HomeMy WebLinkAbout2016-01-12-Meeting Minutes
Engineering Services Committee Meeting Commission Chamber - 1/12/2016
ATTENDANCE:
Present: Hons. Fennoy, Chairman; Hasan, Vice Chairman; Smith and
Guilfoyle, members.
Absent: Hon. Hardie Davis, Jr., Mayor.
ENGINEERING SERVICES
1. Consider approving an Easement Deed to Atlanta Gas Light for a Gas Regulator
Station.
Item
Action:
Approved
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Approve
Motion to
approve.
Motion Passes
4-0.
Commissioner
Ben Hasan
Commissioner
William Fennoy Passes
2. Approve award of Construction Contract to Blair Construction in the amount of
$5,938,494.60 for Belair Road Improvement Project as requested by AED.
Award is contingent upon receipt of signed contracts and proper bonds as
requested by AED. (Bid Item 15-196)
Item
Action:
Approved
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Approve
Motion to
approve.
Motion Passes
4-0.
Commissioner Ben
Hasan
Commissioner
Grady Smith Passes
3. Approve entering into an agreement with Georgia Power, stating that Augusta,
GA will pay for the Transmission Facility Relocation Costs on the Druid
Park Road Improvements Project in accordance with the estimate totaling
$849,328.00. Also, approve the Utility Relocation Agreement to be executed
Item
Action:
Approved
by the Augusta, GA Legal Counsel and the Mayor, and approve payment upon
completion of the work as requested by AED
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Approve
Motion to
approve.
Motion Passes
4-0.
Commissioner Ben
Hasan
Commissioner
Grady Smith Passes
4. Notification of emergency water main relocation at First Presbyterian Church by
Blair Construction, Inc. in the amount of $90,477.40.
Item
Action:
Approved
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Approve
Motion to
approve.
Motion Passes
4-0.
Commissioner
Ben Hasan
Commissioner
William Fennoy Passes
5. Authorize Augusta’s participation in the Georgia Power Distributed Generation
(solar energy) program, paying the $25 per KW capacity reservation and
authorizing Augusta to execute all documents required under the program.
Item
Action:
Approved
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Approve
Motion to approve
receiving this item as
information. Mr.
Fennoy votes No.
Motion Passes 3-1.
Commissioner
Grady Smith
Commissioner
Wayne
Guilfoyle
Passes
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Motion to approve tasking
the Administrator to assign
the appropriate staff within
Approve
the government with
reviewing opportunities to
generate revenue through
the use of future solar
power projects and bring
back a recommendation.
Mr. Guilfoyle and Mr.
Smith vote No.
Motion Fails 2-2.
Commissioner
Ben Hasan
Commissioner
William
Fennoy
Fails
6. Approve entering into an agreement with Georgia Power for relocation of
distribution facilities associated with the Mark Church Road Improvements
Project; approve the Utility Relocation Agreement to be executed by the
Augusta, GA Legal Counsel and the Mayor, and approve payment upon
completion of the work.
Item
Action:
Approved
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Approve
Motion to
approve.
Motion Passes
4-0.
Commissioner Ben
Hasan
Commissioner
Grady Smith Passes
7. Motion to approve the minutes of the Engineering Services Committee held on
December 8, 2015.
Item
Action:
Approved
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Approve
Motion to
approve.
Motion Passes
4-0.
Commissioner
Ben Hasan
Commissioner
William Fennoy Passes
8. Approve entering into an agreement with Georgia Power for relocation of
distribution facilities associated with the Windsor Spring Road Phase V
Improvements Project; approve the Utility Relocation Agreement to be executed
by the Augusta, GA Legal Counsel and the Mayor, and approve payment upon
completion of the work as requested by AED.
Item
Action:
Approved
Motions
www.augustaga.gov
Motion
Type Motion Text Made By Seconded By Motion
Result
Approve
Motion to
approve.
Motion Passes
4-0.
Commissioner Ben
Hasan
Commissioner
Grady Smith Passes
Engineering Services Committee Meeting
1/12/2016 1:05 PM
Attendance 1/12/16
Department:
Presenter:
Caption:
Background:
Analysis:
Financial Impact:
Alternatives:
Recommendation:
Funds are Available
in the Following
Accounts:
REVIEWED AND APPROVED BY:
EASEMENT DEED FOR GAS REGULATOR STATION
PARCEL IDENTIFICATION NUIUBER: 1 57-0-01 8-06-0 ADDRESS: 17 25 TObACCO ROAd
TH1SlNDENTUREmadeandenteredintothis-dayof-2015,betwettn
Augusta, Georgia, a political subdivision under the laws of Georgia, hereinafter refened to ls
AUGUSTA, and ATLANTA GAS LIGHT, hereinafter referred to as AGL;
WITNESSETH, that AUGUSTA, for and in consideration of thc sum of ONE DOLL/)'R
($1.00) in hand and truly paid by AGL at and before the sealing and dclivery of these presen':s,
ind other valuable coniideration, thc receipt whereof is hereby acknowledged, has grantlid,
brrgained, sold, conveyed and confirmed, and by these presents does grant, bargain, s,itll,
coniey and confirm unio AGL, its successors and assigns, an easement over a strip of larrd
containing 375 Square Feet, as rhown on EXHIBIT "A", prepared by Phoenix Consultittg
Scryice, lnc., dated Apnl 27,2015, attached hereto and made a part hereof, and to whifi
rcference is made for a more accurate and complete description of the metes, bounds a ld
courses.
This easement is in addition to the easement granted to Atlanta Gas Light, on June ii,O,
2014, which deed is recorded in the records of the Clerk of Superior Gourt of Richmond Courtly,
Gcorgia, in Realty Book 1445, Pagcs 1801-1802, and is granted together with the right of
ingreis and egresi thereto, as long is such ingress and egress bc outside of any fenced and/or
galcd area(s) of tfre Max N. Hicfs WTP property and in no way pose a threat to the security a td
iafety of same. Should a time comc, when AUGUSTA determines that it is necessary for t,re
ingreis and egress route to be changed, it will notify AGL thirty (30) days prior to such chant:le.
AGL shall have no right to protest such determination.
PURPOSE
Also granted to AGL is the right to construct, install, maintain, inspect, operate, repiirir,
rcplace, change, or remove a gas rigulator station, or stations, including regulators, heaterrs,
pipcline gate vLke, or valves, witn eny by-passes, cross-overs, scrapcr traps, gas main or milin
inO otne? appurtenances and equipmeni used in connection therewith or incidental hereto, or
any part thereof within the easement as shown on EXHIBIT 'A."
REVERSION
AUGUSTA grants this easement with the understanding that should AGL, for ttny
reason, abandon said easement, or cease to use said easement for the herein stated purposrrs,
said easement shall immediately revert to AUGUSTA.
INpEMNtFTCATTON
AUGUSTA grants this easement with the understanding that AGL agrees hereby to
indemnify, save and hold AUGUSTA harmless from and against any and all claims, or le1lal
actions, arising out of, or in any way connecled with, the use by AGL, its. representative r,
agents,'or inviiees of the herein easement. AGL agrees to indemnify, save and hold AUGUSI'A
hirmless from any and all harm that may arise from, or be caused by, its occupancy r)r
activities, on said easement.
TO HAVE AND TO HOLD thc aforesaid rights, ways, eascments, privileges at'rd
appurtcnances unto AGL, in perpetuity.
lN WITNESS WHEREOF, AUGUSTA has set its hand and scll, thc day and year fit'st
abovo written.
Signod, Sealed and Delivered in thc prproncc of:
AUGUSTA, GEORGIA
By:
Hardie Davis, Jr,
As its Mayor
Attest:
Clerk of Commission
(sEAL)
WTNESS
NOTARY PUBLIC
Rlctmond County, Gcorgia
My Commisrion Expires:
(Noary Seal)
lN WITNESS WHEREOF, ATLANTA GAS LIGHT, the un_dersigned has hereunto sct,
his, her, their, hand and seal this 5 day of n { /'6ts.
Signed, sealed and delivered
t*a
My Commission Expires:
(NOTARY SEAL)
ATLANTA GAS LIGHT COMPANY
Title: Vice President of Operations_.-
in the presenqe of:
Unofficial Witness
I , I: i RICHMOND COUMt/t,' 'l I : I l6ootro'u
I j , lr . i I l
r ri , I i I
ltll I rl/' , i,rl',riif|I Ili I , .[*,ffi,T*f,#-+I ceonor PoffiR EASEUENI
I
I : '* , /.r( :ii ;I !,e I jr r, Ir[,t,lri,: II'l I , -'_i4*t I r? i_--4-', i
* -l-
iPorcel Line Toble L- a,'-Z@r-r I Nr rs' oo"w I zs.oo' J I
L2 I Naa'+z' oo'E I rs.oo' I I
LJ I sr ra' oo"e I zs.oo' I t.rr+ I saa' +z' oo"w I ts.oo' l, ]
PERTIAI,IENT REGULATOfl ESIIT.
375 S0. FT.0.0086 Ac.
GEORGIAY
D.
I li
1,.
PROPOSED
hrcuuron
EASEMENT
375 SQ. FEET
NiF
LrcEll'lD
O PIE'OEoH} PlEP0fx/H,YEDal II TB VIIITD*l G/ S vrl'\f,O tttT P?to flrDrcrlE)fix(aifio)-G-- r:; [q{ cN |tf-P-- t:ilndr dfrlc 0 Porti-FO-- t::Altoa Rtn ems $E
:li0{-l
lu.rJ-- iit-;-4l-f
11.'Ili 1li ilr
LJ
AUOUSTA.CEORGIA P.o.a.,IfiIsrHfl$
PARCEL t5700t8080 efii nrfiT-f-t Y
D,8.806, PC, 2004
-^'r LINE\FL- , \.
L{}.t-;u'-rlr
cAsLE - -
/B/rl-\ ATLANTAGASLIGHT
' ' r -
D,B, r44i, PG, l8o r
EXHIBT 'A'
*P.O.B.gl, rf oq:E 1t2.,8tm atE&lqFrlfff OA FOWER MW AITID $OUTHENN
A.r1Y OFTOTACCOnOAD
I
I
I
,t
lI,t
I
I
i
I
THEN{&SOUmVSg,r'ilvloAcoNmErE
TOUNDATPNOTEMT
C&AFHTC SClr-€E
ATLANTA OAS LIEHT IRAW\,1: M-F-./K-P.
'ILE:
PROPOSID PERMANENT REGULATOR EASEMENT CROSSING
AInJSIA GEONOA
RI'HMOND 'OIINTY GFOPGIA
}CALE: l"= 30'
IAT:E: 4/27/15l6sdo)HECKED; B.H.
REUSION ) ATE ENOl.lO4(XXt
BY: Phoenlx Conrulthg
Augusta, GA
lit, t*l
,a
r rlp "r
Disclaimer: While every eJJbrt is nade to keep in/brmation provided over the
internet accurate and up-to-date, tlugusta does not certillt the authenticity or
occurocy oJ'such information. No warronties, express or intplied, are providedfctr
the records and/or mapping dota herein, or.fbr their use or interpretation by the
User.
,#s;
ifs! 'r";hr'
'-:ft,H"$,
s+u
fffht
Map Scale
I inch :376 feet
lUt9l20t5
Engineering Services Committee Meeting
1/12/2016 1:05 PM
Atlanta Gas Light Easement Deed for Gas Regulator Station
Department:Augusta Utilities Department
Presenter:Tom Wiedmeier
Caption:Consider approving an Easement Deed to Atlanta Gas Light for a
Gas Regulator Station.
Background:On June 30, 2014, Augusta granted an easement, to Atlanta Gas
Light (AGL), for a Regulator Station, on its’ property at the Max
N. Hicks WTP. When AGL began installation of the regulator,
they discovered that they were too near the FAA cable that runs
on the site. AGL is requesting an additional easement, so that
they can set the regulator further away, from the FAA cable.
Analysis:The requested additional easement is small, consisting of an area
of 375 square feet. The area is near the Tobacco Road right-of-
way and abuts the Georgia Power Easement. It is in an area that is
not needed, for the operations of the Hicks Plant.
Financial Impact:None
Alternatives:Disapprove the additional easement to Atlanta Gas Light.
Recommendation:Approve the additional easement to Atlanta Gas Light.
Funds are Available
in the Following
Accounts:
N/A
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Augusta-Richmond County, Georgia
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County,
Georgia that the following Capital Project Budget is hereby authorized:
Section 1: The project is authorized to CPB# 323-041110-201823332 to award the Construction contract
to Blair Construction in the amount of $5,938,494.60 for Belair Road Improvement
project. Funding in the amount of $5,938,494.60 is available in the project construction account
($1,300,000), LMIG Funds ($2,983,376.95); TIA Discretionary ($815,601.65) and Augusta
Utilities Department ($839,516.00).
Section 2: The following revenues are anticipated to be available to the Consolidated
Government to complete the project.
Special 1% Sales Tax, Phase III 2,341,000$
Special 1% Sales Tax, Phase III Recapture 20,000$
AUD 15,000$
LMIG 2,983,377$
TIA Discretionary 815,602$
AUD 839,516$
7,014,495$
Section 3: Copies of this Capital Project Budget shall be made available to the
Comptroller for direction in carrying out this project.
Adopted this ____________________ day of ______________________.
Approved
_________________________________________________
Original-Commission Council Office
Copy-Public Works
Copy-Finance Department
Copy-Purchasing Department
CPB#323-041110-201823332
CAPITAL PROJECT BUDGET
BELAIR ROAD
(Wrightsboro Road to Jimmie Dyess Parkway-Formerly New Belair Road)
Honorable Hardie Davis, Jr., Mayor
12.29.2015
Augusta-Richmond County, Georgia CPB#323-041110-201823332
CAPITAL PROJECT BUDGET
BELAIR ROAD
(Wrightsboro Road to Jimmie Dyess Parkway-Formerly New Belair Road)
CPB AMOUNT CPB NEW
CPB CHANGE CPB
SOURCE OF FUNDS
SPOST, PHASE III
323-041110-0000000-000000000 ($2,341,000) ($2,341,000)
SPLOST, PHASE III RECAPTURE
323-04-1110-6011110-296823333 ($20,000) ($20,000)
AUD
507-04-3410-5212115-81000030 ($15,000) ($15,000)
LMIG ($2,983,377) ($2,983,377)
TIA Discretionary ($815,602) ($815,602)
AUGUSTA UTILITIES ($839,516) ($839,516)
TOTAL SOURCES: ($2,376,000) ($4,638,495) ($7,014,495)
USE OF FUNDS
ADVERTISING
323-04-1110-5233119-201823332 $1,000 $1,000
ENGINEERING
323-04-1110-5212115-201823332 $441,785 $441,785
RIGHT OF WAY
323-04-1110-5411120-201823332 $184,750 $184,750
CONSTRUCTION
323-04-1110-5414110-201823332 $1,748,465 $3,798,979 $5,547,444
AUGUSTA UTILITIES $839,516 $839,516
TOTAL USES: $2,376,000 $4,638,495 $7,014,495
12.29.2015
CPB#323-041110-201823332
12.29.2015
CPB#323-041110-201823332
12.29.2015
Invitation to Bid
Sealed bids will be received at this office on Thursday, August 20, 2015 @ 3:00 p.m. for furnishing:
Bid Item #15-196 Belair Road Drainage Improvements Project for Engineering Department
Bids will be received by Augusta, GA Commission hereinafter referred to as the OWNER at the offices of:
Geri A. Sams
Procurement Department
535 Telfair Street - Room 605
Augusta, Georgia 30901
706-821-2422
Bid documents may be examined at the office of the Augusta, GA Procurement Department, 535 Telfair Street –
Room 605, Augusta, GA 30901. Plans and specifications for the project shall be obtained by all prime,
subcontractors and suppliers exclusively from Augusta Blue Print. The fees for the plans and
specifications which are non-refundable are $200.00.
It is the wish of the Owner that all businesses are given the opportunity to submit on this project. To facilitate this
policy the Owner is providing the opportunity to view plans online (www.auguatablue.com) at no charge through
Augusta Blue Print (706 722-6488) beginning Thursday, July 9, 2015. Bidders are cautioned that submitting a
package without Procurement of a complete set are likely to overlook issues of construction phasing, delivery of
goods or services, or coordination with other work that is material to the successful completion of the project.
Bidders are cautioned that acquisition of documents through any other source is not advisable. Acquisition of
documents from unauthorized sources places the bidder at the risk of receiving incomplete or inaccurate
information upon which to base his qualifications.
A Mandatory Pre Bid Conference will be held on Friday, July 31, 2015 @ 10:00 a.m. in the Procurement
Department, 535 Telfair Street, Room 605. A mandatory site visit will follow.
All questions must be submitted in writing by fax to 706 821-2811 or by email to
procbidandcontract@augustaga.gov to the office of the Procurement Department by Tuesday, August 4,
2015 @ 5:00 p.m. No bid will be accepted by fax, all must be received by mail or hand delivered.
No Bid may be withdrawn for a period of 60 days after time has been called on the date of opening. A 10% Bid
bond is required to be submitted along with the bidders’ qualifications; a 100% performance bond
and a 100% payment bond will be required for award.
Invitation for bids and specifications. An invitation for bids shall be issued by the Procurement Office and shall
include specifications prepared in accordance with Article 4 (Product Specifications), and all contractual terms and
conditions, applicable to the procurement. All specific requirements contained in the invitation to bid
including, but not limited to, the number of copies needed, the timing of the submission, the required
financial data, and any other requirements designated by the Procurement Department are considered
material conditions of the bid which are not waiveable or modifiable by the Procurement Director. All
requests to waive or modify any such material condition shall be submitted through the Procurement Director to
the appropriate committee of the Augusta, Georgia Commission for approval by the Augusta, Georgia
Commission. Please mark BID number on the outside of the envelope.
Bidders are cautioned that acquisition of BID documents through any source other than the office of the
Procurement Department is not advisable. Acquisition of BID documents from unauthorized sources places the
bidder at the risk of receiving incomplete or inaccurate information upon which to base his qualifications.
GERI A. SAMS, Procurement Director
Augusta Chronicle July 9, 16, 23, 30, 2015
Metro Courier July 15, 2015
Revised: 1/12/2015
TRI-STAR CONTRACTORS INC
ATTN RICHARD BERRY
47 LEGACY LANE
EDGEFIELD SC 29824
CONTRACT MANAGEMENT INC
ATTN: BARRETT BOWDEN/JAMES
WILLIAMS
1827 KILLINGSWORTH
AUGUSTA GA 30904
COLUMBIA DIVERSIFIED INC.
ATTN: DAVID WHEATLEY
6677 EUBANKS DRIVE
APPLING, GA 30802
QUALITY STORM WATER SOLUTIONS
ATTN THERON SAPP
437 CAMBRIDGE CIRCLE
MARTINEZ GA 30907
EAGLE UTILITY
ATTN TIM MCELROY
1350 BRANCH ROAD
BISHOP, GA 30627
BLAIR CONSTRUCTION
ATTN PATRICK DILLARD
PO BOX 770
EVANS, GA 30809
D & S UTILITIES
ATTN BILL HEAD
1644 HOLY TRINITY CHURCH ROAD
LITTLE MOUNTAIN, SC 29075
L-J INC
ATTN: RANDALL MCCLAIN
603 PINE LOG ROAD
BEECH ISLAND, SC 29842
HARRIS CONSTRUCTION
ATTN: JEFFERY HARRIS
1736 BARTON CHAPEL ROAD
AUGUSTA, GA 30906
MABUS BROS CONSTRUCTION
ATTN LARRY GOOLSBY
920 MOLLY POND ROAD
AUGUSTA, GA 30901
GA-CAROLINA PAVING
3020 MILLEDGEVILLE RD.
AUGUSTA, GA 30904
BEAMS CONTRACTING
ATTN: BUDDY ROWLAND
15030 ATOMIC ROAD
BEECH ISLAND SC 29842
SITEC
ATTN; DAVID MCGHEE
217 FAIRFIELS STREET NE
AIKEN, SC 29801
REEVES CONSTRUCTION
ATTN: GREG HAMILTON
1 APAC INDUSTRIAL WAY
AUGUSTA, GA 30907
CROWDER CONSTRUCTION
ATTN: MARK DICKSON
1229 ROYAL DRIVE, SUITE C
CONYERS, GA 30094
WALL ASPHALT
ATTN: CHARLIE WALL
617 ROCKMART ROAD
VILLA RICA, GA 30108
J&B CONSTRUCTION & SRVC INC
3550 GORDON HIGHWAY
GROVETOWN GA 30813
GA-CAROLINA PAVING
3020 MILLEDGEVILLE RD.
AUGUSTA, GA 30904
J & H GRADING & PAVING
ATTN: KEVIN WALTERS
1579 EDGEFIELD HIGHWAY
AIKEN, SC 29801
ATTN: LOUIE A. PITTMAN, III
PITTMAN CONSTRUCTION CO
P. O. BOX 155
CONYERS, GA 30012-0155
JHC CORPORATION
ATTN: CHRIS CAYIA
1029 PEACHTREE PARKWAY N #359
PEACHTREE CITY, GA 30269
L.C. WHITFORD CO.,
ATTN: SPENCER CHRISTENSON
3765 FRANCIS CIRCLE
ALPHARETTA, GA 30004
ATTN: MATTHEW WALSH
ARCHER WESTERN CONTRACTORS
2410 PACES FERRY RD SE, STE 600
ATLANTA, GA 30339-1821
ATTN: BOBBY CATES
RUBY-COLLINS, INC
4806 WRIGHT DRIVE
SMYRNA, GA 30082
ATTN: Q. WILLIAM HAMMACK
C. W. MATTHEWS CONTRACTING
P. O. DRAWER 970
MARIETTA, GA 30061-0970
ATTN: ROBIN J. SNELL
E. R. SNELL CONTRACTOR
5102 PIERCE COURT
EVANS, GA 30809
ABIE LADSON
HAMEED MALIK
ENGINEERING DEPARTMENT
YVONNE GENTRY
LSBOP OFFICE
BID ITEM #15-196
BELAIR ROAD DRAINAGE
IMPROVEMENTS
FOR ENGINEERING DEPARTMENT
PROJECT MAILED JULY, 8, 2015
BID ITEM #15-196
BELAIR ROAD DRAINAGE
IMPROVEMENTS
FOR ENGINEERING DEPARTMENT
BID DUE: THU., AUG. 20, 2015 @ 3PM
Engineering Services Committee Meeting
1/12/2016 1:05 PM
Belair Road Improvements- Contract Award
Department:Engineering Department
Presenter:Abie L. Ladson, Director
Caption:Approve award of Construction Contract to Blair Construction in
the amount of $5,938,494.60 for Belair Road Improvement
Project as requested by AED. Award is contingent upon receipt of
signed contracts and proper bonds as requested by AED. (Bid
Item 15-196)
Background:Belair Road Improvements project is an approved SPLOST
project. This project consists of intersection improvements, Traffic
Signal Improvements, adding turn lanes, drainage improvements,
Curb & Gutter and sidewalks along Belair Road between Jimmie
Dyess Parkway and Wrightsboro Road.
Analysis:Bids were received on November 5, 2015 with Blair Construction
being the low bidder. The bid results are as follow:
CONTRACTORS BID 1. Blair Construction $5,938,494.60 2.
Reeves Construction $7,426,501.00 It is the recommendation of
the Engineering Department to award this project to Blair
Construction.
Financial Impact:Funds are available in the construction budget 323-041110-
6011110/201823332-6011110 ($1,300,000), LMIG Funds
($2,983,376.95) 335-04-1110/L13241301 - $1,500,000 and 335-
04-1110/L14341302-$1483,377; TIA Discretionary Funds
(815,601.65), and Augusta Utilities Department ($839,516.00)
Alternatives:1). Approve award of Construction Contract to Blair Construction
in the amount of $5,938,494.60 for Belair Road Improvement
Project as requested by AED. Award is contingent upon receipt of
signed contracts and proper bonds as requested by AED. 2). Do
not approve and cancel the project.
Recommendation:Approve Alternative Number One.
Funds are Available
in the Following
Accounts:
323-041110-6011110/201823332-6011110 ($1,300,000) LMIG
Funds ($2,983,376.95)335-04-1110/L13241301 - $1,500,000 and
335-04-1110/L14341302 $1,483,377; TIA Discretionary Funds
(815,601.65); and Augusta Utilities Department ($839,516.00)
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Please do not process . Once approved by Commission the original Agreement
will be sent for execution. Any questions please contact AED @ ext 5070. Thanks
Engineering Services Committee Meeting
1/12/2016 1:05 PM
Druid Park Improvements (Walton Way to Wrightsboro Road) Utilities Relocation Reimbursement
Department:Abie L. Ladson, Director
Presenter:
Caption:Approve entering into an agreement with Georgia Power, stating
that Augusta, GA will pay for the Transmission Facility
Relocation Costs on the Druid Park Road Improvements Project in
accordance with the estimate totaling $849,328.00. Also,
approve the Utility Relocation Agreement to be executed by the
Augusta, GA Legal Counsel and the Mayor, and approve payment
upon completion of the work as requested by AED
Background:The Druid Park Improvements Project is on the approved Band 1
list of Richmond County’s Transportation Investment Act of 2010
(aka, TIA, TSPLOST) projects. Project consists of improving
roadway operation, safety, surface drainage, and produce
enhanced multi-modal facilities through the use of context
sensitive design including a new roundabout, landscaped medians,
bicycle lanes and shared-use signage, lighting, and a raised
pedestrian crossing plaza.
Analysis:The Druid Park Improvements Project will require that Georgia
Power Company relocate some transmission facilities and Augusta
would be required to enter into an agreement that Augusta will
pay the estimated amount of $849,328.00. This is a cost that is
required to be paid by the City to complete needed improvements.
Financial Impact:Funds are available in Project TIA funds.
Alternatives:1) Approve entering into an agreement with Georgia Power,
stating that Augusta, GA will pay for the Transmission Facility
Relocation Costs on the Druid Park Improvements Project in
accordance with the estimate totaling $849,328.00. Also, approve
the Utility Relocation Agreement to be executed by the Augusta,
GA Legal Counsel and the Mayor, and approve payment upon
completion of the work as requested by Augusta Engineering
Department. 2) Do not approve and find alternative to complete
the project and meet TIA project completion schedule.
Recommendation:Approve Alternative Number One
Funds are Available
in the Following
Accounts:
Project TIA Funds - 371-041110-T13041219
REVIEWED AND APPROVED BY:
Finance.
Law.
Administrator.
Clerk of Commission
UTILITIES DEPARTMENT
Tom Wiedmeier
Director
' j"5 ili:{-;;i;;,r,: :};47
The Utilities Department is submitting the attached documents for rpproval by the procurement
Department in accordance with Article l0_, Sec. l-10-57, Emersencv procurement selection method.The following items nre addressed in the documents attacf,IIl
MEMORANDUM
General project concept
Specific budget approval of Expense purchase:
Source Selection Method
Expense Funds available in fund:
First Presbyterian Church
s90,477.40
Emergency Water Line Relocation
507043490-54254 I 0/88886666 _
5425410
l.
2.
3.
4.
TO:X:{y* ,t", trfat/c'
Director, Procurement Department
Tom Wiedmeier,
Director, utilfties
December 18,20r5
Emergencywater Line Relocation at First preebyterian church
The Utilities Department has an existing 20" water main running across the First presbyterian Churchparking lot on Telfair Street, in the abardoned r(7ht 9f way of Tivggs street. wn"n in" bitv abardonedthe right of way to First Presbyterian, it dkj not specifically retain an easement for the water line.
This water main is a critical water transmission feed to the downtown area that must remain in service.The Church is constructing a new addition that conflicted with the 20'water main. Because there wasno recorded easement for the water line, the church proceeded with deslgn anO OiOOing of the newaddition. The conflict was realized shorfly before the start of construction.
AUD responded with this emergency project to relocate a 'l6" water main arolnd the proposed buildirg assoon as possible in order to not delay the Church construction. AUD determired Btiir bonstruction,-lnc.to be the most suitable Task Order contractor with the abilities to respond quickly to perform pre work andmake the critical tie-ins to maintain operation of this water main.
Due to the lack of a recorded easement, we agreed to share in the cost of relocation. FirstPresbyterian committed to paying up to $4s,000 for the relocation.
The construction is completed and the final cost is $90,477.40 as submitted by Blair. Additional cost wasincurred for the paving needed to restore disturbed areas in Walker Street lcoiisem Authoity parringentry drive). AUD reviewed the cost and found it to be fair, reasonaute, anJ ln-accoroance with AUDdirection during the emergency construction.
Attached are the project drawing, Blai/s request for payment, and a requisition for the seMces provided. Thank),ou.
Augusta Utllities Administration
360 Bay Stre: - Suite I 80 - Augusta. GA 30901(7M) 3t24ts4 - Fax (70613tZ4tZ3
WWW.AUGUSTAGA.COV
FROM:
DATE:
SUBJECT:
tootrl
oilAA
c-rr)<)ix
t
o)
omo
o
U)
,morrlF-
a)L
5I
EIIB
L€)
Ethe)hI
ehL
l*
G
o
6loo
o)
d,
€)
J
Lo,
ct
'a)troa0Lq)
Td
:trltr/.t&ll!I!&a.
t!U&)oq)
trlJo?
Uztrlodlll
E:I
tiolrzaF
U
f&
tr.n
=-]
o
!t\6t{tatI\o\o\o\ooo€€€
c)
$rnc.l.+(a
I
o\$t?tsr
r*o!
#oz
lJ-
>"t!F
&HIL,eldOi
EiQ&
ov)r!Joo
,Uzlll()&EI
rI]
rI1zF
P
&sbdg
R.E4Eoo oo-trII]
2o
!il9?<r.oo
+tzo
Fa
DorI]&
FzE]
2izeo
SEtllqao5at1
H IJ]1-&iEl;at<'1>5<Et-Jaa
o
J
FoF
Blair Construction, Inc.
Asphalt Pauing & Underground UtiUties
4308 Evans-to-Locks Rd
P.O. Box 770, Evans, Georgia 30809
Phone 706.868.1 950 Fax 706.868.1 855
Augusta Utllaties Dept
Steve Behrend
DATE: October 14,2015
rNvotcE # 1568
FOR: First Pre sbyterlan
Description Proposed Quantl$Actual Quanlty Unlt Prlce AJOUNT
:urnish and lnstall 16 inch DIP 350 restrained 2St 27f;LF $121.00 $ 33,275.00
Iapping Sleeve and Valve 20X16 ,|1 EA $14,110.00 $ 14,110.00
=urnish and lnstall 16 inch valve open right 1 1 EA $6.286.0($ 6,286.00
:umish and lnstall 12 inch valve open righl 1 c EA $2,600.0($
,ressure test including 2 test taps 1 1 LS $1,600.0($ 1,600.00
Visc Filtings c s EA $1,088.0($ 9,792.00
Srassing 1 c LS $600.0($
Sterilization 'l ,|LS $2,300.00 s 2.300.00
Final Connections Sunday NighUMonday Morn 1 1 LS $5,200.00 $5,200.00
Palch Pavement Coliseum Properly 6t u SY $48.00 $ 4,512.00
Remove Fence 'l 1 LS $750.00 $750.00
lump Sum 10% (mob/demob,traffic control, etc)1 ,|LS $8,'149.m $ 8,149.00
$ 81,462.00
Curb to Curb Overlay 35f SY $12.65 $4,503.40
Church has agreed to remove the oak tree
lnvoice will refleci the aclual quantities
TOTAL $ 90,477.40
THANK YOU FOR YOUR BUSIT{ESSI
ATTACHMENT A: Prime Contractor Data Gollection Form
BID NUMBER
PRIME CONTRACT TITLE:
START I}ATE:
Telfair St Walerline
08tuDats
COMPLETION DATE:wt4l20t5
Complete the Following Informationlor Each Contract/Purchase Order ldentiJied
Business Name:Blair Construction,Inc
Business Contact Person Infonnation:
Name:William R Mutimer, Jr
Title:
E-Mail:
Vice-President Telephone: (706 r 868-1950
wil lia m @blairco nstructiol.uq
Business Address:P.O. Box 770,4308 Eviuos to Lock Road
City, State, Zip:Evans Georgia 30809
Total Award Amount (including all Change Orders):$
$
s
$
90,477.40
Total Amount Paid:
Total Amount Paid:
Total Amount Paid:
Brief Description of Work Performed by Prime Contractor:
Business Owner(s) Primary Race/Ethnicity (White, Black, Hispanic, Asian, Native American, orOther): White
Business Owner(s) Primary Gender (Male or Fernale):Mate
Total No. of First-Tier Subcontractors/Sub-consultants/Suppliers on this Contract:
{This number should match the number of entries cn Attachment B)
2013
2014
?015
CERTIFICATION
'
SIGNATURE PAGE TOR ATTACHIT'IENTS A & B
I attes! to the best ofmy knowledge and belief, that the information furnished in
Attachment A and Attachment B is correct and accurate.
William R Mulimer, Jr V.P.
PRINTED NAME AND TITLE
Company:Blair Construction, lnc.
Narne of Company
PhoneNtrmber:
Date:
706-868-1950
rcl8ngt5
Name and Title of Company
sq(
o\
tdOic.l\o
-l
rn
fnrfi
\o
(\l.q\0
o\t\dt
o\
rocr\?.1\oc,l
4
\o
c!a\o
o\t"
Ed)!r=,o.oo.a=€3b.E=()>s
l-),sor Ltro)o5
o+'i (A()
a
(\I6!3r-
-vF..;=XTO1-odx
9 5gELC.\o
\oao(\\oo99*,nLr€t+!imoo
-t1rl6<s
-v(>a $FAtr(d
=
tn;3._o tq I.iE.g+f-o
=chdaEoNor;r'hE
:oo
=m-!1 tntsx€XYclteEqooYO\ta€.-o()
C'\\oAo.€3xoU)oqo-rCG!r
EE$>=6 ooO11 6
XE3
IA3
e)
sl
OD0.)ko060
lI)
ti)L()
o(.1
a()
d
,o
E
or)
oc
()
o4€0.c,F
a!
iEo(,U
ec!
Qooat\r-r+oc'\s
qa !dJ<
troF.z
F
N
t-3
3or{(,oto
I
oF
2
I&o
E,rdAF
o6.rll&
E
o
ra
oz
F.UhlF!o
A
it)g
!.,(l
q)
(coF
x
c
Filjlr- I
=tsrJ _ .t)i! Irl '=Jd =Az EF LJ .I'
EL. H O)Af-u7u,, =frs 3
EH -q?b bd* :.[d g-- u-aFl O<trrdA. U0Z,H trIq= €rE €f) \r/ .=On ,inx g>r B2zgxu 61,, tY! '!:'l\Ji) EHLA E<l 8\rr-o>E Atqt a"
-a-(JY 6Jaz EIts.]
l.raI]?l
.G
Bl!-
6
P
r!
o
-l:ll.:
J
F
F&o
elo
t-zaU&
rI1!.
ta
F"
2t,aAL:N
&o
L
4l
*zOr-r- l^LJ tr]
td'- Elzc
la|z
zFUfil
Eda-
NiFoN
€qc-t-t-oo\
o
=6iES.a\j
I3\
=N!0o
G'<E \o'tS'LF.a)!?$r(L
=ro\o1S€N
9nlaoog3'o r\,o\-c, .-O\i
3S.q \)
>'\-O L'
Fr q)FS7E
lJ -5AE€lU<3hECt,.osdu
il)
oE-oo g
hotd
.?EF
z
t-
N
Jt
ov2
aslooGo*A.
uo
!0
frJ(a
ozf-Uf:]h
!
o
6)d>
t/)
'a
()F
o()'a
liO.
a
co.(,o(n
(,.oo
rh
o
Lo)
'{)
60
t
otr
a
4.,ra
U)
U2LJoo(c
oos
ct')
cl
a
-1
=&Uo*nr)t-;tHar
ri tEl,HazH9;ti
a$2HF{ ,i(2\
afrrH
lFl<t>*aa;i*
AFis
fF-2VXUHE\J ;)aaz>OF1z2
7eit'(a;)U
t
(>
oF
_l
+lol
I
Eo
TLnIilf:lo.
,oLr{il
,:t
a,
z
btd
o
x
Engineering Services Committee Meeting
1/12/2016 1:05 PM
Emergency Water Line Relocation
Department:Utilities
Presenter:Tom Wiedmeier
Caption:Notification of emergency water main relocation at First
Presbyterian Church by Blair Construction, Inc. in the amount of
$90,477.40.
Background:The Utilities Department has an existing 20” water main running
across the First Presbyterian Church parking lot on Telfair Street,
in the abandoned right of way of Twiggs Street. When the City
abandoned the right of way to First Presbyterian, it did not
specifically retain an easement for the water line. This water main
is a critical water transmission feed to the downtown area that
must remain in service. The Church is constructing a new addition
that conflicted with the 20” water main. Because there was no
recorded easement for the water line, the church proceeded with
design and bidding of the new addition. The conflict was realized
shortly before the start of construction. AUD determined Blair
Construction, Inc. to be the most suitable Task Order contractor
with the abilities to respond quickly to perform the work and make
the critical tie-ins to maintain operation of this water main.
Analysis:Due to the lack of a recorded easement, we agreed to share in the
cost of relocation. First Presbyterian committed to paying up to
$45,000 for the relocation. The construction is completed and the
final cost is $90,477.40 as submitted by Blair. Additional cost was
incurred for the paving needed to restore disturbed areas in
Walker Street (Coliseum Authority parking entry drive). AUD
reviewed the cost and found it to be fair, reasonable, and in
accordance with AUD direction during the emergency
construction.
Financial Impact:$90,477.40 under account number 507043490-
5425410/88886666-5425410
Alternatives:N/A
Recommendation:Submitted for information.
Funds are Available
in the Following
Accounts:
Funds are availble in account 507043490-5425410/88886666-
5425410.
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Engineering Services Committee Meeting
1/12/2016 1:05 PM
GA Power Solar Program
Department:Environmental Services
Presenter:Mark Johnson
Caption:Authorize Augusta’s participation in the Georgia Power
Distributed Generation (solar energy) program, paying the $25 per
KW capacity reservation and authorizing Augusta to execute all
documents required under the program.
Background:Augusta evaluated feasible sites at city facilities and identified 5
possible locations suitable for this program, and applied to
Georgia Power to be considered under this program. Currently,
Georgia Power is performing an interconnect impact study which
is scheduled to be complete on January 22, 2016. On or about that
date Georgia Power will announce projects which could be
awarded under this program. Georgia Power has performed onsite
inspections for interconnect impact at 3 of the 5 sites submitted,
which include, the sewer treatment plant on Mike Padgett, the
water production facility on Tobacco Road and the jail on Phinizy
Road. Upon Georgia Power releasing the final short list, awarded
projects will be required to pay the $25 per KW capacity
reservation, which is estimated to cost Augusta $25,000 per site
selected.
Analysis:In the event that Augusta is awarded any of these projects, it must
operate on an accelerated timeline to meet the goal of Georgia
Power to have these projects online by the end of 2016.
Additionally, there is an economic benefit to accelerating such
projects as there is a 30% tax credit which is scheduled to expire
at the end of 2016. This tax credit could greatly reduce the
expense to Augusta. Therefore, Augusta is proposing doing an
accelerated version of a design build RFP or solicit interest in a
developer land lease agreement.
Financial Impact:At current market conditions, Augusta assumes a range of capital
cost of about $2.25 per watt. Thus, a megawatt system would cost
an estimated $2,250,000. Under this program Georgia Power is
paying 10.4 cents per kWh for a 25 year power purchase
agreement (PPA) and 11.4 cents per kWh for a 35 year PPA. At
an annual production of 1,500,000 kWhs for each 1MW installed,
that would equate to annual revenues of $156,000-$171,000.
Based on the lower revenue projections the system would generate
$3,900,000 over the life of the PPA with an initial investment of
$2,250,000.
Alternatives:Do not participate in Georgia Power's solar program.
Recommendation:Authorize Augusta’s participation in the Georgia Power
Distributed Generation (solar energy) program, paying the $25 per
KW capacity reservation and authorizing Augusta to execute all
documents required under the program.
Funds are Available
in the Following
Accounts:
Funds for the $25 per KW would be paid for by account number
541-04-4210/5212999. The department will need to move
approximately $25,000 into this line items to cover the full
amount of the project.
REVIEWED AND APPROVED BY:
Finance.
Law.
Administrator.
Clerk of Commission
Augusta-Richmond County, Georgia
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County,
Georgia that the following Capital Project Budget is hereby adopted:
Section 1: This project is authorized to CPB#371-041110-T13049126 to enter into an agreement with
Georgia Power stating that Augusta, GA will pay 19.17% of the estimated cost, which is
$154,448.00 for relocation of Distribution Facility on the Marks Church Road project
with the estimate totaling $805,615.00. Funding to come from TIA Discretionary.
Section 2: The following revenues are anticipated to be available to the Consolidated
Government to complete the project.
Special 1% Sales Tax, Phase V 2,500,000$
TIA Discretionary 195,975$
TIA Project Funds 24,850
TIA Project Funds 568,145
TIA Discretionary 154,448
3,443,418$
Section 3: Copies of this Capital Project Budget shall be made available to the
Comptroller for direction in carrying out this project.
Adopted this ____________________ day of ______________________.
Approved
_________________________________________________
Original-Commission Council Office
Copy-Engineering Department
Copy-Finance Department
Copy-Procurement Department
CPB#371-041110-T13049126
Honorable Hardie Davis, Jr., Mayor
CAPITAL PROJECT BUDGET
MARKS CHURCH ROAD RECONSTRUCTION PROJECT
CHANGE NUMBER SIX
Please do not process this document. Once approved by the Commission the original will be sent to the Clerk of Commission for execution. For information reference this request, contact Engineering at ext 5070. Thanks
1 of 2 12.21.2015
Augusta-Richmond County, Georgia CPB#371-041110-T13049126
CAPITAL PROJECT BUDGET
MARKS CHURCH ROAD RECONSTRUCTION PROJECT
CHANGE NUMBER SIX
CPB AMOUNT CPB NEW
SOURCE OF FUNDS CPB ADDITION CPB
SPLOST, PHASE V
325-04-1120-6011110 ($2,500,000)($2,500,000)
TIA DISCRETIONARY ($195,975)($154,448)($350,423)
371-041110-5212115/T13049126-5212115 ($592,995)($592,995)
TOTAL SOURCES: ($3,288,970) ($154,448) ($3,443,418)
USE OF FUNDS
ENGINEERING
325-04-1120-5212115-209825201 $685,128 $685,128
CONSTRUCTION
325-04-1120-5414110-209825201 $396,010 $396,010
CONSTRUCTION
371-041110-5414110-T13049126 $568,145 $568,145
UTILITY
325-041120-5414510-209825201
$1,639,687 $154,448 $1,794,135
TOTAL USES:$3,288,970 $154,448 $3,443,418
2 of 2 12.21.2015
Engineering Services Committee Meeting
1/12/2016 1:05 PM
Mark Church Road Improvements -Utilities Relocation Reimbursement
Department:ABIE L. LADSON, DIRECTOR
Presenter:ABIE LADSON
Caption:Approve entering into an agreement with Georgia Power for
relocation of distribution facilities associated with the Mark
Church Road Improvements Project; approve the Utility
Relocation Agreement to be executed by the Augusta, GA Legal
Counsel and the Mayor, and approve payment upon completion of
the work.
Background:Mark Church Road Improvements Project is one (1) of fifty (50)
City of Augusta, Georgia TIA (aka TSPLOST) projects. Project
limits are Wrightsboro Road to I-520/Wheeler Road off ramp.
This project consists of widening the existing two-lane roadway to
a three-lane roadway, and adding curb & gutter, sidewalks and a
storm sewer. Project will be completed in two phases (Phase 1 and
Phase 2). Phase I scope consist of utilities relocation and is under
construction. Roadway improvements require relocation of
Georgia Power facilities outside the roadway ROW and Augusta
Georgia is responsible to pay for such relocation
Analysis:The Mark Church Road Improvement Project will require that
Georgia Power relocates its distribution facilities within project
limits. It is mandated that Augusta, GA enters into an agreement
to pay 19.17% of the estimated cost, which is $154,448.00. This is
a cost is required to be paid by the City to complete needed
improvements.
Financial Impact:Georgia Power has advised the Augusta share cost is $154,448.00.
Funds are available in TIA Discretionary funds.
Alternatives:1) Approve entering into an agreement with Georgia Power for
relocation of distribution facilities associated with the Mark
Church Road Improvements Project; approve the Utility
Relocation Agreement to be executed by the Augusta, GA Legal
Counsel and the Mayor, and approve payment upon completion of
the work. 2) Do not approve and find alternative to complete the
project and meet TIA project completion schedule.
Recommendation:Approve Alternative Number One
Funds are Available
in the Following
Accounts:
TIA Discretionary Funds
REVIEWED AND APPROVED BY:
Finance.
Law.
Administrator.
Clerk of Commission
Engineering Services Committee Meeting
1/12/2016 1:05 PM
Minutes
Department:Clerk of Commission
Presenter:
Caption:Motion to approve the minutes of the Engineering Services
Committee held on December 8, 2015.
Background:
Analysis:
Financial Impact:
Alternatives:
Recommendation:
Funds are Available
in the Following
Accounts:
REVIEWED AND APPROVED BY:
Augusta-Richmond County, Georgia
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County,
Georgia that the following Capital Project Budget is hereby adopted:
Section 1: This project is authorized to CPB#371-041110-T15040154 to enter into an agreement with Georgia Power, stating that
Augusta, GA will pay 42.53% of the estimated cost of $259,497.00 for the cost to relocate the Distribution facilities
Section 2: The following revenues are anticipated to be available to the Consolidated
Government to complete the project.
Special 1% Sales Tax, Phase III 1,467,000$
Special 1% Sales Tax, Phase IV 600,000$
TIA Discretionary Funds 226,597$
SPLOST III Recapture Funds 248,197$
TIA Discretionary Funds 96,411$
TIA Discretionary Funds 259,497
GDOT M230 136,552
3,034,254$
Section 3: Copies of this Capital Project Budget shall be made available to the
Comptroller for direction in carrying out this project.
Adopted this ____________________ day of ______________________.
Approved
_________________________________________________
Original-Commission Council Office
Copy-Engineering Department
Copy-Finance Department
Copy-Procurement Department
on the Windsor Spring Phase V project with the estimate totaling $609,785.00. Funding is available in the TIA project
Utility account.
CPB#371-041110-T15040154
CAPITAL PROJECT BUDGET
WINDSOR SPRING ROAD IMPROVEMENTS, PHASES IV & V
(SR 88 TO WILLIS FOREMENA RD AND WILLIS FOREMAN RD TO TOBACCO RD)
UTILITY RELOCATION REIMBURSEMENT
Honorable Hardie Davis, Jr., Mayor
Please do not process this document. Once approved by the Commission the original will be sent to the Clerk of Commission for execution. For information reference this request, contact Engineering at ext 5070. Thanks
1 of 2 12.21.2015
CAPITAL PROJECT BUDGET
WINDSOR SPRING ROAD IMPROVEMENTS, PHASES IV & V
(SR 88 TO WILLIS FOREMENA RD AND WILLIS FOREMAN RD TO TOBACCO RD)
UTILITY RELOCATION REIMBURSEMENT
CPB AMOUNT CPB NEW
SOURCE OF FUNDS CPB ADDITION CPB
SALES TAX, PHASE III
323041110-000000-299823766 ($1,467,000)($1,467,000)
SPECIAL 1% SALES TAX, PHASE IV
324041110-000000-202824766 ($600,000)($600,000)
TIA DISCRETIONARY FUNDS ($323,008)($323,008)
SPLOST III RECAPTURE FUNDS ($248,197)($248,197)
GDOT M230 ($136,552)($136,552)
TIA UTILITY FUNDS ($259,497) ($259,497)
TOTAL SOURCES:($2,390,008) ($259,497) ($3,034,254)
USE OF FUNDS
ENGINEERING
323041110-5212115-299823766 $1,745,061 $1,745,061
ENGINEERING
32304110-5212115-299823766 $459,560 $459,560
RIGHT OF WAY
323041110-5411120-299823766 $570,136 $570,136
UTILITY
371-041110-T15040154-5414510 $259,497 $259,497
TOTAL USES:$2,774,757 $259,497 $3,034,254
2 of 2 12.21.2015
Engineering Services Committee Meeting
1/12/2016 1:05 PM
Windsor Spring Road Phase V Improvements - Relocation Reimbursement
Department:Abie L. Ladson, Director
Presenter:Abie Ladson
Caption:Approve entering into an agreement with Georgia Power for
relocation of distribution facilities associated with the Windsor
Spring Road Phase V Improvements Project; approve the Utility
Relocation Agreement to be executed by the Augusta, GA Legal
Counsel and the Mayor, and approve payment upon completion of
the work as requested by AED.
Background:Windsor Spring Road Phase V is a Commission approved
SPLOST project. It is a blended roadway improvements project
funded by local, state and federal funds. Augusta is responsible
for funding roadway design, environmental permitting, and public
owned utilities relocation. GDOT under agreement with Augusta
is responsible for the funding and managing of roadway
construction. GDOT let this project on December 18, 2015 and
ER Snell is the contractor. Construction bid for phase V is
$21,734,133.15. Roadway improvements require relocation of
Georgia Power facilities outside of the roadway ROW. Augusta
Georgia is responsible to pay for such relocations.
Analysis:The Windsor Spring Road Phase V Project requires that the
Georgia Power Company relocate its distribution facilities within
project limits. It is mandated that Augusta, enters into an
agreement to pay 42.53% of the estimated cost, which is
$259,497.00. This cost is required to be paid by the City in order
to complete the needed improvements.
Financial Impact:Georgia Power has advised the Augusta share cost is $259,497.00.
Funds are available in Project TIA funds.
Alternatives:1) Approve entering into an agreement with Georgia Power for
relocation of distribution facilities associated with the Windsor
Spring Road Phase V Improvements Project; approve the Utility
Relocation Agreement to be executed by the Augusta, GA Legal
Counsel and the Mayor, and approve payment upon completion of
the work as requested by AED. 2) Do not approve and find an
alternative to complete the project and meet TIA project
completion schedule.
Recommendation:Approve Alternative Number One.
Funds are Available
in the Following
Accounts:
Project TIA Funds 371-04110-5414510-T15040154
REVIEWED AND APPROVED BY:
Finance.
Law.
Administrator.
Clerk of Commission