas to be cleared. Trees and other vegetation,
except such individual trees, groups of trees, and vegetation, as may be indicated on the
drawings to be left standing, and all stumps, roots and brush in the areas to be cleared shall
be cut off one foot above the original ground surface. Individual trees and groups of trees
designated to be left standing within cleared areas shall be trimmed of all branches to such
heights and in such manner as may be necessary to prevent interference with the construction
operations. All limbs and branches required to be trimmed shall be neatly cut close to the
whole of the tree or to main branches, and the cuts thus made shall be painted with an
approved tree wound paint. Individual trees, groups of trees, and other vegetation, to be left
standing, shall be thoroughly protected by barriers or by such other means as the
circumstances require. Clearing operations shall be conducted so as to prevent damage by
falling trees to trees left standing, to existing structures and installations, and to those under
construction, and so as to provide for the safety of employees and others.
2. GRUBBING: Grubbing shall consist of the removal and disposal of all stumps, roots and
matted roots from the site as indicated on the drawings. In foundation areas, stumps, roots,
logs or other timber, matted roots, and other debris not suitable for foundation purposes shall
be excavated to a depth of not less than 18 inches below any sub grade, shoulder or slope. All
depressions excavated below the original ground surface for or by the removal of stumps and
roots, shall be refilled with suitable material ,and compacted to make the surface conform to
the surrounding ground surface.
-03.
DISPOSAL OF CLEARED AND GRUBBED MATERIAL:
Saw logs, pulp wood, cord wood or other merchantable timber removed incidental
to clearing and grubbing shall become the property of the Contractor and may be sold by him,
provided such disposal is otherwise in accordance with these specifications. All incombustible matter
removed shall be hauled away and deposited at locations approved by the Engineer. Combustible
matter may be burned or may be disposed of as stated above. Burning shall be done at such time and
such manner as to prevent fire from spreading and to prevent any damage to adjacent cover and shall
further be subject to all requirements of Local, State and Federal Governments pertaining to the
burning. No burning will be allowed on the site unless all fires are kept under constant attendance
by persons having equipment necessary to prevent the spreading of fire. Such equipment shall
include, at the minimum, a bulldozer or front end loader, and an approved pump and hose connected
to an acceptable source of water. Disposal by burning shall be kept under constant attendance until
all fires have burned out or have been extinguished.
TS-1-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-2
GRADING
-01.
SCOPE:
This section covers grading for the roadways, parking areas, drives and/or walks,
including all excavations, formation of embankments, preparation of sub grade for pavements and
finishing and dressing of graded earth areas, shoulders, and ditches. Work in connection with
excavation, trenching, and backfilling for utility lines is specified under the section entitled
"Excavating and Backfilling. "
-02.
CONSERVATION OF TOPSOIL:
Except where otherwise noted on the plans, topsoil shall be removed without
contamination with subsoils and spread on areas already graded and prepared for topsoil, or shall be
transported and deposited in storage piles convenient to areas that are to receive application of topsoil
later, or at locations indicated. Topsoil shall be stripped to a depth on to 6 inches and, when stored,
shall be kept separate from other excavated materials and piled free of roots, stones, and other
undesirable materials.
-03.
EXCAVATION:
The term "excavation" used hereinafter is defined as "unclassified excavation."
Excavation of every description regardless of material' encountered within the grading limits of the
project, shall be performed to the lines and grades indicated. Suitable excavated material shall be
transported to and placed in fill areas within the limits of the work. When directed, unsuitable
material encountered within the limits of the work shall be excavated below the grade shown and
replaced with suitable material. Materials considered unsuitable are those conforming to passes PT,
OR" CR, l\1H, OL, CL, or ML as described under the Unified Soil Classification System.!lUnsuitable
and surplus excavation material not required for fill shall be disposed of in designated waste or spoil
areas. During construction, excavation and filling shall be performed in a manner and sequence that
will provide drainage at all times. Material required for fills in excess of that produced by excavation
within the grading limits shall be excavated from the borrow areas indicated or from other approved
areas selected by the Contractor, as specified herein.
-04.
SELECTION OF BORROW MATERIAL:
1. GENERAL: Borrow material shall be selected to meet the requirements and conditions of
the particular fill for which it is to be used. The material shall consist of sandy soils or sand-
clay soils capable of being readily shaped and compacted to the required densities and shall
be free of roots, trash and any other deleterious material. Any necessary clearing, grubbing,
disposal of debris and satisfactory trimming and drainage of the borrow areas shall be
considered incidental to operations of the borrow excavation and shall be performed by the
Contractor at no additional cost to the Owner. Unless specifically provided, no borrow shall
be obtained within the limits of the project site without written approval,
2. BORROW AREA(S): Borrow material shall be furnished by the Contractor from private
sources selected by the Contractor and shall consist of a suitable material of the type
mentioned above. The Contractor shall obtain from the Owners the right to procure material,
shall pay all royalties and other charges involved, and shall bear all the expenses of developing
the sources, including rights-of-way for hauling.
TS-2-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-05.
EXCAVATION OF DITCHES AND GUTTERS:
Ditches and gutters shall be cut accurately to the cross-sections and grades indicated
by the drawings. All roots, stumps, and other foreign matter in the sides and bottom of ditches and
gutters shall be cut one foot below finish grade. Care shall be taken not to over-excavate ditches and
gutters below the grades indicated. Any excessive ditch and gutter excavation due to removal of
roots, stumps, etc., or due to over-excavation shall be backfilled to grade either with suitable material,
thoroughly compacted, or with suitable stone or cobble to form an adequate gutter paving, as
directed. The Contractor shall maintain all ditches and gutters excavated under this specification free
from detrimental, quantities of leaves, sticks, and other debris until final acceptance of the work.
Suitable earth material excavated from ditches and channel changes shall be placed in embankments.
Excavated material shall not be deposited within a distance from the edge of any excavation ofless
than 1112 times the depth of the excavation. When storm drain pipe terminates in a new ditch, the
headwall or end section together with ditch pavement shall be constructed immediately as called for
on the plans. Ditch slopes and disturbed earth areas shall be grassed as required under the section
entitled "Grassing (Bermuda)." The Contractor shall be responsible for maintaining these newly
constructed ditches and take immediate action subj ect to approval to keep erosion of the ditch bottom
and slopes to a minimum during the life of the contract. No additional compensation will be given
to the Contractor for the required maintenance.
-06.
PROTECTION OF EXISTING SERVICE LINES AND UTILITIES
STRUCTURES:
Existing utility lines that are shown on the drawings or the location of which are made
known to the Contractor prior to excavation that are to be retained, as well as utility lines constructed
during excavation operations, shall be protected from damage during excavation and backfilling, and
if damaged, shall be repaired by the Contractor at his expense. In the event that the Contractor
damages any existing utility lines that are not shown, or the locations of which are not known to the
Contractor, report thereof shall be made immediately to the Engineer. If determined that repairs are
to be made by the Contractor, such repairs will be ordered under the clause of the GENERAL
CONDITIONS of the Contract entitled Changes.
-07.
BACKFILL ADJACENT TO STRUCTURES:
Backfill adjacent to structures shall be placed and compacted uniformly in such manner
as to prevent wedging action or eccentric loading upon or against the structures. Slopes bounding
or within areas to be backfilled shall be stepped or serrated to prevent sliding of the fill. During
backfilling operations and in formation of the embankments, equipment that will overload the
structure in passing over and compacting these fills shall not be used. Backfill for storm drains and
sub drains, including the bedding, shall conform to the additional requirements as specified.
-08.
PREPARATION OF GROUND SURFACE FOR FILL:
All vegetation, such as roots, brush, heavy sods, heavy growth of grass, and all
decayed vegetable matter, rubbish and other unsuitable material within the area upon which fill is to
be placed shall be stripped or otherwise removed before the fill is started. In no case will unsuitable
material remain in or under the fill area. Sloped ground surfaces steeper than 1 vertical to 4
horizontal on which fill is to be place shall be plowed, stepped or benched, or broken up as directed,
in such manner that the fill material will bond with the existing surface. Prepared surfaces on which
compacted fill is to be placed shall be wetted or dried as may be required to obtain the compaction
specified.
TS-2-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-09. FILL:
Fills and embankments shall be constructed at the locations and to lines and grades
indicated. The completed fill shall correspond to the shape of the typical section indicated or shall
meet the requirements of the particular case. Suitable material removed from the excavation shall be
used in forming the fill., Fill material shall be reasonably free from roots, other organic material and
trash, and from stones have maximum dimension greater than 6 inches. No frozen material will be
permitted in the fill. Stones having a maximum dimension larger than 4 inches shall not be permitted
in the upper 6 inches of fill or embankment. The material shall be placed in successive horizontal
layers of 8 inches to 12 inches in loose depth for the full width of the cross section and shall be
compacted as required.
-10.
COMPACTION:
1. OVERALL OR OVERLOT AREAS: Each layer of the fill or embankment, except in areas
indicated as not requiring compaction, shall be compacted by rolling with an approved
tamping roller, heavy rubber-tired roller, three steel wheeled power roller, vibratory roller or
other compaction equipment, whichever is best suited for the types of soil encountered to at
least 95 percent of maximum Standard Proctor density at optimum moisture content.
.2. FIELD CONTROL: In all fill areas field density tests will be performed in sufficient number
(minimum of one test on each alternate lift or as recommended by the Engineer) to insure that
the specified density is being obtained. These tests will be made at the expense of the
Contractor and will be in accordance with ASTM D-698.
-11.
FINISHED EXCAVATION. FILLS. AND EMBANKMENTS:
All areas covered by the project, including excavated and filled sections and adjacent
transition areas, shall be uniformly smooth graded. The finished surface shall be reasonably smooth,
compacted, and free from irregular surface changes. The degree of finish shall be that ordinarily
obtainable from either bladegrader or scraper operations, supplemented with hand raking and
finishing, except as otherwise specified. The finished surface shall be not more than 0.10 foot above
or below the established grade or approved cross section. Ditches and gutters shall be finished so as
to permit adequate drainage. The surface of areas to be grassed shall be finished to smoothness
suitable for the application of grassing materials. The surface of embankments or excavated areas
for road construction or other areas to be paved on which a base course or pavement is to be placed
shall not vary more than 0.05 foot from the established grade and approved cross section. In areas
where the bulking of soil as a result of grassing operations 'will tend to retard surface drainage along
the edge of pavements, the finished grades shall be left 0.1 foot below grade.prior to grassing.
-12.
DISPOSAL OF WASTE MATERIAL:
All vegetation, roots, brush, sod, broken pavements, curbs and gutter, rubbish, and
other unsuitable or surplus material stripped or removed from the limits of construction shall be
disposed of off the site, except where otherwise approved in writing by the Engineer. The material
shall be dumped, spread, and leveled to drain. Surplus excavation shall be hauled to, compacted in
accordance with overall and overlot areas, and sloped to drain in the disposal area where directed.
The unsuitable material shall be leveled to drain and firmed under the normal operation of spreading
and hauling equipment. Any trees, stumps, brush, down timber, etc. in the area to be used for
disposal shall be cleared by cutting (to within six (6) inches of the ground) and shall be disposed of
by burning, removal from the property or a combination of both. Clearing and disposal of trees,
stumps, etc. shall comply with the applicable portions of the clearing and grubbing specifications.
TS-2-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-13.
PLACEMENT OF TOPSOIL:
Topsoil shall be placed on all shoulders, slopes, ditches, and other earth areas graded
under this contract, excluding borrow areas, unless otherwise specified on the plans. Topsoil shall
be uniformly placed on these areas to a compacted depth of not less than three (3) inches or more
than four (4) inches. The material shall be free from clods of soil, matted mots, mots grater than lf2
inch in diameter, and any other objectionable material which might hinder subsequent grassing and
mowing operations. The material shall be placed, leveled, and lightly compacted with at least one
pass of a cultipacker or light pneumatic-tired mller, to required cmss sections, but shall be left one-
tenth (0.10) of a foot below the finished earth grade.
-14.
PROTECTION:
Newly graded areas shall be pmtected from traffic and from emsion, and any
settlement or washing away that may occur from any cause, prior to acceptance, shall be repaired and
grades re-established to the required elevations and slopes, at no additional expense to the Owner.
TS-2-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
April, 2001
SECTION TS-3
EXCA VA TION AND BACKFILLING
-01.
SCOPE:
This section covers all excavation, trenching and backfillingfor pipe lines, complete.
-02.
EXISTING IMPROVEMENTS:
The Contractor shall maintain in operating condition and protect from damage all
existingimprovementsincludingutilities,roads, streets, sidewalks, drives, power and telephone lines,
gas lines, water lines, sewers, gutters and other drains encountered, and repair to the satisfaction of
the Engineer any aerial, surface or sub surface improvements damaged during the course of the work.
Where and ifshown on the plans, the locations and existence or nonexistence of underground utilities
are not guaranteed. The Contractor shall contact the various utility companies to determine and/or
verify such information prior to proceeding with the work. He shall make reasonable and satisfactory
provisions for the maintenance of traffic on streets, drives, walkways and at street crossings andif
necessary to provide temporary walkways and bridges for crossing of the open trench as directed.
Work shall not commence within Augusta right-of-way until a Right-of-Way Encroachment Permit
is obtained from the Public Works Department.
EXCAVATION:
-03.
All excavation of every description and of whatever substances encountered shall be
performed to the depths indicated on the drawings or as specified herein. Excavation shall be made
by the open cut method except as otherwise specified or shown on the drawings. Excavation
methods shall generally meet or exceed Occupational Safety and Health Adminis:ration (OSHA)
construction industry standards.
All excavated materials not required for fill orbackfill shall be removed and wasted
as directed. The banks of shallow trenches shall be kept as nearly vertical as practicable and where
required shall be properly sheeted and braced. Except where otherwise indicated, trench bottoms
shall be not less than 12 inches wider nor more than 16 inches wider than the outside diameter of the
pipe to be laid therein, and shall be excavated true to line, so that a clear space of not less than 12
inches in width is provided on each side of the pipe. The bottom of trenches shall be accurately
graded to provide uniform bearing and support for each section of the pipe on undisturbed soil at
every point along its entire length, except forportions of the pipe sections where it is necessary to
excavate for bell holes and for the proper sealing of pipe joints. Bell holes shall be dug after the
trench bottom has been graded. Bell holes shall be excavated only to an extent sufficient to permit
accurate work in the making of the joints and to insure that the pipe, for a maximum of its length will
rest upon the prepared bottom of the trench. Depressions for joints other than mechanical shall be
madein accordance with the recommendations of the j oint manufacturers for the particularjointused.
Excavation for structures and other accessories shall be sufficient to leave atleast 12 inches in the
TS-3-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
April, 2001
clear between their outer surfaces and the embankmentor timberwhich maybe used to hold the bank
and protect them. Where damage is liable to result from withdrawing sheeting, the sheeting will be
ordered to be left in place. Except at locations where excavation of rock from the bottoms of
trenches is required, care shall be taken not to excavate below the depths indicated. Where rock
excavation is required, the rock shall be excavated to a minimumoverdepth of 4 inches below the
normal required trench depth. The overdepth rock excavation and all excess trench excavation shall
be backfilledwith loose, moist earth, thoroughly tamped. Rock is defined as materials which are so
hard or cemented that the excavation of such material requires blasting. The excavation shall proceed
in a conventionalmannerwith satisfactory effort made to remove hard materials before the Engineer
makes a determination of need for blasting. Predrilling and blasting will be allowed, if the Contractor
can provide evidence for the Engineer's review that boring logs can andwill show that the material
can or cannot be excavated. Evidence will be provided for the Engineer's review and approval before
predrilling and blasting is undertaken. The excavation and removal of isolated boulders or rock
fragments larger than one cubic yard in volume encountered in materials of common excavation shall
be classified as rock excavation. Whenever wet or otherwise unstable soil that is incapable of
properly supporting the pipe, as determined by the Engineer or indicated on the drawings, is
encountered in the trench bottom, such soil shall be removed to a depth required for the lengths
designated by the Engineer, and the trench backfilledto trenchbottom grade, as herein specified, with
coarse sand, fine gravel, or other suitable material. Backfill with earth under structures will not be
permitted and any unauthorized excess excavation below thelevels indicated for the foundation of
such structures shall be filled with sand, gravel, or concrete, as directed.
A. Grading and Stacking: All grading in the vicinity of trench excavation shall be
controlled to prevent surface ground water from flowinginto the trenches. Anywater
accumulated in the trenches shall be removed by pumping or by other approved
methods. During excavation, material suitable for backfilling shall be stored in an
orderly manner a minimum distance of one and one-half times the depth of the
excavation back from the edges of trenches to avoid overloading and prevent slides
or cave-ins. Material unsuitable for backfilling, as determined by the Engineer, shall
be removed from the job site and disposed of by the Contractor in a manner as
approved by the Engineer.
B. Shoring and Sheeting: All shoring, sheeting, and bracing required to perform and
protect the excavation and to safeguard employees and the publicshallbe performed.
The failure of the Engineer to direct the placing of such protection shall not relieve
the Contractor of his responsibility for damage resulting from its omission.
Whenever sheeting is driven to a depth below the elevation of the top of the pipe, that
portion of the sheeting below the elevation of the top of the pipe shall not be
disturbed or removed. Sheeting left in place shall be cut off not less than 1 foot below
finished grade. No sheeting shall be removed until the excavation is substantially
backfilled as hereinafter specified.
C. Water Removal: Where water is encountered, it shall be prevented from
accumulatingin excavated areas by pumping, well-pointingand pumping, or by other
TS-3-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
April, 2001
means approved by the Engineer as to capacity and effectiveness. Water removed
from excavations shall be discharged at points where it will not cause injury to public
or private property, or the work completed or in progress. All efforts to prevent
sedimentation shall be made. Under no circumstances shall trench bottoms be
prepared, pipes laid, or appurtenances installed in water. Water shall not be allowed
to rise in unbackfilled excavations after pipe or structures have been placed.
D.
Blasting: Explosives are to used only within legal limitations. Before explosives are
used, all necessary permits for this work shall be secured and all precautions taken in
the blasting operations to prevent damage to private or public property or to persons.
The Contractor shall assume full liability for any damage that mayoccur during the
use of explosives. No blast shall be set offwithin 50 feet of pipe already laid in the
trench.
E.
Tree Protection: Care shall be exercised to protect the roots of trees to be left
standing. Within the branch spread of the tree, trench shall be opened only when the
work can be installed immediately. Injured roots shall be pruned cleanly and backfill
placed as soon as possible.
-04.
BACKFILLING:
Trenches and other excavations shall not be backfilled until all required tests are
performed and the work has been approved by the Engineer. The trenches shall be carefully
backfilledwith the excavated materials approved for backfillingconsisting of earth, loam, sandy clay,
sand and gravel, soft shale, or other approved materials. No material shall be used for backfilling
that contains mulch, other unstable materials, stones, blasted rock, broken concrete or pavement, or
other hard materialshaving any dimensiongreater than 4 inches; or large clods of earth, debris, frozen
earth or earth with an exceptionallyhigh void content. Backfilling within Augusta right-of-way shall
conform to Georgia Department of Transportation and City of Augusta specifications.
For backfillup to a level 1 foot over the top of pressure pipelines and 2 feet above the
top of gravity pipelines, only selected materials shall be used. Select materials shall be finely divided
material free from debris, organic material and stone, and may be suitable job excavated material or
shall be provided by the Contractor from other sources. The backfill shall be placed in uniform layers
not exceeding 8 inches in depth. Each layer shall be moistened and carefully and uniformly tamped
withmechanicaltampers or other suitabletools. Each layer shall be placed and tamped under the pipe
haunches with care and thoroughness so as to eliminate the possibility of voids or lateral
displacement.
TS-3-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
April, 2001
The remainder of the backfill material shall then be placed and compacted above the
level specified above. In areas not subject to traffic, the backfill shall be placed in 12 inch layers and
eachlayermoistenedand compacted to a density approximating that of the surrounding earth. Under
roadways, driveways, paved areas, parking lots, along roadway shoulders and other areas subj ect to
traffic, the b ackfill shall be placed in 8 inch layers and each layer moistened and compacted to density
at least equal to that of the surrounding earth so that traffic can be resumed immediately after
backfillingis completed. Any trenches which are improperly backfilled, or where settlement occurs,
shall be reopened to the depth required for proper compaction, then refilledand compacted with the
surface restored to the required grade compaction. Along all portions ofthe trenches not located
in roadways, the ground shall be graded to a reasonable uniformity and the mounding over the
trenches left in a neat condition satisfactory to the Engineer.
Sheeting not specifiedto be 1 eft in place shallbe removed as the backfillingprogresses.
Sheeting shall be removed in such a manner as to avoid caving of the trench. Voids left by the
removal of sheeting and shoring shall be carefully filled and compacted. Where, in the opinion of the
Engineer, damage is liableto result from withdrawing sheeting, the sh eeting will be ordered to be left
in place.
-05.
PAVEMENTREMOVALANDREPLACEMEN~
Where necessary existing pavements shall be removed and replaced, the applicable
specificationsofthe Georgia DepartmentofTransportation or local authority shall govern this'work.
Joints shall be sawed, unless joints equally uniform in the opinion of the Engineer result frornother
means. Refer to Augusta-Richmond County Right-of-Way Encroachment Guidelines for pavement
removal and replacement.
TS-3-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-4
WATER DISTRIBUTION SYSTEM
-01.
STANDARDS FOR WATER MAINS:
A. CONTRACTOR RESPONSIBILITIES:
1. The Contractor is responsiblefor verifyingthe exact location, size and
material of any existing water facility proposed for connection or use
by the proj ect.
2. All work that occurs in the public right-of-way shall comply with the
Augusta-Richmond County Planning Commission "Development
Documents" (latest version) and Public Works Department's Right-of-
Way EncroachmentGuidelines(latestversion). Any field changes that
occur in the public right-of-way and are not specifically related to
water or sewer items shall be coordinated with the Public Works
Department.
B. COVER:
1. Standard depth of cover is 4 feet below existing and proposed road
surface (and areas designed for normal traffic loading) unless
otherwise approved by the Augusta Utilities Department.
2. Minimumcover to finished grade over water mains shall be 36 inches.
Minimum cover under ditch bottoms shall be 24 inches. These must
be approved by the Augusta Utilities Department on a case-by-case
basis.
C. HORIZONTAL SEPARATION
1. Ten (10) feet to any existing or proposed sanitary sewer/force main,
storm sewer or sewer manhole (less than 10 feet requires pipe material
to be Ductile Iron Pipe (DIP) for both Water Main and Sewer/Force
Main).
2. Fifteen (15) feet to buildings, top of bank of lakes/streams/creeks,
other structures (10 feet absolute minimum- only when unavoidable, .
and pipe material is required to be DIP).
3. Ten (10) feet minimum separation to gas mains.
4. Ten (10) feet minimum to underground electric cable.
TS-4-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
5. Current Georgia EPD separation requirements.
6. All separation distances above are edge to edge.
D. VERTICAL SEPARATION:
1. Water main shall cross over other pi pes.
2. Eighteen (18) inch minimum separation (edge to edge) between all
pipes and cables shall be maintained (6 inch absolute minimum
separation with DIP) when conforming to Georgia EPD separation
requirements.
3. When water mains cross under sewers, additional measures shall be
taken. At least 18 inches of separation between the bottom of the
sewer and the top of the water main shall be provided. Adequate
structural support for the sewer to prevent deflection or settling on the
water main. The joint of water pipe shall be centered at the crossing.
Encasement of the water pipe in concrete shall also be considered.
E. WATER MAIN MATERIAL:
Water mains shall be either ductile iron pipe (DIP), polyvinyl chloride (pVC), or
galvanized pipe as outlined below. Any pipe, solder and flux used during installation
of the water lines and services must be "lead-free" with not more than 8% lead in pipe
and fittings, and not more than 0.2% lead in solders and flux.
DIP shall be centrifugally cast and shall conform to AWWA CI50/ANSI A21.50
(latest version) for design and AWWA CI51/ANSI A21.51 (latest version) for
manufacture. PVC pipe 6 inch to 12 inch diameter shall conform to AWWA C900
(latest version). PVC pipe 14 inch to 36 inch diameter shall conform to AWWA
C905 (latest version).
For water mains 6" through 16", DIP Pressure Class350 shall be allowed. Forwater
mains 18" through 24", DIP Pressure Class 300 shall be allowed. PVC C900 (most
current date), Class 200, SDR-14 with cast iron equivalent O.D.s, gasket bell end
with elastomeric gaskets shall be allowed for water mains 6" through 10" (solvent
weld joints are not permitted). Galvanized pipe shall be seamless, American made,
Schedule 80 and shall conform with the ASTM Specifications. Flanged DIP shall
have threaded ductile iron flanges and shall conform to the requirements of A WW A
C115 (latest version). All flanges shall be Ductile Iron Class 150, ANSIB 16.5 (latest
version). Flanges shall be flat faced and all joints shall use 1/8 inch black neoprene
full-faced gaskets.
Ductile iron pipe and fittings shall have bituminous coating outside and shall be
cement lined in accordance with A WW A C 1 04/ ANSI A21. 4 (latest version). DIP
shall have 1/16" cement mortar liningwithrubber gasket push-onjointsor mechanical
TS-4-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
joints. Mechanical j oint glands shall be ductile iron. Tee bolts and nuts shall be Cor-
Ten steel. Rubber gasket j oints shall conform to AWWA Cll1/ANSI A21.11 (latest
version), and shall be furnished by the pipe manufacturer with the pipe. A non-toxic
vegetable soap lubricant shall be supplied with the pipe in sufficient quantities for
installingthe pipe. The lubricant shall be approved by NSF for use with potable water
m81ns.
Pipe dassesdesignated previously in this standard are minimumallowed. Actual pipe
class shall be determined based upon the installationand the use intended. Pipe shall
be appropriately labeled on the drawings. All PVC pipe for potable water service
shall bearthe approved stamp of the National Sanitation Foundation. Copper wire
(12 gauge, bare single strand) shall be attached along the top of all buried PVC water
lines, wrapped around service corporations and stubbed up into all valves boxesfor
locating purposes.
1. DIP shall be required in the following circumstances:
a. Within 10 feet of sanitary and storm pipes.
b. Within 15 feet of structures (nearside of concrete footing), or
top of bank oflakes/streams/creeks.
c. Crossings over or under sewers, gas and storm pipes with less
than 18 inches separation, withnojointallowedwithin 10 feet
of crossing.
d. Beneath all paved areas, excluding driveways or sidewalks.
e. Within project boundaries of sub divisions with private roads
where the Utilities Department will take over the line for
operations and maintenance.
f. Along all state right-of-ways.
2. The UtilitiesDirector may mandate DIP in any instances of off-site or
on-site construction where future abuse to the line is possible due to
location or circumstances.
3. Restrained Joints shall be DIP as follows:
a. For 12-inch and Smaller- Restrained joint shallbe U.S. Pipe
Field Lok, AmericanDuctile Iron Pipe Lok-Fast, EBAA Iron
Mega-Lug, or an equivalent product.
b. For 14-inch Diameter and Larger - Restrained joint shall be
U.S. Pipe TRFlex, American Ductile Iron PipeLok-Ring, or
equivalent product.
TS-4-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
c.
If inserting in older cast iron pipe, the restrained j oint shall be
as approved by the Augusta Utilities Department.
Retainer Glands/Mega-Lug shall not be considered a fitting.
The restraint method shall be suitable for the pipe size
thickness and test pressure as required for the specified design
case. All pipe installed under ground should be retrained joint.
d.
Mains may be tapped as long as the tapping lineis smallerthan
the tapped line unless otherwise approved by the Augusta
Utilities Department. See Section G for service tap
requirements. Equal size line connections approved by the
Augusta Utilities Department shall require that a tee be cut
into the main where possible. Tees are also required at
locations dictated by the Utilities Director. Tapped
connecti ons in pipe and fittings shall b e made in such a manner
as to provide a watertight j oint and adequate strength against
pull-out.
Tapping Sleeves and Valve shall be ductile iron, mechanical
joint. Tapping sleeves and valves are required for all taps 4
inches and greater. Taps less than 4 inches shall be provided
with a service saddle meeting the requirements of Section G.
Valves shall be provided on all taps. Tapping sleeves shall be
a minimum of 6 feet from pipe joints.
e.
Schedule 40 PVC shall only be used as sleeves for the
installation of service line tubing under all pavement areas.
Use in the water distribution system or other areas are not
acceptable.
f.
Unspecified transitions from DIP to PVC are not allowed.
Material for transition shall be indicated and specified and
must be approved by the Augusta Utilities Department.
g.
All construction material shallbe first quality, not previously
used. Repair clamps are not acceptable. Damaged or faulty
pipe and materials must be properly replaced. All gaskets
shall be new. When connecting to existing valveSJr fittings,
gaskets shall be replaced, not reused.
h.
The Contractor shall provide a complete set of shop drawings,
which shall indicate the Augusta Utilities Department's
specific material requirements. In general, material
requirements will be guided by the latest versions of the
specifications of A WW A, ANSI, ASTM, and NSF.
TS-4-4
I
I
I
I
I
I
I
I
I'
I
I
I
I
I
I
I
I
I
I
F.
VALVES, FITTINGS AND APPURTENANCES
Gate valves, 4 inches to 12 inches, shall be the resilient seat type conforming
to A WW A C509 (latest version). Valves larger than 12 inches shall be gear
operated butterfly valves, conforming to A WW A C504 (latest version).
Wafer valves shall not be accepted.
Valves shall OPEN LEFT if installedsouth of Gordon Highway (SR 10), or
OPEN RIGHT if installed north of Gordon Highway. Valves shall be
provided with valve stem extensions to within 6 inches of ground surface,
where centerline of pipe to grade is greater than 4 feet.
Valve boxes shall be M&H E-2702, Mueller HI0364 or approved equal.
Each valve box shall be slip-type to adjust for a minimum cover of36" bury.
The flanged base of the valve box shall be at least six (6) inches above the
pipe so not to stress water lines 4" and smaller. Extension pieces will be
required for additional depth over valves. Extensions shall be M&H E-3120
or Mueller H-I0375. Covers shall have "WATER" cast on top.
All valves, bends, tees, crosses and dead ends shall be restrained by a
mechanical restraint systems as outlined in Paragraph 0 1.E.3, or by useof a
concrete thrust block in those instances that warrant such an installation.
Thrust blocks shall be poured-in-place concrete having a minimum
compressive strength of 3,000 psi after 28 days of cure time. All materials,
fittings and appurtenances intended for use inpressure pipe systems shall be
designed and constructed for a minimumworking pressure of 150 psi unless
the specific application dictates a higher working pressure requirement.
Standard pressure pipe fittings of size four (4) inch ill and larger shall be
ductile iron conforming to AWWA C153 (latest version), with mechanical
joints unless flanged or restrained joints are required. Gray cast-iron fittings
are not allowed. Ductile iron fittings shall be cement lined in accordance with
AWWA CI04 (latest version). Mechanical joint fittings, 24 inches and
smaller shall be rated for 350 psi working pressure. Flanged joint fittings 24
inches and smaller shall be rated for 250 psi working pressure. All fittings 30
inches and larger shall be rated for 250 psi working pressure. For sizes less
than four (4) inch ill, fittings shall be suitable to the pipe material and
application. Glands for mechanical joint fittings shall be ductile iron, and tee
bolts and nuts shall be Cor-Ten steel. Only bolt systems furnished by the
manufacturer for mechanicalj oints are acceptable; nuts and bolts shall be new,
not reused. Pipe gaskets shall be new as supplied by the pipe manufacturer.
All flanges shall beductileiron Class 150, ANSI B16.5. All flanges shall be
flat faced. Full face, 1/8 inch black neoprene gaskets shall be used on all
flanged joints. All joints shall conform to AWWA C111 (latest version).
Bolts, nuts and washers for flanges shall be hot dip galvanized, except T -bolts
shall be Cor-Ten steel.
TS-4-5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
List of Specifications
ANSI!AWW A C151/A21.5l-96 4-FEB-1996 or latest version
American National Standard for Ductile-Iron Pipe, Centrifugally Cast, for
Water
ANSI!AWWA C150/A21.50-96 1996 or latest version
American National Standard for Thickness Design of Ductile-Iron Pipe
ANSI! A WW A C 115/ A21.15-94 1994 or latest version
American National Standard for Flanged Ductile-Iron Pipe With Threaded
Flanges
ANSI! A WW A C 111/ A21.1l-95 1995 or latest version
American National Standard for Rubber-Gasket Joints for Ductile-Iron
Pressure Pipe and Fittings
ANSI!AWWA C153-98 1998 orlatestversion
American National Standard for Ductile-Iron and Gray-Iron Fittings, 3 in.
through 48 in. (75 mm through 1200 mm), for Water and Other Liquids
ANSI!AWWA CI04/A21.4-95 1995 orlatestversion
American National Standard for Cement-Mortar Lining for Ductile-Iron
Pipe and Fittings for Water
G.
WATER SERVICE LINES AND TAPS
Tapping sleeves and tapping crosses shall be of a heavy body ductile iron,
mechanical j oint suitable for a working pressure of 150 psi for sleeves and
crosses larger than l4-inch (200 psi for sleeves and crosses equal to or less
than 14-inch), as approved by the Augusta Utilities Department.
No direct service taps shall be allowed. All service line taps shall be supplied
with corporation stops. Service line tubing shall be rolled of soft continuous
and seamless copper Type K conforming to A WW A C800 and ASTM B-88
(latest version).
Corporation Stops and Main Connectors:
%" FB600 - 3 Ford or Equal
I" FB600 - 4 Ford or Equal
Taper Thread Inlet by Flare Copper Outlet
Eighth Bends:
%" LA02 - 33 Flare 1/8 Bend
%" LA04 - 33 Compression 1/8 Bend
TS-4-6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I" LA02 - 44 Flare 1/8 Bend
1" LA04 - 44 Compression 1/8 Bend
Minimum size for residential use shalhe one (1) inch. The service line shall
be laid in a straight line and be of a continuous piece of pipe from corporation
to curb cock. The curb cock shalLbe located 6 inches behind and 8 inches
below the top of new curb or edge of asphalt. Where service connects to DIP
or any pressure-rated pipe, service saddles must be used. Brass double strap
tapping saddles shall be used. U-bolt type straps are not acceptable. All
water service taps on the main shall be spaced at a minimum distance of 18
inches apart and a minimumof 18 inches from a bell or fitting. If two or more
taps are required at a minimumspacing, they shall be offset 450 alternatively.
Services greater than one (1) inch shall be seamless galvanized. 2" services
shall have two 2" 90-degree galvanized elbows per Augusta Utilities' 2 Inch
Water Service detail.
Services shall not exceed over 100 feet from the main to the meter. Where
possible, meter shall be placed in unpaved area as close to the water main as
possible.
-02.
CONSTRUCTION:
A. WATER DISTRIBUTION SYSTEM INSTALLATION:
Authorization must be obtained from the Augusta Utilities Department to
construct, alter or modify a water line. Construction of water infrastructure
will be authorized by the Utilities Department upon approval of submitted
plans and notification of the Augusta Utilities Department at least 24 hours
prior to starting construction (706-772-5503). Where water lines will
encroach publicright-of-way, a Right-of- W ay Encroachment Permit approved
by the Public Works Department is required prior to construction. A Right-
of-Way Encroachment Permit application is available through the Public
Works Department (706-821-1706).
Installation of water mains and associated appurtenances shall be in
accordance with current A WW A specifications and manufacturer's
requirements for the specific product. Loading or unloading and storage of
pipe, fittings, valves, etc. shall be done such that to avoid damage. The
interior of all pipe, fittings, valves, etc. shallbe kept free of dirt and foreign
matter at all times. All piping shall be placed in a dry trench with a stable
bottom. Wet trench installation shall be allowed only upon written approval
of the Utilities Director.
Mechanical restraint systems shall be required at each fitting involving a
change of direction and as specified in the approved plans. Concrete thrust
blocks will be allowed in lieu of mechanical restraint systems.
TS-4-7
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Backfill shall be free of boulders and debris, and shall cornform to Georgia
Department of Transportation Specifications. Sharp or rocky material
encountered in the base shall be replaced with proper bedding. Pipe shall be
laid on line and grade as designed. Pipe joints, gravity blocks, service
connections, and conflicts shall be left exposed until visually inspected and
approved by the Augusta Utilities Department's Inspector.
All valves shall be placed according to plans. Valve stems shall be installed
plumb. Valve stem extensions are required as described in Section F. Air
reliefvalves shall be installed at all high points in the water main where air can
collect, as shown on the plans or as directed by Augusta Utilities.
List of Specifications:
ANSI! A WW A C600-93 1993 or latest version
Installation of Ductile-Iron Water Mains and Their Appurtenances
ANSI!AWWA C605-94 30-JAN-1994 or latest version
Underground Installation of Polyvinyl Chloride (PVC) Pressure Pipe and
Fittings for Water
ANSI!AWWA C512-92 1992 or latest version
Air Release, AirN acuum and Combination Air Valves for Water Works
Servi ce
1. Handling and Storing of Materials: Unload pipe so as to avoid
deformation or other injury thereto. Place no pipe within pipe of a
larger size. Store pipe and fittings on sills above storm drainage level
and deliver for laying after the trench is excavated. Valves shall be
drained and so stored as to protect them from freezing.
2. Pipe Laying(General): The interior of the pipe shall be clean and j oint
surfaces wiped clean and dry when the pipe is lowered into trench.
Lower each pipe, fitting and valve into the trench carefully and lay
true to line and without objectionable breaks in grade. The depth of
cover below finished grade shall be not less than 3 feet,or as shown
on the drawings. Give all pipes a uniform bearing on the trench
bottom. Allow no trench water or dirt to enter the pipe after laying.
Insert a watertight plug in the open end of the pipingwhen pipe laying
is not in progress.
3. Reaction Blocking: All plugs, caps, tees, bends and other fittings shall
be provided with adequate reaction blocking as shown on the
drawings. Reaction blocking shall be made to bear directly against the
undisturbed trench wall. Where trench conditions are, in the opinion
of the Engineer, unsuitable for reaction blocking, the Contractor shall
provide tied joints to adequately anchor the piping as shown on the
TS-4-8
I.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
drawings. All the rods and clamps shall be given a bituminous
protective coating.
4. Connection to Existing System: All connections to existing mains
shall be made under the direct supervision of the Augusta Utilities
Department's Inspector. Valves on existing mains shall be operated
by or under direct supervision of Augusta Utilities Department
personnel. Tapping sleeves and valves shall be pressure tested prior
to tapping. If service to existing customers must be cut off, the
Augusta Utilities Department shall be notified at least three(3) days
in advance to make necessary notifications. The Contractor shall
disinfect and secure appropriate Utilities Department clearancesand
samples for any service interruptions which occur as a result of a
Contract request for shut down or error. The clearances shall be
obtained within 72 hours of reactivation.
If cut-off of service is required, the Contractor shall be ready to
proceed with as much material pre-assembled as possible at the site to
minimizethe length of servi ce interruption. Augusta Utilities reserves
the right to postpone service cut-off if, in the opinion of the Utilities
Director, the Contractor is not ready to proceed on schedule. No
customer should be without water for more than four (4) hours. The
Owner/Developer shall arrange for temporary services to Customer
if water will be shut off for more than four hours.
Local chlorination will be required for all pipe and fittings used to
complete connections with the potable water sy stem. Tapping sleeves
and valves shall be chlorinated in accordance with A WW A
requirements. All wet taps shall be witnessed by the Augusta Utilities
Department's Inspector.
B.
CLEANING AND FLUSHING:
Upon completion of installation, the mains shall be flushed and the water
disposed of without creating a nuisance. Flushing must achieve a minimum
water velocity of 2.5 fps in all portions of the pipe. The duration of the
flushingwill be determined by the Augusta Utilities Department' s Inspector.
If, in the opinion of the Augusta Utilities Department's Inspector, there is
insufficientwater availablefor proper flushing, the Contractor shall clean the
lines by pigging. No flushing or cleaning shall take place without an Augusta
Utilities representative present. The existing mains that the new mains are
connected to may be required to be flushed under the direction of the Augusta
Utilities Department when service is restored.
TS-4-9
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
C.
TESTING AND DISINFECTION:
Pressure and Leakage Testing: Before any work will be accepted for
payment, the Contractor will fill the piping with water, open outlet as
necessary for expellingthe entrapped air. No fire hydrant shall be opened full
force during charging operations. Thereafter, furnish the necessary equipment
and test the piping under the supervision of the Engineer for a period of at
least 4 hours at not less than 1.25 times the design pressure in pounds per
square inch, based upon the highest elevation of the section under test.
Pressuretestingshallbeinaccordancewith the latest A WW A Standard C600,
Section 4.1. at 1. 5 times the working pre.ssure at the point of testing. Inspect
all joints, and remedy to the satisfaction of the Engineer any defects
discovered. Continue the test until all visible leaks have been eliminated from
the part of the system under test, and the pressure remains constant with a
maximum pressure drop of 5 psi for the duration of the test.
All water mains shall be leak tested. The Contractor shall provide all
equipment, materials and labor necessary for pressure and leak testing. This
test must be observed by an Augusta Utilities Department representative and
the design engineer. A pumping pressure of 200 psi must be supplied at the
expense of the Contractor. The main tested shall either be isolated from
active potable lines or protected from leakage by a double valve arrangement.
All water used for pressure testing must be potable water with an adequate
chlorine residual. Water lines shall be tested by valve sections. Maximum
allowable leakage shall be as determined in accordance with current A WW A
specifications. The standard duration. of test is four (4) hours. Testing
procedures shall meet or exceed A WW A C600 (latest version) requirements.
Any portions of the main which fail the test shall be replaced or adjusted until
the entire new main passes the test criteria. The pressure and leakage test
shall be done concurrently.
Augusta Utilities shall be notified at least 24 hours in advance to schedule
bacteriological testing of water mains. The Contractor shall replace or adjust
components of the pipeline which fail the test. Clearance is required from the
Utilities Department before the Augusta Utilities Department will allow the
main to be put into service.
Immediately following the pressure test, and before any work will be accepted
for payment, the Contractor shall perform a leakage test. Leakage is defined
as the quantity of water to be supplied into the newly laid pipe, or any valved
section thereof necessary to maintain the specified leakage test filled with
water to within 5 psi of the test pressure. No pipe installation will be accepted
until the leakage is less than the number of gallons per hour as determined by
the formula:
L
snIP
133200
TS-4-l0
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
L = Allowable leakage in gallons per hour.
S = The length of pipe in the section tested.
D = The nominal diameter of the pipe in inches.
P = The average test pressure during the leakage test in pounds
per square inch gauge.
The leakage test shall be conducted in accordance with A WW A Standard C-
600, Section 4.1 (latest version).
All piping complete with fittings and appurtenances shall be sterilized as
specified in the applicable sections of A WW A Specification C651 (latest
version) "Disinfecting Water Mains." Piping and appurtenances shall be
thoroughly flushed then chlorinated with not less than fifty parts per million
(50 ppm). Calcium hypochlorite can be used. Water from the existing
distribution system or other source of supply should be controlled so as to
flow slowly into the newly laid pipeline during the application of chlorine.
The solution should be retained in the pipeline for not less than 24 hours and
a chlorine residual of 10 ppm should be available at this time. The system
shall then be flushed with potable water and the sampling program started.
Sampling taps and chlorinated water used for disinfection shall be flushed to
a location that will not damage property, persons, etc., and shall be provided
by the Contractor at the expense of the Contractor. The provisions of this
paragraph apply equally to new pipe and fittings and to existing pipelines into
which connections have been made or which may have been otherwise
disturbed to the extent that contamination may have occurred. All
requirements of the health authorities shall be observed in executing this work.
The disposal of heavily chlorinated water (following disinfection) must be
accomplished in accordance with the latest editions of the A WW A Standard
C651 and the EPD's Minimum Standards for Public Water Systems.
Two or more successive sets of samples, taken at 24 hour intervals and tested
by a State approved private lab, shall indicate bacteriologically satisfactory
water and the results submitted to the Augusta Utilities Department.
D.
WATER/SEWER SEPARATION:
A 10 foot horizontal separation shall be maintained between water and sewer
lines. Where the horizontal separation cannot be met or where water and
sewer lines must cross, an 18 inch vertical separation, water over sewer must
be maintained. Where the above conditions cannot be met, water and sewer
lines shall be cast iron or ductile iron pipe with joints staggered such that
maximum separation between joints exists. The water line shall be installed
over the sewer line.
E.
AS-BUILT DRAWINGS:
As the work progresses, record on one set of utility drawings all changes and
deviations from the contract drawings in sizes, lines or grade. Record also the
exact final location of water lines by offset distances to surface improvements
TS-4-11
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
such as edge of existing pavement or to property lines, etc. at a maximum
interval of 200 feet. Make sufficient measurements to locate definitely all
water lines etc., to permanent points. The drawings will show references to
all valves, fittings, pipe brand changes, etc. Transfer accurately all such
records in red pencil to white prints of the utility drawings and deliver them
to the Engineer with montWy payment estimate.
TS-4-l2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
J
I
I
I
I
SECTION TS-5
EROSION CONTROL MEASURES
-01. GENERAL:
This section covers erosion control measures required on the job as shown on the
plans. These measures are minimum requirements and may be augmented by the Engineer if positive
control is not established.
-02.
CONSTRUCTION SCHEDULE:
The initial construction on the site is tentatively scheduled to begin on or about
February, 2005. Final stabilization of the soils should be obtained by April, 2005.
-03. EROSION AND SEDIMENT CONTROL PLAN:
The following steps for reducing erosion and containing sediment are recommended
for use during construction, and until the earth areas can be stabilized with vegetation.
-04.
-05.
GENERAL PROCEDURES:
1.
Earth areas which are not to be paved shall be grassed at the earliest possible time
during the construction phase, so as to minimize exposure to rainfall and run-off.
2.
Temporary berms, wherever possible, should be constructed at the end of each day
of grading, in order to contain sediment and slow down erosion in the cut and fill
areas, should rainfall occur during the night. Berms shall also be constructed, where
needed, to prevent sediment from being transported onto areas outside the actual
construction limits.
3.
Silt and erosion barriers of the type which tend to filter suspended solids from the
water flowing through them shall be employed to the extent necessary to contain most
of the water -borne silt. Examples of this type ofbarrier include II silt" fence, windrows
oflimbs and laps, and stone or rubble riprap.
4.
Erosion due to wind is not likely to be of concern on this project, considering the
types of soils expected and the strip-like geometry of construction areas. However,
wherever possible, trees or groups of trees and bushes should be left standing to
serve as windbreaks.
5.
Sediment basins shall be constructed if shown on plans and removed when final
stabilization is attained.
ELEMENTS OF THE PLAN:
The plans for the prevention of erosion and sedimentation for this site will be
determined in the field. The elements of the plan are discussed as follows, and are listed in
chronological order, as far as is practical. The construction activities should proceed in the order
listed.
1. Remove all marketable timber from the rights-of-way, the utility easements, the
designated fill areas, and other areas to be cleared.
TS-5-l
I
I
I
I
I
I
I
I
I
r
I
I
I
I
I
I
I
I
I
2.
Begin clearing and grubbing operations in the vicinity of the hay dams shown on the
drawings. Immediately after the area has been cleared for their placement, install
dams and berms consisting of hay or straw bales or limbs and laps as directed, to be
silt barriers as shown on the drawings. Care should. be taken not to clear and grub
beyond the construction limit.
3.
As grading operations commence, the topsoil shall be stripped and stockpiled in
mounds surrounded by berms. As mentioned above, berms or windrows should be
constructed each afternoon at approximately 100 foot intervals across the graded
areas, except in the low-lying areas of the project. This action will tend to check
erosion should rainfall be experienced during the night.
4.
Construction on the sanitary and storm sewer lines should be commenced as soon as
grading operations have been substantially completed. The disturbed strip along each
line which is located outside of a street right-of-way should be grassed immediately
upon the completion oftrench backfilling, as described below.
5.
A graded depression around each catch basin on the site should be used to contain
sediment during construction. A ring of hay or straw bales, or silt fencing, secured
to the ground by mean of two No.3 reinforcement bars or other suitable anchoring
method, should be installed around each catch basin site as soon as the drainage pipes
have been laid. These should be spaced leaving a gap of approximately three inches
between each bale where hay is used.
6.
As soon as the graded areas which are not to be paved, to be built upon, or receive
underground utilities have been brought to final grade, three or four inches of tops oil
shall be spread over these areas. Grassing operations should be begun immediately,
as described in the grassing specifications. Roadway shoulders and slopes should
receive a similar treatment as soon as the installation of the utilities has ended.
7.
All grassing will be performed in accordance with the section of the specifications
entitled" Grassing (Bermuda)". Should seasonal limitations prevent the establishment
of the permanent grass cover, the area to be grassed shall be covered with temporary
grass cover; then the permanent grass will be established as soon as its growing
season is reached.
8.
The hay bale dams and silt fencing described above should not be removed until the
surrounding pavement base material has been placed and is ready for priming.
9.
All silt retention basis, traps, barriers, etc., should be inspected daily and cleaned at
least weekly.
10.
All work shall be in accordance with good grading practice and shall conform to
accepted practices in Erosion Control.
TS-5-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-6
GRASSING (BERMUDA)
-01.
SCOPE:
This section covers the furnishing of all labor and materials and the performance of
all work required to assure the establishment of a dense permanent cover of Bermuda grass on all
areas of the site disturbed by construction operations.
-02.
SEED BED PREPARATION:
Final grades will be established as shown on the plans prior to any seed bed
preparation. Washes, low spots and hillocks or windrows will be evened and the bed will be
smoothed to facilitate uniform drainage after establishment of the turf. Graded surfaces will be
maintained in a smooth and even condition until the required cover is established.
After the areas to be seeded have been brought to an even and smooth grade, they
shall be thoroughly loosened to a depth of at least 6 inches by plowing, discing, harrowing, or other
approved methods until the tillage is acceptable as suitable for seeding. During tillage operation, the
surface shall be cleared of all roots, cable, wire, or other waste material which might hinder final
grading, planting, or subsequent maintenance operations. Any operations of the Contractor, shall be
smoothed out before seeding operations are begun.
-03. FERTILIZATION:
At least two soil samples per acre shall be taken by the Contractor and analyzed to
determine the suitability ofthe particular soil for planting. Fertilization and lime application rates shall
be set accordingly. The rates given in the following paragraphs shall be used for bidding purposes
and differing quantities will become the basis for an equitable adjustment in the contract price.
Fertilizer shall be distributed uniformly at a rate of 1500 pounds of commercial 6 .12.12
analysis fertilizer per acre, and shall be incorporated into the soil to a depth of approximately 3 inches
by discing, harrowing, or other approved methods. The incorporation of fertilizer may be a part of
the tillage operation specified above, or a part of the hydroseeding procedure as described below.
Immediately following, or simultaneously with, the incorporation of fertilizer, lime
shall be distributed at the rate of 3000 pounds per acre and shall be incorporated into the soil to a
depth of at least three inches by discing, harrowing, or other acceptable methods. The incorporation
oflime along with the fertilizer may forma part of the tillage operation specified above.
Not less than 30 days after completion of seeding, the Contractor shall furnish and
apply Nitrate of Soda or Ammonium Sulphate to the planted areas. Nitrate of Soda shall be a com-
mercial product, containing not less than 16 percent Nitrogen and Ammonium Sulphate not less than
20 percent Nitrogen. The Nitrogen fertilizer shall be uniformly spread and distributed with approved
equipment at a rate that will give not less than 60 pounds of available Nitrogen per acre. Other
commercial types of nitrogenous material may be substituted at the option of the Contractor. The
time of application shall be limited to the season of June through August.
TS-6-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
!
I
-04.
SEEDING:
Permanent grass cover will consist of Common Bermuda seeded in accordance with
one of the following methods:
1. Between the dates of April 1 and June 1, Hulled Common Bermuda seed shall be
applied at a rate of 10 pounds of seed per acre.
2. Between the dates of October 1 and March 1, Unhulled Common Bermuda seed shall
be applied at a rate of 10 pounds of seed per acre.
3. If seeding is undertaken between September 15 and Februaryl5, Unhulled Common
Bermuda seed shall be applied at a rate of 1 0 pounds of seed per acre simultaneously
with Rye seed at a rate of 28 pounds per acre.
Seed may be applied by means of a Hydro-seeder or other means approved by the Engineer.
-05.
COMPACTION:
Immediately after seeding operations have been completed, the areas shall be
compacted by means of a cultipacker, roller wood float, or other approved equipment sufficiently
weighted, or compacted by hand methods, to reduce air pockets to a minimum. The complete planted
area shall be left with a firm, even surface, free from abrupt humps and hollows, and to the established
grade.
-06.
MULCHING:
All areas planted for temporary or permanent grass shall be uniformly mulched with
hay or straw at the rate of 2 'h tons per acre, except where hydro seeding is employed using a
cellulose mulch mixed with the seed and fertilizer.
-07. ACCEPTANCE:
Grassed areas will be accepted when a 95% cover by permanent grasses is obtained
and weeds are not dominant.
TS-6-2
I
I
I
I
I
I
I
I
I
r
I
I
I
-01.
A.
SECTION TS-7
ON-SITE SODIDM HYPOCHLORITE GENERATION SYSTEM
GENERAL:
WORK INCLUDED
1. This Section covers the work necessary by the General Contractor and On-site
Sodium Hypochlorite Generation System (OSHGS) Supplier to furnish, install, test
and make ready for operation an On-site Sodium Hypochlorite Generation System.
The Generation System includes, but is not limited to the Sodium Hypochlorite
Generator Skid with integral water softeners, piping, valves, system control cabinet
with PLC as well as ancillary equipment as specified herein, installation, related
testing, start-up and training services.
2. The OSHGS Supplier shall furnish the following components of the Skid Mounted
OSHGS Generation System at a minimum:
a. Sodium Hypochlorite Generation cells
b. 304 Stainless Steel Skid
c. Interconnect piping, valves, solenoid control valves and accessories
d. Control cabinet, PLC and associated equipment
e. Water Softener
f Salt/brine tank
g. Sodium hypochlorite solution storage tank
h. Feed pumps and motors
3. The General Contractor shall install the OSHGS, as specified in this specification and
as shown on the drawings. The General Contractor shall be responsible for
connecting all conduit, wire, pipe, etc. for the OSHGS supplied equipment to the
equipment, including piping from the feed pumps to the injection points to provide a
complete and fully operational OSHGS.
4. The OSHGS Supplier shall inspect the installation of the Generation System and the
General Contractor correct systems errors if any. Following the correction of all
errors, the OSHGS Supplier shall provide a Certification of Proper Installation for the
Generation System.
5. The OSHGS Supplier shall submit Shop Drawings required for the fabrication,
installation and control of the Generation System equipment. The Shop Drawings
shall be submitted to the Owner for review and approval.
6. The OSHGS Supplier shall be responsible for programming the Generation System
package control software. The OSHGS Supplier will supply an Allen Bradley
MicroLogix 1500 for use in the OSHGS. The Supplier shall program the PLCs
compatibility with the Owner's SCAD A control systems. The Engineer or Owner will
TS-7-1
I
I
I
I
I
I
I
I
provide PLC programming protocol to the OSHGS Supplier, and criteria for the
interconnection of the Generation System PLC with the SCADA system PLCs.
7. The OSHGS Supplier shall perform functional, performance and start-up testing of
the Generation System.
8. The OSHGS Supplier shall submit an Operation and Maintenance Manual and
Maintenance Summary Forms for the Generation System. The O&M Manual and
Forms shall be reviewed by the General Contractor and issued to the Engineer for
review and approval.
9. The OSHGS Supplier shall train Owner's personnel and provide detailed instructions
in the operation of the Generation Equipment.
B.
GENERAL
1. All electrical, mechanical, metal, painting and instrumentation work included herein
shall conform to the applicable Sections or Divisions of this project except as
otherwise shown or specified. The OSHGS shall be shipped as one self contained unit
with all factory piping and wiring complete to input and output, flanged, threaded,
etc. connections located at easily accessible points on the skid. The standard for pipe
and conduit for the skid interconnect is; schedule 40 PVC.
2. The Drawings show details ofthe components and their overall relationships. Not all
items incidental to the OSHGS are shown or specified. It is the intent of these
Contract Documents that the OSHGS Supplier is to provide a complete and workable
system whether or not any specific component is shown or specified.
3. Power shall be provided by the General Contractor to the system control panels as
shown on the OSHGS skid drawings. The General Contractor shall be responsible for
providing all necessary conduit and wiring necessary for a complete electrical service
to this location. All wiring shall comply with the National Electrical Code, 1996
edition.
C. REFERENCES
1. The following references apply:
a. American National Standards Institute (ANSI).
b. American Society for Quality Control (ASQC).
c. American Society of Mechanical Engineers (ASME).
d. American Society for Testing Materials (ASTM).
e. American Water Works Association (A WW A).
f. The Chlorine Institute (CI).
g. Confinement of Substances Hazardous to Health (COSHH).
h. Institute of Electrical and Electronics Engineers (IEEE).
1. International Standards Organization (ISO).
TS-7-2
I
I
I
I
I
I
I
I
I
I
J. National Electrical Code (NEC).
k. National Electrical Manufacturers Association (NEMA).
l. National Fire Code (NFC).
m. National Institute of Occupational Safety & Health (NIOSH).
n. Occupational Safety and Health Administration (OSHA).
o. Standard Fire Code (SFC).
p. Uniform Fire Code (UFC).
q. Water Environment Federation (WEF).
D.
SYSTEM DESCRIPTION
1. Feed Points - Under normal operating conditions, site generated sodium hypocWorite
solution (nominally 0.8 percent) will be injected into the process at locations shown
on the drawings for disinfection.
2. Functional Requirements
a. Instrumentation, controls, logic, programming, interlocks and valving shall be
provided by the OSHGS Supplier as required for the system to operate as
described below.
b. General arrangement, piping sizes and accessories are shown on the
Contract Drawings.
3. Generator Operation
a. The generator shall automatically start and stop based on the high and low
levels in the sodium hypochlorite solution day tank.
b. The water softener resin shall automatically be regenerated with salt solution
from the brine tank.
c. The generator shall shut down and alarm for the following conditions:
(1) Cell is not full
(2) Hypochlorite temperature exceeds 1200F (490C)
(3) Inlet flow falls below a preset value
(4) Rectifier high voltage
(5) Rectifier high temperature
d. The following additional alarms shall be provided on the control panel:
(1) Low-low level for Day Tank
(2) High-high level for Day Tank
(3) Alarms for Injection Pump #1
(4) Alarms for Inspection Pump #2
TS-7-3
I
I
I
I
I
r
I
4.
Level Indicators for Day Tank
a. The OSHGS Supplier shall provide internal ultrasonic level transmitters on
each storage day tank for operation of the generation equipment and alarm
initiation. Level controls for each tank shall be brought to the operator
interface for selection of the active tank.
b. The level transmitters shall provide 4-20 mA signals linearly proportional to
monitor and send the following four (4) specific level conditions to the
hypochlorite system panel and to the SCADA interface panel via the data
highway:
(1) One (1) high for generator shut-off
(2) One (1) low for generator start
(3) One (1) high-high for high level alarm
(4) One (1) low-low for low level alarm
E. SUBMITTALS
1. Shop Drawings - The OSHGS Supplier shall submit the following to the Owner, for
approval by the Owner, six (6) sets of shop drawings for each generation system in
accordance with the following:
a. Manufacturer/Supplier's literature, illustrations, Specifications and bill of
materials for each component of the system. Data shall include a complete
description in sufficient detail to permit comparison with the technical
Specifications.
b. Dimensions (including anchor bolt layout), materials, SIze, weight and
performance data.
c. Drawings showing fabrication, assembly, installation and wiring diagram.
Wiring diagrams shall consist of, at a minimum, of control schematics,
including coordination with other electrical control devices operating in
conjunction with the Sodium hypochlorite generator feed system.
d. Motor Data: For each motor furnish a certified motor data sheet for the actual
motor.
e. Pump Data: For each pump furnish a performance certification indicating:
head, capacity, efficiency and horsepower.
f A list of all parameters, ratings or other characteristics where the proposed
Sodium hypochlorite generator system deviates from the requirements set
forth in these Specifications.
g. Affidavits of compliance with referenced standards and codes.
TS-7-4
I
I
I
I
I
I
r
I
!
h. Manufacturer/supplier's standards for Sodium hypochlorite generator system
equipment.
1. Process flow diagrams.
J. Control logic diagrams incorporating the Owner's SCADA System.
k. Dimensioned inlet/outlet system connections.
1. The acceptable range of water pressure for proper system operation. If a
pressure or flow regulator is required, it shall be provided.
2.
Operation and Maintenallce Data - The OSHGS Supplier shall submit two (2) copies
of preliminary Operation and Maintenance manuals and four (4) copies of the final
manuals for each generation system as described below:
a. Required Operation Data
(1) Complete, detailed operating instructions for each piece of equipment.
(2) Explanations for all safety considerations relating to operations.
(3) Recommended spare parts lists
b. Required Maintenance Data
(1) Maintenance data shall include all information and instructions
required by plant personnel to keep equipment properly cleaned,
lubricated and adjusted so that it functions economically throughout
its full design life.
(2) Explanation with illustrations as necessary for each maintenance task.
(3) Recommended schedule of maintenance tasks.
(4) Lubrication charts and tables of alternate lubricants.
(5) Troubleshooting instructions.
(6) List of maintenance tools and equipment.
(7) Name, address and phone number of manufacturer and manufacturer's
local service representative.
F. QUALITY ASSURANCE
1. OSHGS Supplier's Qualifications
a. The OSHGS Supplier shall have experience in furnishing equipment of similar
capacity and service capability to the equipment described herein. As part of
their submittal package, the system manufacturer shall submit the following:
(1) Evidence that equipment of similar capacity and service capability has
been in successful operation in at least five (5) separate installations
TS-7-5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
,
,
I
within Georgia.
(2) Current NSF Standard 61 Certification for the system being offered.
(3) Evidence of certification by the Environmental Technology
Verification Drinking Water Treatment Systems program, conducted
by the E.P.A & N.S.F to verify the performance claims of the system
manufacturer.
(4) The Sodium hypochlorite generation equipment shall be pre-
assembled and tested to assure compliance with pressure and
operational requirements.
G.
DELIVERY, STORAGE AND HANDLING
1. The General Contractor shall be responsible for the delivery, storage and handling
of products in accordance with the manufacturer's recommendations. The OSHGS
shall be provided with a minimum of four lifting lugs integrally welded to the skid
framing.
H.
WARRANTY REQUIREMENTS
1. Prior to acceptance of the Sodium hypochlorite generator system, provide written
warranty from the OSHGS Supplier that includes the following statements:
a. OSHGS Supplier has inspected the installation.during and after completion
and the Sodium hypochlorite generator system is free from faults and defects
and is in conformance with the Contract Documents.
b. OSHGS Supplier must provide the following after sales services:
(1) Must provide a 24-hour 365-day toll free service hot line.
(2) On site technician availability.
(3) Next day or overnight parts availability.
(4) Must provide evidence of spare parts availability on this system such
as electrodes, rectifiers, control cabinets, metering pumps.
c. Sodium hypochlorite generator system will remain free of defects for a period
of two (2) years from the date of final acceptance.
d. If the equipment requires repair or replacement because of ordinary wear and
tear under normal conditions, the OSHGS Supplier will repair or replace such
equipment as required without cost (including shipping and handling) to the
Owner.
e. OSHGS Supplier will provide a five-year not to exceed cost guarantee for
replacement of the anodes.
TS-7-6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I.
1.
-02.
A.
B.
f The electrodes shall have a 2-year full replacement warranty and a 3-7 year
prorated straight-line replacement warranty from the date offinal acceptance.
g. The warranty period shall start from the date of commissioning of the system.
SYSTEM START-UP
1. The chlorination equipment manufacturer shall furnish the services of a qualified field
engineer to check installation, start-up and instruct operating personnel in the proper
operation and maintenance of the equipment.
COMPONENT SELECTION
1. Suppliers are strongly encouraged to use materials and/or components made in the
US.A. Any component which is not made in the US.A. shall require individual
submittals and pre-approval prior to installation.
PRODUCTS:
PRE-APPROVED MANUFACTURER
1. The pre-approved OSHGS equipment supplier is Severn Trent Water Purification,
Inc. / ClorTec. The equipment is indicated as a basis of design and being non-
proprietary, this equipment represents the minimum acceptable standard of quality for
equipment, materials and methods of construction. Other packaged booster pumping
station suppliers shall seek approval by the engineer a minimum often (10) calendar
days prior to bid opening. A pre-bid submittal for any alternate equipment
substitutions will be required as outlined within this specification.
2. A list offive (5) installations where similar equipment by the manufacturer is currently
in similar service; include contact name, telephone number, mailing address of the
municipality of installation, engineer, owner, and date of installation. If five
installations do not exist, the list shall include all that do exist. If no installations exist,
a statement.to that effect must be included.
GENERATOR SYSTEM EQUIPMENT
1. Provide one sodium hypochlorite generator system, capable of producing 24 pounds
per day chlorine equivalent as 360 gallons per day 0.8% sodium hypochlorite solution.
2. Generation system shall have a 48-hour reserve capacity for sodium hypochlorite
solution.
3. The electrolytic system shall generate an aqueous solution of a IDlmmum
concentration of 0.8 percent (::l:O.05%) by weight sodium hypochlorite expressed as
TS-7-7
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
4.
7.
chlorine. The minimum capacity shall be demonstrated to be equal to the capacity
specified for each installation while not exceeding the maximum raw material
quantities.
The electrolytic cell shall consume a maximum of 3 .0 pounds of salt per pound of
chlorine equivalent output, using solar salt containing no organic binders, flow control
agents or resin cleaning material, and meeting the following specifications:
:.. ....... ....... .... ......................... ..... ...... ....~.......... .........." ................ ............ ..............~
:~., i
t..~~.r:4...(~g~g)...........................w....J...}Y.~.!gg!.........w...........w.w........w........w.w........J
j NaCl: 1 !
r........:.:.:.......:.~.....:.:.........~.:~.:~~~I~..~..~...........:...:r.:.?~.:Ir;:.:~~~g;;........:.:.........:~.:.:..':':':'.]
~ - wet i 93.3% minimum I
~.~~~~~~~~w._nnnnnnnnn_nnnnnnnnn~nnnnnnnnn____n__n_________w._____t
~ Calcium Sulfate ; 0.30% maximum I
[::M~g~~~!~~:..~gg2E!~~::...:]:::.:Q;:Q:~~~:~~,~~~:.::....::..:.:.:~::.:...::.:.:.:]
~ Calcium Chloride i 0.10% maximum !
r...'iy.!~gri.~~1~iii...~~!.f~i~..................I....Q.:.2.~~...~~~~.!i..................................]
~ Insolubles ! 0.1% maximum !
E=m~l
~ Iron (as Fe\ i 0.002% maximum !
................. ............'1...............................................................................................
5.
The electrolytic cell shall consume a maximum of2. 0 AC kilowatt-hours of electricity
per pound of chlorine equivalent output.
6.
The electrolytic cell shall consume a maximum of 15.0 gallons of water per pound of
chlorine equivalent output. The raw water supply to the softener shall be free of
organics and suspended solids.
The generator shall have no waste products associated with its use other than
hydrogen gas, which is to be vented to the atmosphere.
8.
The generator package shall be mounted in the general location shown on the
drawings and shall be factory wired, plumbed and mounted on a self-contained skid
assembly.
9.
The generator package shall consist of the electrolytic cell( s), flow control panel,.
rectifier cabinet, control panel containing system controls, water softener with flow
meter and all necessary interconnecting wiring and hardware.
10.
The generator package shall have the following redundant interlocked safety features:
a. Cell high temperature switch, for each cell
b. Cell low level switch, for each cell
c. Rectifier over voltage switch
TS-7-8
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
d. Transformer high temperature switch
e. Automatic voltage and current regulation
11. The Bellows Pump shall function to automatically dilute concentrated brine with
softened water netting a2.8% solution to be delivered to the cell(s). The flow control
panel shall have valving capable of allowing the brine pump to blend muriatic acid into
the cell(s) for cleaning purposes.
12. All of the above safety features shall be interlocked to prevent operation if any of the .
normal parameters are exceeded. In the event of a trip condition, an alarm contact
set will be made signaling a shutdown condition. Each alarm condition, along with
normal operating status, shall be individually sent to the plant control system via the
data highway if provided by the Owner.
13. The process shall operate in a batch environment allowing for consistent hypochlorite
concentrations and greatest efficiencies.
14. The sodium hypochlorite generator equipment shall be the MCT Series as
manufactured by Severn Trent Services ClorTec, unless the equipment is approved
by pre-bid submittal as outlined within this specification.
C.
GENERATOR SYSTEM EQUIPMENT
1. The electrolytic cell shall be constructed of clear acrylic materials, allowing for full
visual inspection of electrodes from all angles.
2. Cell construction shall be tubular, allowing electrodes to be removed as a single
assembly. Any necessary joining of cell materials shall be by solvent welding or
mechanical compression. Thermal welding will not be allowed.
3. The tubular cells shall be factory tested to 55 psi, for a period of 3 0 minutes, before
final assembly and shipment.
4. The electrodes shall be titanium and the anodes coated with a mixed metal oxide
catalytic coating for electrical efficiency and maximum longevity. They shall be
vertically oriented solid flat plate construction to maximize the high velocity gas lift
between electrodes, which will minimize scaling. Expanded metal electrodes will not
be allowed.
5. Maximum allowable cell current density shall be no more than 1.20 amps/sq. in. The
OSHGS Supplier shall provide calculations showing all relevant cell data. Data shall
include electrode area measurements, and current flows. Electrode service factor shall
be expressed as amps per square inch of electrode surface.
6. The Electrolytic Cells shall be mounted for clear and easy access on the OSHGS skid.
TS-7-9
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
D.
CONTROL SYSTEM
1. The OSHGS Supplier shall provide a NEMA 12, 304 stainless steel, Sodium
Hypochlorite Control Panel, which shall include controls for the entire sodium
hyp 0 cWorite generation and feed system.
2. All controls and operation logic specified herein and as shown on instrumentation
loop diagrams required for the system shall be programmed in a Programmable Logic
Controller (PLC). The PLC shall be Allen Bradley MicroLogix 1500. General
Contractor shall coordinate with OSHGS Supplier, instrumentation supplier and
owner for proper integration of system.
3. The control panel shall display all relevant operating parameters and/or alarm
conditions.
4. The control panel cabinet will be UL 508 approved and house the operator interface
terminal (OIT), PLC, and terminal strips to fully support the functions of generator
operation, tank levels and metering pumps proportional control.
5. The OIT shall have the following features as a minimum:
a. Operation specific function keys
b. Dedicated scrolling keys for multiple message review
c. NEMA 4, 6-inch monochrome touchscreen.
d. Serial communications port for PLC connection
6. The control cabinet logic will function at the PLC level where operating parameters
will be measured, corrected, scaled, reported and controlled. The OIT will serve as
the operator interface, data input screen, and alarm log.
7. The generator PLC and display will control and monitor all functions and operational
parameters including, but not limited to, the following:
a. Cell safety devices
b. Rectifier control
c. DC amperage and voltage
d. Hypochlorite tank levels
e. Chlorine residual
f. Metering pump flow pacing and dosing
g. Alarm history
h. Maintenance log
1. Security protection
J. Altitude valve status (on Owner's system)
8. A single metering pump shall be activated whenever the existing altitude valve is
opened and deactivated when the altitude valve is closed. The status of this valve will
be relayed to the control panel via a limit switch on the valve itself.
TS-7-l0
I
I
I
I
I
I
I
I
I
1
I
I
I
I
I
I
I
I
I
9. The operation of the metering pumps shall be alternated in order to prevent excessive
wear of any one pump.
10. Both pumps shall be capable of operating in automatic or manual mode and shall be
compatible with the Owner1s SCADA system.
11. Additional controls and parameters to be coordinated with Owner pnor to
programmmg.
E.
GENERATOR SKID - The generation system shall be pre-piped and skid mounted. The
OSHGS skid frame shall be constructed of304 stainless steel tube steel. The power brush
finishing is a production methoQ of metal finishing that employs wire elastomer bonded wire,
or non-metallic (cord, natural fiber or synthetic) brushing wheels in automatic machines, semi-
automatic machines, semi-automatic machines and portable air tools to smooth or roughen
surfaces, remove surface oxidation and weld scale or remove burrs. Horizontal and vertical
tube steel sections shall be of . 25-inch wall thickness and have a depth no greater than thirty-
four inches by a length not exceed six feet. The skid frame shall be configured to allow easy
access to all components. All vertical and horizontal frame connections shall be welded
connections. Skid to be welded per ANSI!AWS A5.22-95, specification for stainless steel
electrodes for flux cored arc welding and stainless steel flux cored rods for gas tungsten arc
welding. The completed frame with all mounted components shall comply with the UBC
structural requirements of seismic zone four. The skid shall be fitted with a minimum of four
support legs and four transport wheels. The skid frame shall support as a minimum the
following mounted equipment:
a. Generator Electrolytic Cells
b. Control/Rectifier Panel
c. Water and Brine pump
d. Water softeners
e. Interconnect pipes valves and fittings
f. Interconnect conduit and wiring
F.
. TRANSFORMER RECTIFER - Locate transformer rectifier in the control cabinet.
Transformer rectifier at a minimum shall include the following: (1) Air-cooled power supply
/ linear rectifier, (2) Soft start constant current, (3) Emergency shut off switch.
G.
WATER SOFTENER - The water softener shall be dual tank, continuously operational and
capable of automatically regenerating without the use of electric timers or gear motors. The
softener shall be capable of exchanging 14,688 grains of hardness as CaC03 between
regeneration cycles. Regeneration cycles shall be flow dependent only. WASTE BRINE
SHALL BE DIRECTLY DISPOSED OF INTO A 5 GALLON BUCKET WHICH SHALL
BE REMOVED AND REPLACED BY MAINT AINANCE PERSONEL.
H.
BRINE TANK - The OSHGS supplier shall provide one 78 Gallon HDLPE salt/brine storage
tank with the storage capacity of 750 pounds of salt. Brine level control to consist of clear
TS-7-11
I
I
I
I
I
I
I
I
I
1
I
I
I
I
I
I
I
I
I
PVC external sight glass fitted with level sensing switch at 12" that actuate the primary
solenoid operated diaphragm valve. All level controls shall be operated and serviced at ground
level. Top mounted valves and controls are not acceptable.
1.
SODIUM HYPOCHLORITE STORAGE TANK
1. The supplier shall supply one 475 gallon, high-density linear polyethylene hypochlorite
storage tanks, 48-inches in diameter.
2. The polyethylene sodium hypochlorite solution tank( s) shall be provided with the
following accessories:
a. Ultrasonic level sensor and associated flanged connection. The level
transmitter shall provide a 4-20 mA level signal for proper operation of the
generation system.
b. Vent connection.
c. Fill connection.
d. Pump suction connection.
e. Drain and overflow connections.
f 12-inch top flanged manway with cover.
1.
SODIUM HYPOCHLORITE DOSING SYSTEM
1. The solution inj ection metering pumps shall be positive, hydraulic actuated diaphragm
proportioning pumps and shall be manufactured by a single manufacturer.
2. The solution metering pumps shall be suitable to operate 24-hour per day.
3. The metering pumps shall be able to operate with a 10: 1 turn down ratio, which can
be manually adjusted by a micrometer dial. Pumps must also have the capability to
be retrofitted with an electric positioner for stroke adjustments to be added by the
Owner at a later date.
4. Acceptable Manufacturer: Neptune
5. Sodium Hypochlorite Metering Pumps
a. Number required: Two
b. Maximum Feed Rate Capacity: 18 G.P.H. @ 80 P.S.I.
c. Speed Control: Constant
TS-7-12
I
I
I
I
I
I
I
I
I
1
I
I
I
I
I
I
I
I
I
M.
d. Materials of construction shall be suitable for use with 0.8% sodium
hypochlorite solution.
e. Pumps shall be equipped with double diaphragm heads with leak detection and
alarm.
f. Pumps shall be driven by an electric motor.
g. Pumps and components shall be mounted on a corrosion resistant skid.
h. Metering pumps shall be pre-set for the following conditions, at a minimum:
(1) Primary setting - 0.5 ppm @ 2200 gpm, which equates to an injection
rate of 8.2 gph
(2) Secondary setting - 1.0 ppm @ 2200 gpm, which equates to an
injection rate of 16.4 gph
1. Metering pump controls supplied by the O. S .H. G. S manufacturer as a part of
their control package
6. Each pump shall be supplied with a pulsation damper, backpressure valve, pressure
relief valve, and calibration column mounted on a polyethylene stand.
K.
WATER REA TER - A water heater is not required. Plumbing shall be in a configuration
which would allow the addition of a water heater at a later time by others.
L.
TOOLS, SPARE PARTS, AND MAINTENANCE MANUALS
1. The OSHGS Supplier shall furnish, one set of the following spare parts for each
installation, with each onsite sodium hypochlorite generator system:
a. One (1) complete set of fuses
b. One (1) set of spare parts kit for each of the pumps
c. One (1) set of spare parts kit for the backpressure and pressure relief valves.
d. One (1) electrolytic cell level and temperature switch assembly
2. Spare parts shall be packed in sturdy containers with clear indelible identification
markings and shall be stored in a dry, warm location until transferred to the Owner
at the completion of the contract.
3. Furnish an initial supply of all greases and lubricants required to start operations.
Supply an amount of these materials equivalent to one year of continuous operation
for each system.
SERVICE CONNECTIONS ON INTERNAL PIPING -All plumbed devices eventually
requiring service, such as meters, control valves, pumps and like equipment, shall be easily
TS-7-13
1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-03.
A.
B.
removed from the piping by the presence of appropriately placed and sufficient quantity of
adaptors and couplings.
EXECUTION:
EXAMINATION AND :pREPARATION
1. The General Contractor shall inspect all equipment and materials against approved
Shop Drawings at time of delivery. Equipment and materials damaged or not meeting
requirements of the approved Shop Drawings shall be immediately returned to the
OSHGS Supplier for replacement or repair.
2. Equipment and materials shall be stored in a dry location and protected from the
elements according to the OSHGS Supplier's instructions.
3. Equipment and materials shall be handled in an approved manner according to the
OSHGS Supplier's instructions.
INSTALLATION
1. Installation of the generator, metering pumps, tanks and appurtenances shall be
performed by the General Contractor and shall be in accordance with the Drawings
and with the OSHGS Supplier's instructions and recommendations. Conflicts of
information shall be called to the attention of the Engineer.
2. All equipment units or assemblies shall be installed on concrete bases and secured
with anchor bolts in accordance with the OSHGS Supplier's recommendations and as
shown. The concrete bases shall.be poured up to I-inch below the metal bases, legs
or soleplates. Equipment legs or base plates shall be accurately shimmed to grade and
the spaces between filled with an approved non-shrink grout. After the grout has
reached its initial set, exposed edges shall be cut back 2 inches and the edges neatly
finished with 1 to 2-cement mortar. Where channel base plates are used, the void
inside the channel shall be filled with non-shrink mortar and the open ends plastered
with 1 to 2-cement mortar. The General Contractor shall coordinate with OSHGS
supplier for skid placement and anchoring.
3. General Contractor shall inspect all concrete pads for proper elevation, dimensions,
cutouts, evenness and anchor bolt locations and correct if necessary.
4. General Contractor shall provide a drain for each piece of equipment, according to
the OSHGS Supplier's instructions.
5. Inst~lation shall include furnishing and applying an initial supply of lubricants, as
provided by the OSHGS Supplier.
6. General Contractor shall support piping independent of equipment. Equipment shall
be free from all loads and stresses induced by the piping.
TS-7-l4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
7. All equipment including motors, belts and drives shall be aligned to the best industrial
standards. Field check and adjust all equipment alignments in the presence of the
Engineer or Engineer's representative.
8. The General Contractor shall inspect all equipment before installation, if damaged;
notify the OSHGS Supplier promptly. Do not install damaged equipment until the
Contractor makes repairs in accordance with OSHGS Supplier's written instruction
and approval.
9. Tie-down lugs for tanks shall be grouted or shimmed to prevent excessive loads being
transferred to the tank shell.
10. Make all electrical connections in conformance with the requirements of the electrical
specifications.
c.
START-UP SERVICES AND TESTING
1. General Contractor and OSHGS Supplier shall verify that structures, equipment,
pumps and motors are compatible for an efficient system.
2. General Contractor and OSHGS Supplier shall make equipment adjustments required
to place system in proper operating condition.
3. General Contractor and OSHGS Supplier shall test the sodium hypochlorite feed
system for proper operation in the presence of the Owner and Engineer.
4. The OSHGS Supplier shall furnish all testing equipment and devices required.
5. If the sodium hypochlorite feed system fails to meet any of the specified performance
requirements, General Contractor and/orOSHGS Supplier shall modify and/or replace
defective equipment until it meets specified requirements. Re-test system to verify
satisfactory operation.
6. Demonstrate the accuracy of each metering pump using job supplied calibration
column.
7. The General Contractor, after installation of storage tanks is complete but before
piping connections are made, block all outlets and fill each tank with water to again
check for leaks. No leakage will be permitted.
8. The OSHGS Supplier's field services - Retain, for a period of not less than Three (3)
days for installation assistance of the generation system factory trained representatives
of the manufacturer of each component with demonstrated ability and experience in
the installation and operation of the equipment. The representative shall performthe
services listed below:
TS-7-15
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
a. Inspect the completed installation and prepare an inspection report.
b. Test, calibrate and adjust all components for optimum performance.
c. Assist in initial start-up and field-testing.
d. Instruct Owner's personnel in the operation and user maintenance of all
components. Conduct a training seminar at the site.
e. Supervise the correction of any defective or faulty work before and after
acceptance by Owner.
9.
Dosing pump manufacturer's field services - Retain, for a period of not less than one
(1) day, factory trained representatives of the dosing pump manufacturer with
demonstrated ability and experience in the installation and operation of the dosers.
The representative shall perform the services listed below:
a. Inspect the completed installation and prepare an inspection report.
b. Test, calibrate and adjust all components for optimum performance.
c. Assist in initial start-up and field-testing.
d. Instruct Owner's personnel in the operation and user maintenance of all
components. Conduct a training seminar at the site.
e. Supervise the correction of any defective or faulty work before and after
acceptance by Owner.
TS-7-16
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-01.
A.
B.
SECTION TS-8
PRE-ASSEMBLED PRECAST CONCRETE STORAGE BUILDING
GENERAL:
SUMMARY
Contractor to furnish precast concrete transportable building. Building to be delivered and
placed on owner's prepared foundation in accordance with manufacture's recommendations
(PART 3). Precast building to be EASI-SET brand Model AES-I012HL as manufactured
by AES PRECAST CO., INC., 3851 17th Street, Northport, AL 35476 or pre-approved
equal. Building to be provided by manufacturer with all necessary openings as specified by
contractor in conformance with manufacturer's structural requirements.
QUALITY ASSURANCE
1. ACI-318-95, "Building Code Requirements for Reinforced Concrete". Concrete
Reinforcing Institute, "Manual of Standard Practice".
2. ANSI!ASCE-7-95 "Building Code Requirements for Minimum Design Loads in
Buildings and Other Structures".
3. 1996 BOCA.
4. UL- 752 Test Method Level Four (4) for Bullet Resistance certified by an Independent
Structural Engineer.
5. Concrete Reinforcing Institute, "Manual of Standard Practice. "
6. Building fabricator must have a minimum of 5-years experience manufacturing and
setting transportable precast concrete buildings.
7. PCI Design Handbook - 5th Edition.
8. Uniform Building Code -1997.
9. Manual of Steel Construction - LRFD AISC - 2nd Edition.
10. Manual of Steel Construction - ASD AISC - 9th Edition.
TS-8-l
I
I
I
I
I
I
I
I
I
I
I
I,
I
I
I
I
I
I
1
C.
-02.
A.
DIMENSIONS & DESIGN LOADS
1. Dimensions:
Exterior: 12' O"W x 10' O"L x 9' 5"H
Interior: 11' 6"W x 9' 5"L x 8' O"H
Walls are 3" or 4" Thick; Floor is 6" Thick; Roof is 4" @ edge and 5" @ center,
giving a 1" slope from center to edge.
2. Design Loads:
a. Seismic load performance category IC', Exposure Group III
b. Standard Live Roof Load - 60 PSF
c. Standard Floor Load - 250 PSF Minimum
d. Standard Wind Loading - 130 MPH
3. Roof: Roof panel shall slope I" from center to sides. The roof shall extend a
minimum of2 Y2" beyond the wall panel on each side.
4. Roof, floor and wall panels must each be produced as single component monolithic
panels. No roof, floor, or vertical wall j oints will be allowed, except at comers. Wall
panels shall set on top of floor panel.
PRODUCTS:
MATERIALS
1. Concrete: Steel-reinforced, polypropylene fiber reinforced, 4000 PSI minimum 28-
day compressive strength, air-entrained (ASTM C260).
2. Reinforcing Steel: ASTM A6l5, grade 60 unless otherwise indicated.
3. Reinforcing Fiber: Polypropylene fiber, Fibermesh @ 1.5 pounds per cubic yard.
4. Caulking: All joints between panels shall be caulked on the exterior and interior
surface of the joints. Caulking shall be SIKAFLEX-lA elastic sealant or equal.
5. Panel Connections: All panels shall be securely welded together with 1/4" thick steel
brackets. Steel is to be of structural quality, hot-rolled carbon complying with ASTM
A283, Grade C. Cast-in anchors used for panel connections to be Dayton-Superior
#F-63, or equal. '
TS-8-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
6. Curb: On interior of building there shall be a continuous curb poured around the
entire perimeter, with various support curbs within. Curbs shall be steel reinforced
and bonded to the floor slab with an epoxy bonding agent. Curbs shall have a
minimum dimension of 6" x 6". Sump area shall be coated with two-part epoxy, and
sloped to center of building.
7. Grating.: Building shall have Fiberglass Grating, Yellow, covering the entire floor
area. Grating shall provide 3 50 PSF minimum loading and shall be slip resistant.
B.
ACCESSORIES
1. Doors and Frames: The building shall be equipped with one (1) pair 3' -0" x 7' -0" x
1 %" Fiberglass Doors and frames.
Door Hardware:
a. Hinges: Vandal Proof (primed with non-removable hinge pins), Stainless
Steel, 3 per door.
b. Lock Set: Stainless Steel Mortise Lock with Removable Core 6 Pin Type.
Panic Hardware shall be provided for one side of door.
c. Threshold: CECO #897 V raised interior, extruded aluminum threshold with
neoprene seal, or equal.
d. Door Stop: Ives 1 15B26D Heavy duty cast bracket and welded chain with
vinyl cover, or equal.
e. Drip Cap: National Guard 15D72.
f Astragal: CECO P444/68R, aluminum, or equal.
g. Deadbolts: Top and Bottom inactive leaf I" x 6-3/4" Stainless Steel Lever
extension flush bolt.
C.
FINISHES
1. Interior of Building: Smooth Steel Form Finish, painted with an epoxy coating
suitable for protection against sodium hypochlorite, color is to be determined by
owner.
2. Exterior of Building: Broom Finish, painted to match existing storage tank.
3. Roof to have smooth trowel finish sealed With Hydrostop Premium Coat membrane
reinforced liquid applied roofing system, White.
4. All colors to be selected by owner.
TS-8-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
D.
E.
F.
G.
-03.
A.
ELECTRICAL
1. Two (2) 150W VaporproofIncandescent Light Fixtures.
2. One (1) SPST Switch.
3. One (1) wall mounted electrical outlet (to located by owner).
4. One (1) thermostat for control or both exhaust fan and heater.
5. One (1) 125A 3-Phase Main Lug Interior Service Panel.
VENTILATION
1. One (1) 12" Corrosion Resistant Shutter Mount Exhaust Fan.
2. Two (2) 12" x 12" Vent Openings with Rain Hoods.
HEATING
1. One (1) 5KW Electric Unit Heater.
MISCELLANEOUS
1. One (1) Concrete Loading Ramp.
2. All conduit shall be RMC (Rigid Metallic Conduit), Surface Mount.
EXECUTION:
SITE PREPARATION (Standard Pre-assembled Building)
1. AES Precast Building shall bear fully on a crushed stone base that is at least one foot
larger than the length and width of building.
2. Stone shall be a minimum of 4" thick or down to firm sub grade. Substrate below
stone must have a vertical soil capacity of 1,500 pounds per square foot. Stone shall
be 3/8" or smaller and placed within a perimeter form with flat and level top edge for
screeding, such as concrete curbing, railroad ties, or compacted earth.
3. Stone must be screeded to level within 1/4" in both directions. Forming material shall
remain around stone after the building is set.
4. The crushed stone base shall be kept within the confines of the soil or perimeter form.
TS-8-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
B.
ACCESS
1. Purchaser must provide level unobstructed area large enough for crane and tractor
trailer to park adjacent to pad. Crane must be able to place outriggers within 3'_0" of
edge of pad and truck and crane must be able to get side-by-side under their own
power. No overhead lines may be within 75' radius of center of pad. Firm roadbed
with turns that allow 65' lowbedtractor and trailer must be provided directly to site.
No building shall be placed closer than 2'-0" to an existing structure.
TS-8-5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-9
ELECTRICAL
-01.
SCOPE:
The work covered by this section of the specifications consists in furnishing all plant,
labor, equipment, appliances, and materials in performing all operations in connection with the
installation of the electrical system for the project, complete, in strict accordance with this section of
the specifications and the applicable drawings, and subject to the terms and conditions of the contract.
-02.
CODES. PERMITS. AND INSPECTIONS:
The Contractor shall obtain, at his own expense, all necessary permits required for the
proper execution of the work covered by this section of the specifications. Further, he shall comply
with the regulations of the National Electrical Code, and shall deliver to the Owner, without charge,
all certificates of inspection issued by inspecting authorities.
-03.
MATERIALS AND WORKMANSHIP:
All materials shall be new and shall conform with the standards of Underwriter's
Laboratories, Inc., in every case where such a standard has been established for the particular type
of material in question. All work shall be executed in a workmanlike manner and shall present a neat
and mechanical appearance when completed.
-04.
MATERIAL AND EQUIPMENT SCHEDULES:
The Contractor shall submit to the Engineer a complete list of materials, fixtures and
equipment to be incorporated in the work. The list shall include catalog numbers, cuts, diagrams,
dra~ings and other descriptive data as may be required by the Engineer. In order to standardize, all
material shall be Square D or equal except as may be specified on the drawings.
. -05. ELECTRICAL SERVICE AND METERING:
1. SERVICE: Service voltage for the various elements of the installations shall be as scheduled
on the plans.
2. METERING: It shall be the responsibility of the Contractor to coordinate the metering
requirements with the local utility to assure that meter sockets are located properly for the
various service laterals.
-06.
EOUIPMENT ENCLOSURES:
Unless specifically specified otherwise, equipment enclosures shall be NEMA
Type 3R.
-07.
WIRING METHODS:
TS-9-l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Generally, and unless otherwise specified on drawings, wiring shall consist of insulated
conductors installed in rigid zinc-coated conduit and direct burial type UP/G wiring.
1. CONDUIT SYSTEM: Conduit shall be threaded, rigid zinc-coated steel or PVC, where
allowed by codes and regulations. All conduit shall be installed in accordance with the
National Electrical Code. Crushed or deformed raceway shall not be installed. Equipment
connections shall be made with flexible conduit with liquid tight covering and connectors.
Rigid metal conduit buried underground shall be coated with asphaltic paint.
2. CONDUCTORS: Conductors shall be copper and sizes shall not be less than those shown
on the drawings. Branch circuit conductors shall not be smaller than No. 12 AWG. All
interior wiring shall have a code grade insulation type THW. Direct burial cable shall be type
UP/G.
-08.
OUTLETS AND DEVICES:
Outlet boxes of a type to suit the intended use shall be installed at the locations shown
on the drawings. Wall switches shall be mounted within reach of the access hatch and receptacles
18 inches above the floor.
1. Where required, wiring troughs shall be constructed of code-gauge galvanized sheet metal
with screw fastened covers and shall be sized as shown on the drawings.
2. Device plates of the one-piece type shall be provided for all outlets to suit the device installed.
Plates on unfinished walls or on fittings shall be of zinc-coated sheet metal having rounded
or beveled edges.
3. RECEPTACLES: All duplex convenience receptacles located on dry areas shall be
specification grade, rated 20 amperes, 125 volts, AH&H 1991, or approved equal.
-09.
LIGHTING FIXTURES:
Lighting fixtures oftypes and sizes as indicated on the drawings shall be furnished and
installed complete with lamps.
-10.
MOTOR STARTERS:
Unless otherwise specified, all motor starters shall be furnished with the equipment
and installed under this section of the specifications. Enclosures shall be raintight unless otherwise
noted on the plans. Selector switches and pilot lights shall be provided in the covers as indicated on
the plans. Unless otherwise noted, operating coils shall be 120 volts, Square D Company, Class 8536
and 8538.
1. VERIFICATION OF MOTOR SIZE: The plans indicate the anticipated horsepower of all
motors. This information is furnished as a guide and it shall be the responsibility of the
Contractor to verify the horsepower of equipment being furnished.
TS-9-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-11.
CONTROL EQUIPMENT:
Unless otherwise installed as part of an equipment package, all accessory items for the
control of motors shall be furnished and installed under this Section of the Specifications.
Conduit and control wiring between control panels and motor starters shall be
furnished and installed as required for a complete and operating system.
-12.
GROUNDING:
The neutral conductor and equipment grounding shall be in accordance with the
applicable sections of the National Electrical Code:
-13.
TESTS:
After the entire electrical system is completed, and at such time as the Engineer may
direct, the Contractor shall conduct an operating test for approval. The tests shall be performed in
the presence of the Engineer or his authorized representative, and the equipment shall be
demonstrated to perform in accordance with the requirements of these specifications. The Contractor
shall furnish all equipment and personnel required for the tests.
-14.
GUARANTEE:
The Contractor shall leave the entire electrical system installed under this contract in
proper working order and shall, without additional charge, replace any work or material which
develops defects, except from ordinary wear and tear, within one year from the date of final
acceptance by the Owner.
TS-9-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-IO
CONCRETE CONSTRUCTION
-01.
SCOPE:
This section covers concrete construction, complete, including reinforcement thereof
-02.
FORMS:
Forms shall be ofwood, metal, structural hardboard or other suitable material that will
produce the required surface finish. Forms placed for successive pours for continuous surfaces shall
be fitted to accurate alignment to assure a smooth completed surface free from irregularities, and shall
be sufficiently tightto prevent the loss of mortar. No forms shall be left permanently in place without
approval of the Engineer. Holes resulting from removal of form ties shall be filled solid within 12
hours after removal of forms with cement mortar.
-03.
REINFORCING AND EMBEDDED METALS:
Bar reinforcement shall be intermediate grade new billet steel conforming to the
requirements of the ASTM Designation A15. All bars % inch and larger shall be deformed bars
conforming to ASTM Designation A305. Detailing, fabrication and tagging of reinforcement shall
be done in accordance with ACI "Manual of Standard Practice for Detailing Reinforced Concrete
Structures" (ACI 315), except that where longer laps are indicated on the design drawings, the
drawings shall govern. Wire fabric reinforcement shall consist of steel wire conforming to the
requirements of ASTM Designation A185. Anchor bolts and structural shapes shall conform to
ASTM Designation A36. Exposed surfaces of embedded steel shall be given one shop coat of Red
Lead Iron Oxide conforming for Federal Specification TT -P-86c, Type II, unless otherwise noted on
the drawings. Anchor bolts and miscellaneous steel items to be embedded in concrete shall be
accurately placed in accordance with the drawings, and adequately secured in position to prevent
dislodgement during concrete placing operations. Anchor bolts shall be protected after concrete has
been placed and set by daubing with grease, wrapping with burlap, and covering bolts with wooden
boxes.
-04.
CONCRETE:
All concrete shall be equivalent to ready mix concrete manufactured and delivered in
accordance with the requirements of ASTM Designation C94 and having a compressive strength at
28 days of 3,000 psi, except as noted herein. The concrete manufacturer shall assume the
responsibility of the design ofthe concrete mix in accordance with Alternate No.2 of ASTM C94.
Air entrained concrete shall be used for all concrete.
TS-lO-l
Slabs on grade
Footings
All others
Max. 4", Min. 3"
Max. 5", Min. 3"
Max. 6", Min. 3"
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1. MATERIALS:
A. Cement: Cement shall be Type I or IA "Portland" cement, all one manufacturer,
conforming to ASTM, C150 or ASTM C175, respectively.
B. Aggregates: Aggregates shall conform to ASTM C33. Coarse aggregate shall be
crushed rock or gravel and graded from % inch to number 4 sieve for mass or
foundation concrete. Fine aggregate shall be natural sand.
C. Water: Mixing water shall be proportioned so that slump when measured with
standard slump cone does not exceed the following:
D. Joint Filler Strips: Premolded joint filler strips shall be resilient compressive,
bituminous and fiber materials saturated with at least 35 percent and not over 50
percent by weight of asphalt. Poured type j oint composition for expansion joints shall
be elastic compound made up of asphalt and colloidal mineral fillers.
2. PLACING CONCRETE: Runways for wheeled equipment shall be provided to convey
concrete. Runways shall not be supported on the reinforcement. Concrete shall be placed
and compacted in layers not over 24 inches deep. Vibrators may be used provided they are
used under experienced supervision and the mixture is dry enough to prevent segregation.
Form vibrators shall not be used. Vibration shall not be used for transporting or moving
concrete inside forms. No more concrete shall be placed than can be consolidated and
finished the same day as placed. Free fall of concrete shall be limited so that no segregation
of materials occurs.
3. JOINTS: Construction joints not indicated on drawings shall be approved by the Engineer
in advance of pour. Joints in foundation walls shall be keyed. Before depositing the concrete
is resumed, the hardened surface shall be roughened, cleaned of foreign matter and thoroughly
wetted but not saturated. The cleaned and wetted surfaces shall be slushed with a coating of
neat cement grout against which the new concrete shall be placed before the grout has
attained its set.
4. FINISHING: After stripping forms, all voids and honeycombs shall be patched by chipping
and scarifying the defective areas and treating it with an approved bonding agent. All such
voids shall be patched, not merely plastered. Grout mixture shall consist of one part Portland
cement and one part sand. Immediately following removal of forms, all fins and irregular
projections shall be removed from all surfaces except from those which are not to be exposed
or waterproofed. Slabs shall be struck-off and consolidated by approved machine or hand
methods, screeding and tamping concrete so that upon completion, the surface shall be true
to grade as shown on drawings and free of surface voids. All floors shall have a monolithic
steel trowel finish unless otherwise indicated on the drawings. Exterior walls shall be
compacted, screeded and floated to a true even surface with wood floats and then broomed.e
TS-lO-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-ll
GRADED AGGREGATE BASE COURSE
-01. SCOPE:
This section covers a graded aggregate base course to receive bituminous paving under
another section, complete.
-02. GENERAL SPECIFICATIONS:
The graded aggregate base course shall conform to all applicable specifications of Section 300
of the Standard Specifications for Roads and Bridges of the Georgia State Department of
Transportation, Latest Edition.
-03. PREPARATION OF SUBGRADE:
The sub grade to receive the graded aggregate base course shall be constructed in accordance
with requirements of Section 209 of the Standard Specifications for Roads and Bridges of the
Georgia State Department of Transportation.
-04. MATERIALS & CONSTRUCTION FOR SURFACE COURSE:
Materials and construction for the graded aggregate base course shall be in accordance with
Section 310 of the Standard Specifications for Roads and Bridges of the Georgia State Department
of Transportation.
TS-ll-l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-12
BITUMINOUS PAVING
-01. GENERAL:
A. This section covers the construction of pavement for all roads and parking areas, complete.
B. Construction of the subgrade, base course and paving of the roadways and parking areas shall
be undertaken immediately after completion of all storm drain lines and structures, all curbs
and gutters, all yard piping, conduits and other facilities passing beneath paved areas, and all
structural slabs and foundations required within or adjacent to the paved areas.
-02. PRODUCTS:
A. The asphalt concrete mixture shall conform to the Georgia Department of Transportation,
Standard Specifications for Highway Construction, for Type E asphalt concrete. The job mix
shall be approved by the Engineer and no material shall be used until approved.
B. Lane Marking Paint: Alkyd-Resin type, ready mixed complying with AASHTO M248,
Type I.
-03. EXECUTION:
A. SEASONAL LIMITATIONS
No bituminous mixtures shall be applied for surface treatment between October 21 st and April
10th, except as directed by the Engineer.
B. WEATHER LIMITATIONS
Bituminous mixtures shall not be produced or placed during rainy weather, when the sub grade
or base course is frozen or shows any evidence of excess moisture nor when the moisture on
the surface to be paved would prevent proper bond nor when the air temperature is less then
45 degrees F. in the shade away from artificial heat.
C. APPLICABLE SPECIFICATIONS
All work and materials required under this section of the specifications shall conform to the
applicable sections of the Standard Specifications of the Georgia Department of
Transportation, latest edition.
D. SUB GRADE
The sub grade shall be prepared as specified under Section TS-ll of these specifications.
TS-12-l
TS-12-2
E.
PRIME COAT
A prime coat of 0.3 to 0.8 gallons per square yard of medium curing cut-back asphalt (RC-
250 or emulsion grades RS-2 or SS-l) shall be applied with a pressure distributor at a
temperature between 80 degrees F. and 140 degrees F. The prime coat shall be applied to
the previously prepared base course when the atmospheric temperature is above 50 degrees F.
F.
SURFACE COURSE
1. The mixture shall be transported from the mixing plant to the point of use in approved
vehicles. Loads shall not be of such size or weight as to interfere with the efficient
operation of the spreader. Loads shall not be sent out so late in the day as to prevent
the completion of spreading and compaction of the mixture during daylight, unless
artificial light is provided. The mixture shall be delivered at a temperature between
225 degrees F. and 325 degrees F. and within 20 degrees F. of the temperature set at
the mixing plant.
2. Upon arrival at the point of dumping, the mixture shall be dumped into the hopper and
spread by mechanical pavers, true to line, grade and cross section specified and to the
loose depth that will secure a compacted thickness of2 inches. The hot mixture shall
be free from lumps and shall be spread while it is in a workable condition.
After the mixture has been screeded and before roller compaction is started, the
surface shall be checked, all fat spots and irregular areas removed and replaced with
satisfactory material. All irregularities in alignment and grade along the outside edge
shall also be corrected by the addition of removal of mixture before the edge is rolled.
3 . While the mixture is hot, it shall be compacted thoroughly and uniformly by rolling.
The surface of the compacted mixture shall be smooth, and true to crown and grade.
Any mixture that becomes loose or broker, mixed with dirt or is in any way defective,
shall be removed and replaced with fresh hot mixture which shall be immediately
compacted to conform to the surrounding area. Any area showing an excess of
bituminous materials shall be removed and replaced, and the edges shall be kept to a
reasonable straight line and trimmed.
4. The density after compaction shall be at least 98 percent of the laboratory-determined
density.
5. Protection of Pavement: The newly finished pavement shall be protected from
vehicular traffic of any kind until the pavement has cooled and hardened and in no
case less than 6 hours.
6. Tolerances: The finished surface shall not vary more than 1/8 inch in 10 feet from the
true profile and cross section.
SECTION TS-13
MEASUREMENT AND PAYMENT
-01.
SCOPE:
This section describes the methods for measurement and payment of all contract bid
items.
-02.
MEASUREMENT AND PAYMENT:
The following item numbers correspond to the contract bid items in the proposal
section of this document.
Item 1 - Precast concrete building shall be measured individually (each) and shall include the
cost for grading, graded aggregate base, building completed with accessories and finishes as
specified, precast concrete ramp, and installation. No additional payment shall be made for
these items.
Item 2 - Clor- Tee on-site Sodium Hypochlorite Generation System shall be measured lump
sum and shall include the cost for the Clor- Tee Generation System as specified which shall
include at a minimum a dual tank water softener, brine tank, brine proportion system,
electrolyzer cell panel, power supply, required metering pumps and sodium hypochlorite
storage tank. No additional payment shall be made for these iterns.
Item 3 - Electrical service and system wiring shall be measured lump sum and shall include
costs for the required electrical service and all system wiring installed complete including
all required conduit and tie-ins. No additional payment shall be made for these items.
Item 4 - System piping shall be measured lump sum and shall include all piping inside of
building installed complete, pressure and leakage testing, pipe sterilization, bacteriological
testing and flushing. No additional payment shall be made for these items.
Item 5 - 1" copper water service shall be measured individually (each) and shall include costs
for piping from main to building, valve with valve box, dewatering, trench excavation, water
main connection, normal backfill and property restoration. No additional payment shall be
made for these items.
Item 6 - 3/4" PVC sodium hypochlorite injection line shall be measured individually (each)
and shall include costs for piping from building to main, valve with valve box, water main
connection, trench excavation, dewatering, installation, normal backfill and property
restoration. No additional payment shall be made for these items.
Item 7 - 3" diameter PV C drain pipe shall be measured lump sum and shall include costs for
pipe and installation, trench excavation, trench box, dewatering, asphalt cutting, normal
joints and gaskets, normal backfill, 4" floor drain, and tie to existing storm drop inlet. No
additional payment shall be made for these items.
Item 8 - Concrete sidewalk shall be measure in square feet and shall include cost for 3000
psi concrete, installation, site preparation, form work, and finishing. Payment shall include
all removal and disposal costs. No additional payment shall be made for these items.
TS-13-1
Item 14 _ Lump sum construction includes, but is not limited to, the items described in the
Bid Schedule. No separate payment shall be made for these items.
Item 9 _ Graded aggregate base and asphalt paving shall be measured in square yards and
shall include costs for asphalt, aggregate base, installation, and site preparation. No
additional payment shall be made for these items.
Item 10 - Construction outlet shall be measured individually (each) and shall include costs
for materials, installation, cleaning, and removal and disposal. No additional payment shall
be made for these items.
Item 11 - Inlet sediment traps shall be measured individually (each) and shall include costs
for materials, installation, cleaning, and removal and disposal of collected material. No
additional payment shall be made for these items.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Item 12 - Pipe bollards shall be measured individually (each) and shall include costs for
materials and installation. No additional payment shall be made for these items.
Item 13 - Chain link double gate, installed complete shall be measured individual (each) and
shall include the cost for all labor, materials and equipment necessary for a complete
installation. No additional payment shall be made for these items.
TS-13-2
(NOTE:
.- ~
i_
" SECTION PB
PERFORMANCE BOND
Bond # 0000708
THIs BOND IS ISSUED SIMULTANEOUSLY WITH.PAYMENT BOND ON
PAGE PB-3, IN FAVOR OF THE OWNER CONDITIONED .FOR THE
PAY:MENT OF LABOR AND :MATERIAL.)
KNOW ALL:MEN BY THESE PRESENTS:
BRW Construction Group, LLC
That
as Principal,
hereinafter called Contractor, and
Companion Property & Casualty Insurance Company
Georgia
a corporation organized and existing under the laws of the State of
witi} its principal office in the City of Columbia
, State of
South Carolina
.as
Surety, hereinafter called Surety, are held and finnly bound unto AUGUSTA, GEORGIA BY
AND IHROUGH TIffi AUGUSTA-RICHMOND COUNTY COMMISSION as Obligee,
hereinafter 'called the Owner, in the penal mnount of ***SEE BELOW Dollars
($ 164,434.00 ) for the payment whereof Contractor and Surety bind themselves, their heirs,
e1::ecutors, administrators, successors, and assigns, jointly aod. severally, firmly by these presents h'rty ~
.. . . d d . ty f r thousancffour hundred t I ,our
for tbe faithful performance of a certam wntten agreement. ***One hun re SIX ou
WHEREAS, Contractor has by said written agreement dated 6/21/05
entered into a contract with Owner for the construction of AUGUSTA WATER SYSTEM
lMI1l0VEMENTS, CHLORINE BOOSTER STATION, BOND PROJECT NO. 10110,
Augusta. Georgia, in accordance with the drawings and specifications issued by the Augusta
UtiJities Department and tbe Augusta-Richmond County Commission, which contJ;act is by
reference made a part hereof, and is hereinafter referred to as the CONTRACT.
NOW, THEREFORE, the condition of this obligation is such that> if Contractor
shan promptl,y and faithfully perfonn said CONTRACT, then this obligation shalt be null and void;
otherwise it shall remain in full force and effect.
Owner.
The Surety hereby waives notice of any alteration or extension. of time m.ade by the
Whenever Contractor shall be, and declared by. Owner to be in default under the
CONTRACT, the Owner having performed Owner's' obligations thereunder, the Surety m.ay
prom~Jy remedy the default, or shall promptly
(1)
(2)
Complete the CONTRACT in accordance with its terms and conditions or
. ,
Obtam. a bid or bids for Completing the Contract in accordance with ita terms and
conditions, and upon determination by Surety of the lowest responsible bidder or
if the Owner elects, Upon determination by the Owner and the Surety jointly o';t.h.~
lowest responsihle bidder, armnge fur a contract hetween such hidder and Owner,
and make available as Work progresses (even though there should be a default or a
8UC~5ion of defaults under 'the contract or contra.cts of completion arranged.
PB-l
under this paragraph) sufficient funds to pay the cost of completion less the
balance of the contract price; but not exceeding, including other costs and damages
for which the Surety may be liable hereunder, the amount set forth in the first
paragraph hereof The term. "balance of the contract price, II as used in this
paragraph, shall mean the total amount payable by Owner to Contractor under.the
Contract and any amendments thereto, less the amount properly paid by Owner to
Contractor.
Any sui.t under this bond nnist be instituted before the expiration of two (2) years
~ .$e. date on which final payment under th.e CONTRACT falJ.s due.
No right of action shall accrue o.n this bond to or for the use of any person or
~oo Qther than the Owner named herein or the heirs, executors, administrators or
~.oftbeOwner.
Signed and sealed this
6th
day of
July
AD.20~.
:~~.(Y~~.IU J1.~{?hJ
A~.:.._
BRW Construction Group, LLC
(Contractor)
BY@~ ~ (seW)
:eh /'t)U.)-r (Title)
(Seal)
~~ft?-rr;e()~
~jJO/tJp~/(aJJ
Companion Property & Casualty Insurance Company
(Seal)
(Surety)
By 1t~;J~L L--zseal)
, . (Title)
Richard L. Shanahan, AttbrneY-In-Fact
PB-2
....-.-1"1I
SECTION PJl
LABOR ANDMA TERIAL Ii A YMENT BOND
Bond # 0000708
(NOIB:
TIiIS BOND IS ISSUED SIMULTANEOUSLY WIlli PERFORMANCE
BOND ON PAGE PB-I, IN FAVOR OF THE OWNER CONDITIONED FOR
THE PERFORMANCE OF THE WORK.)
KNOW ALL :MEN BY THESE PRESENTS:
That
BRW Construction Group, LLC
as Principal,
.::~ cafied. Contractor, and
~.~{;~~;~.~~~~.~.~~:~~~/ :~.. .:
:r;:;f~i~ organized and existing under the laws of the State of
~~t.\t..,,:.;..,!, :<::: . .
i':: i:W~aI office in the City of Columbia . State of
~~f::.:'.. ::. '
; I,:~ "; '.: ;.;::
Companion Property & Casualty Insurance Company
Georgia
South Carolina
, as
called Surety, are held and finnly bound. unto AUGUSTA, GEORGIA BY
, THE AUGUSTA-RICHMOND COUNTY COMMISSION, as Obligee,
.~ the Owner for the use and benefit of claimants as hereinbelow . defined in . the
.....,.:,.. .' .
)<:.one hundred sixty four thousand four hundred thirty four
Dollars ($ 164,434.00 ) for the payment
'. r and Surety bind themselves, their heirs, eJl:ecutors, administrators, successors,
." .:~tlJtIy and severally, firmly by these presents.
"WHEREAS, Contractor has by written agreement dated 6/21/05
'~:H".:~ contract with Owner for the construction of AUGUSTA WATER SYSTEM
'. ITS, CHLORINE BOOSTER STATION, BOND PROJECT NO. 10110, in
drawings and specifications issued by the Augusta Utilities Department. and
. County Commissio.n, which contract is by reference made a part hereof, and is
>1i&ued to as the CONTRACT.
w . NOW, THEREFORE, the condition of this obligation is such that, if the
-";-::SWlpromptly make payment to all claimants as hereinafter defined, for all labor . and
. .' m: reasonably required to use in the performance of the CONTRACT, then this
.::~ be void; otherwise it shall remain in full force aDd effect, subject, however, to the
..~.tions:
~$~) A claimant is defined as one having it direct contract with tbe Contractor or with a
subcontractor of the Contractor for labor, material, or both, used or reasonably
required for use in the performance of the contract, labor and material being
construed as to include that part of water, gas, power, light., heat, oil, gasoline,
telephone service or rental of equipment directly applicable to the CONtRACT.
(2) The above named Contractor and Surety hereby jointly and severally agree with
the Owner that every claimant as herein defined, who has not been paid in full
before the expiration of a period of ninety (90) days after the date OD. which the
PB-3
last of such claimant's work or labor was done or performed) or materials were.
furnished by such claimant, may sue on this bond for the use of such claimant,
prosecute the suit to final judgement for such sum or sums as may be justly due
claimant, and have execution thereon. The Owner shall not be liable for the
payment of any costs or expenses of any such suit.
(3) No suit or action shall be commenced hereunder by any claimant,
(a) Unless claimant, other than one having a direct contract with the
Contractor, shall have given written notice to any two of the following:
The Contractor, the Owner, or the Surety above named, within. ninety (90)
days after such claimant did or performed the last of the work or labor, or
furnished the last of the materials for which said claim is made, stating with
substantial accuracy the amount claimed and the name of the party to
''-'nom tbe materi.a1s were furnished, or for whom the work or labor was
done or performed. Such notice shall be served by mailing the same by
registered mail or certified mail, postage prepaid, in an envelope addressed
to the Contractor, Owner or Surety, at any place where an office regularly
maintained for the transaction of businessl or served in any manner in
wbich legal process may be served in the state in which the aforesaid
project is located, save that such service need not be made by a public
officer.
'tb) After the expiration of one (I) year following the date on which Contractor
ceased work on said CONTRACT, it being understood, however, that if
any limitation' embodied in this bond is prohibited by any law controlling
the construction .hereof: such limitation shall be deemed to be amended so
as to be equal to the minimum period oflimitationpennitted by such law.
t.e) Other than in a state court of competent jurisdiction in and for the county
or other political subdivision of the state in which the project, or any part
thereof, is situated, or in the United States District Court for the district in
which the project, or any part thereof, is situated, and not elsewhere.
~,
~"-..:
The amount of this bond sball be reduced by and to tbe extent of any payment or
payments made in good faith hereunder, inclusive of the payment by Surety of
.mechanics' liens which may be filed of record against said improvement, whether
or not claim for the amount of such lien be presented under and against this bond.
PB-4
Signed and sealed this
6th
day of
July
AD. 20~.
.n.,.,.~ ~ M '\
,;:'~'1~.;<~ . ~
BRW Construction Group, LLC
(Contractor)
(Seal)
..~.,-~,.."....
" .... .,- J>" ..' .~.
~~~~'~'.j~~,:~~.\:~.. ~~i:~:~ ....
B@e~(Seal)
Pr~~,ow-r (Title)
"""'~llf~
.'~",:~,";. ..
:1::,,~:f~/<. '/ . ,
..~ ._....~, ,J' ..1. .~. . " .
~"(ffi .4J ~ /OJ[
~~~;:H(':::'.:,,':', 0 :/l,
Companion Property & Casualty Insurance Company
(Seal)
(Surety)
BY~~~
I (Title)
Richard L. Shanahan, Attorney-in-Fact
PR_ t;
, .
COMPANION PROPERTY & CASUAL TV INSURANCE COMPANY
P. O. Box 100165 (29202)
51 Clemson Road
Columbia, SC 29229
GENERAL POWER OF ATTORNEY
Know all men by these Presents, that the COMPANION PROPERTY & CASUALTY INSURANCE COMPANY had
made, Constituted and appointed, and by these presents does make, Constitute and appoint Andrew C. Heaner of
Atlanta, Georgia; Richard L. Shanahan of Atlanta, Georgia; Scott Stoltzner of Birmingham, Alabama; Arthur S.
Johnson of Atlanta, Georgia; Lenora N. Cape of Gainesville, Georgia; Mary F. Holland of Chamblee, Georgia;
James E. Feldner of West Lake, Ohio; Jeffrey L. Booth of Parma, Ohio; or Donald H. Gibbs of Atlanta, Georgia,
EACH as its true and lawful attorney for it and its name, place and stead to execute on behalf of the said company,
as surety, bonds, undertakings and contracts of suretyship to be given to all obliges provided that no bond or
undertaking or contract of suretyship executed under this authority shall exceed in amount of the sum of $1,000,000
(One Million dollars).
This Power of Attorney is granted and is signed and sealed by facsimile under and by the authority of the following
Resolution adopted pursuant to due authorization by the Executive Committee of the Board of Directors of the
COMPANION PROPERTY & CASUALTY INSURANCE COMPANY on the 2ih day of August 2004.
RESOLVED, that the Chairman, President or any Vice President of the Company be, and that each or any of them
hereby is, authorized to execute Powers of Attorney qualifying the attorney named in the given Power of Attorney to
execute in behalf of the COMPANION PROPERTY & CASUALTY INSURANCE COMPANY bonds, undertakings
and all contracts of suretyship; and that any Secretary or any Assistant Secretary be, and that each or any of them
hereby is, authorized to attest the execution of any such Power of Attorney, and to attach thereto the seal of the
Company.
FURTHER RESOLVED, that the signature of such officers and the seal of the Company may be affixed to any such
Power of Attorney or to any certificate relating thereto by facsimile, and any such Power of Attorney of certificate
bearing such facsimile signatures or facsimile seal shall be valid and binding upon the Company when so affixed
and in the futiJre, with respect to any bond undertaking or contract of suretyship to which it is attached.
In Witness Whereof, the COMPANION PROPERTY & CASUALTY INSURANCE COMPANY has caused its official
seal to be hereto affixed, and these presents to be signed by its President and attested by its Vice President this
2ih day of August 2004.
Attest: CO~~ANIOf\lPR9PERTY ~~AL TY INSURANCE CO~ANy /)~
By: L~--D- (~If ,. ~ ~r. 1
Charles M. Potok, President Curtis C. Stewart, Vice President & CFO
STATE OF SOUTH CAROLINA
COUNTY OF RICHLAND
On this q I-l day of S~\eV"'\b~ , '2.Lwy ,before me personally came the above named officers t(UD~k~6wn,
who being by me duly swor , did depose and say that he resides in Columbia, in the County of Rich/and ,$fateof,.s.C),'at
Columbia; that he is the President of COMPANION PROPERTY & CASUALTY INSURANCE COMPAf:'JY~:the corpciration.
described in and which executed the above instrument; that he knows the seal of the said corporation; that;" .the ,seal affix~d.tp.;:
the said instrument is such corporate seal; that it was so affixed and that he signed his name th~re~o pursuant tcdue.
authorization. _ >.,. '
(,fi.. 'lv. ~L Notary Public, State of SC, Qualified in Richland County Commission Expires: 7f1~h4'" '
~TATE OF SOUTH CAROLINA '. .. "; "
COUNTY OF RICH LAND ;",
I, the undersigned, an Officer of COMPANION PROPERTY & CASUALTY INSURANCE COMPANY, a South Carolina
Corporation, DO HEREBY CERTIFY that the foregoing and attached Power of Attorney remains in full force and has not been
revoked; and, furthermore, that the Resolution of the Executive Committee of the Board of Directors set forth in the Power of
Attorney is now in force. .~ ' _
Signed and sealed at the City of Columb;a, Daled lh~day of 0\ ~ '. 2eJD~ .
Attached to Bond II 0000708 issued in U/~ t:/. E.:~c/z:.~;;I-
Number 1105 5 counterparts. Curtis C. Stewart, Vice President & CFO