HomeMy WebLinkAbout2015-01-12-Meeting Mintues
Engineering Services Committee Meeting Commission Chamber - 1/12/2015
ATTENDANCE:
Present: Hons. Fennoy, Chairman; Hasan, Vice Chairman; Smith and
Guilfoyle, members.
Absent: Hon. Hardie Davis, Mayor.
ENGINEERING SERVICES
1. Approve construction contract award to Eagle Utility for services associated
with construction of the Highway 56 24 Inch Water Main Project in the amount
of $1,130,767.90. Bid Item 14-222
Item
Action:
Approved
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Approve
Motion to
approve.
Motion Passes
4-0.
Commissioner
Grady Smith
Commissioner Ben
Hasan Passes
2. Approve construction contract award to Gearing Brothers Civil Workers in the
amount of $1,811,949.00 for the Utilities Department.
Item
Action:
Approved
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Approve
Motion to
approve.
Motion Passes
4-0.
Commissioner
Grady Smith
Commissioner Ben
Hasan Passes
3. Approve construction contract award to Gridbee/Solarbee in the amount of
$238,400.40 for the Utilities Department. Bid 14-194
Item
Action:
Approved
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Approve
Motion to
approve.
Motion Passes
4-0.
Commissioner
Grady Smith
Commissioner Ben
Hasan Passes
4. Discuss possible solutions for Augusta Richmond County to provide
consistent clean up and maintenance of downtown sidewalks, streets and
medians. (Requested by Commissioner Davis)
Item
Action:
Rescheduled
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Defer
Motion to refer this
item to the next
committee meeting.
Motion Passes 4-0.
Commissioner
Ben Hasan
Commissioner
Wayne Guilfoyle Passes
5. Motion to approve the minutes of the Engineering Services Committee held on
December 8, 2014.
Item
Action:
Approved
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Approve
Motion to
approve.
Motion Passes
4-0.
Commissioner
Grady Smith
Commissioner Ben
Hasan Passes
6. Notification of the award of a contract with Blair Construction, Inc. for services
associated with construction of the Fort Gordon New Water and Sewage
Connections under the Task Order Program for Infrastructure RFQ #13-194 in
the amount of $696,334.89. Bid item #14-215
Item
Action:
Approved
Motions
Motion
Type Motion Text Made By Seconded By Motion
Result
Approve
Motion to
approve.
Motion Passes
Commissioner
Grady Smith
Commissioner Ben
Hasan Passes
www.augustaga.gov
4-0.
Engineering Services Committee Meeting
1/12/2015 1:15 PM
Attendance 1/12/15
Department:
Caption:
Background:
Analysis:
Financial Impact:
Alternatives:
Recommendation:
Funds are Available
in the Following
Accounts:
REVIEWED AND APPROVED BY:
Invitation to Bid
Sealed bids will be received at this office on Tuesday, November 25, 2014 @ 3:00 p.m. for furnishing:
Bid Item 14-222 Highway 56 (24 Inch) Water Main Project for Utilities Department
Bids will be received by Augusta, GA Commission hereinafter referred to as the OWNER at the offices of:
Geri A. Sams
Procurement Department
530 Greene Street - Room 600A
Augusta, Georgia 30901
706-821-2422
Bid documents may be examined at the office of the Augusta, GA Procurement Department, 530 Greene Street –
Room 600A, Augusta, GA 30901. Plans and specifications for the project shall be obtained by all prime,
subcontractors and suppliers exclusively from ARC Southern. The fees for the plans and specifications
which are non-refundable is $150.00.
It is the wish of the Owner that all businesses are given the opportunity to submit on this project. To facilitate this
policy the Owner is providing the opportunity to view plans online (www.e-arc.com) at no charge through ARC
Southern (706 821-0405) beginning Thursday, August 21, 2014. Bidders are cautioned that submitting a package
without Procurement of a complete set are likely to overlook issues of construction phasing, delivery of goods or
services, or coordination with other work that is material to the successful completion of the project. Bidders are
cautioned that acquisition of documents through any other source is not advisable. Acquisition of documents from
unauthorized sources places the bidder at the risk of receiving incomplete or inaccurate information upon which to
base his qualifications.
A Mandatory Pre Bid Conference will be held on Friday, November 7, 2014 @ 10:00 a.m. in the
Procurement Department, 530 Greene Street, Room 600A.
All questions must be submitted in writing by fax to 706 821-2811 or by email to
procbidandcontract@augustaga.gov to the office of the Procurement Department by Wednesday,
November 12, 2014 @ 5:00 p.m. No bid will be accepted by fax, all must be received by mail or hand
delivered.
No Bid may be withdrawn for a period of 60 days after time has been called on the date of opening. A 10% Bid
bond is required to be submitted along with the bidders’ qualifications; a 100% performance bond
and a 100% payment bond will be required for award.
Invitation for bids and specifications. An invitation for bids shall be issued by the Procurement Office and shall
include specifications prepared in accordance with Article 4 (Product Specifications), and all contractual terms and
conditions, applicable to the procurement. All specific requirements contained in the invitation to bid
including, but not limited to, the number of copies needed, the timing of the submission, the required
financial data, and any other requirements designated by the Procurement Department are considered
material conditions of the bid which are not waiveable or modifiable by the Procurement Director. All
requests to waive or modify any such material condition shall be submitted through the Procurement Director to
the appropriate committee of the Augusta, Georgia Commission for approval by the Augusta, Georgia
Commission. Please mark BID number on the outside of the envelope.
Bidders are cautioned that acquisition of BID documents through any source other than the office of the
Procurement Department is not advisable. Acquisition of BID documents from unauthorized sources places the
bidder at the risk of receiving incomplete or inaccurate information upon which to base his qualifications.
GERI A. SAMS, Procurement Director
Augusta Chronicle October 16, 23, 30, November 6, 2014
Metro Courier October 22, 2014
Revised: 8/15/2011
UNOFFICIAL
BEAMS CONTRACTING
15030 ATOMIC ROAD
BEECH ISLAND SC
29842
BLAIR CONSTRUCTION
P.O. BOX 770
EVANS, GA 30809
EAGLE UTILITY
1350 BRANCH ROAD
BISHOP, GA 30621
YES YES YES
167300 224004 206663
YES YES YES
YES YES YES
YES YES YES
YES YES YES
$1,183,781.07 $1,260,458.59 $1,130,767.90
Addendum 1
Addendum 2
Bid Item #14-222
Highway 56 (24 Inch) Water Main Project
For Augusta, Georgia - Utilities Department
Bid Due: Thursday, December 4, 2014 at 3:00 p.m.
The following vendors submitted a statement of "NO BID":
GEARING BROTHERS CIVIL WORKERS / 621 PONDER PLACE , SUITE 3 / EVANS, GA 30809
JND THOMAS CONSTRUCTION / 2918 PROFESSIONAL PARKWAY SUITE 100 / AUGUSTA, GA 30907
MOOREHEAD CONSTRUCTION / 1513 ANDERSON STREET / BELTON, SC 29627
MURPHY BROTHERS CONST / P. O. BOX 459 / APPLING, GA 30802
SAVE Form
Bid Bond
Bid Price
Total Number Specifications Mailed Out: 25
Total Number Specifications Download (Demandstar): 7
Total Electronic Notifications (Demandstar): 228
Mandatory Pre-Bid Conference: 7
Total packages submitted: 3
Total Noncompliant: 0
Vendors
Attachment B
E-Verify #
Page 1 of 1
Engineering Services Committee Meeting
1/12/2015 1:15 PM
Approve construction contract award in the amount of $1,130,767.90 to Eagle Utility for construction of
the Highway 56 24 Inch Water Main Project Bid item #14-222.
Department:Augusta Utilities Department
Caption:Approve construction contract award to Eagle Utility for services
associated with construction of the Highway 56 24 Inch Water
Main Project in the amount of $1,130,767.90. Bid Item 14-222
Background:The project is to install a new 24 inch water main along the right
of way on the east side of High Way 56. The project consists of
installing 4000 linear feet of new ductile iron water main and
necessary water main appurtenances. This project is needed to
provide a more reliable and adequately sized water main for both
current operation and future growth of the water infrastructure in
Richmond County.
Analysis:Eagle Utility submitted an acceptable bid package and was the
lowest responsive bidder. The staff of the Utilities Department has
completed evaluation of the bid package and it is recommended
that the award go to Eagle Utility for $1,130,767.90 to construct
the Highway 56 24 Inch Water Main Project.
Financial Impact:The lowest responsive bid for the construction of this project was
$1,130,767.90.These funds are available from the following
account 512043410-5425110/80210120-5425110
Alternatives:None
Recommendation:It is recommended to award the contract to Eagle Utility in the
amount of $1,130,767.90 for the construction of the Highway 56
24 Inch Water Main Project
Funds are Available
in the Following
Accounts:
$1,130,767.90 from account 512043410-5425110/80210120-
5425110
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Invitation to Bid
Sealed bids will be received at this office on Thursday, October 9, 2014 @ 3:00 p.m. for furnishing:
Bid Item 14-204 Gordon Highway 24 Inch Water Main Project for Utilities Department
Bids will be received by Augusta, GA Commission hereinafter referred to as the OWNER at the offices of:
Geri A. Sams
Procurement Department
530 Greene Street - Room 605
Augusta, Georgia 30901
706-821-2422
Bid documents may be examined at the office of the Augusta, GA Procurement Department, 530 Greene Street –
Room 605, Augusta, GA 30901. Plans and specifications for the project shall be obtained by all prime,
subcontractors and suppliers exclusively from Augusta Blue Print. The fees for the plans and
specifications which are non-refundable is $75.00.
It is the wish of the Owner that all businesses are given the opportunity to submit on this project. To facilitate this
policy the Owner is providing the opportunity to view plans online (www.augustablue.com) at no charge through
Augusta Blue Print (706 722-6488) beginning Thursday, August 28, 2014. Bidders are cautioned that submitting a
package without Procurement of a complete set are likely to overlook issues of construction phasing, delivery of
goods or services, or coordination with other work that is material to the successful completion of the project.
Bidders are cautioned that acquisition of documents through any other source is not advisable. Acquisition of
documents from unauthorized sources places the bidder at the risk of receiving incomplete or inaccurate
information upon which to base his qualifications.
A Mandatory Pre Bid Conference will be held on Friday, September 19, 2014, @ 11:00 a.m. in the
Procurement Department, 530 Greene Street, Room 200 West.
All questions must be submitted in writing by fax to 706 821-2811 or by email to
procbidandcontract@augustaga.gov to the office of the Procurement Department by Tuesday, September
23, 2014 @ 5:00 p.m. No bid will be accepted by fax, all must be received by mail or hand delivered.
No Bid may be withdrawn for a period of 60 days after time has been called on the date of opening. A 10% Bid
bond is required to be submitted along with the bidders’ qualifications; a 100% performance bond
and a 100% payment bond will be required for award.
Invitation for bids and specifications. An invitation for bids shall be issued by the Procurement Office and shall
include specifications prepared in accordance with Article 4 (Product Specifications), and all contractual terms and
conditions, applicable to the procurement. All specific requirements contained in the invitation to bid
including, but not limited to, the number of copies needed, the timing of the submission, the required
financial data, and any other requirements designated by the Procurement Department are considered
material conditions of the bid which are not waiveable or modifiable by the Procurement Director. All
requests to waive or modify any such material condition shall be submitted through the Procurement Director to
the appropriate committee of the Augusta, Georgia Commission for approval by the Augusta, Georgia
Commission. Please mark BID number on the outside of the envelope.
Bidders are cautioned that acquisition of BID documents through any source other than the office of the
Procurement Department is not advisable. Acquisition of BID documents from unauthorized sources places the
bidder at the risk of receiving incomplete or inaccurate information upon which to base his qualifications.
GERI A. SAMS, Procurement Director
Augusta Chronicle August 28, September 4, 11, 18, 2014
Metro Courier September 3, 2014
Revised: 8/15/2011
Vendors Attachment B
Addendums
1 and 2 E-Verify Number SAVE Form Bid Bond Base Bid Price
BEAM'S CONTRACTING INC.,
15030 ATOMIC RD., BEACH ISLAND, SC 29842 YES YES 167300 YES YES $2,056,953.15
BLAIR CONSTRUCTION
P.O. BOX 770 EVANS, GA 30809 YES YES 224004 YES YES $2,116,593.39
EAGLE UTILITY CONTRACTING INC.,
1350 BRANCH ROAD BISHOP, GA 30621 YES YES 206663 YES YES $2,159,648.40
GEARIG BROTHERS CIVIL WORKERS
P.O. BOX 2684 EVANS, GA 30809 YES YES 226337 YES YES $1,811,949.00
LEGACY WATER GROUP
10120 ROBERT WAY COVINGTON NEWTON GA
30014 YES YES 798569 YES YES $1,989,613.00
JOHN D STEPHENS INC.,
272 HURRICANE SHOALS RD NE
LAWRENCEVILLE GA 30046 YES YES 46876 YES YES $2,185,712.30
Bid Item 14-204
Gordon Highway 24 Inch Water Main Project
For Augusta GA - Utilities Department
Due: Thursday, October 16, 2014 at 3:00 p.m.
Page 1 of 1
Engineering Services Committee Meeting
1/12/2015 1:15 PM
Approve construction contract award in the amount of $1,811,949.00 to Gearing Brothers Civil Workers
for the Gordon Highway 24" Water Main Project. Bid item #14-204.
Department:Augusta Utilities Department
Caption:Approve construction contract award to Gearing Brothers Civil
Workers in the amount of $1,811,949.00 for the Utilities
Department.
Background:The Gordon Highway 24-inch Transmission Water Main project
involves the construction of 6,900 linear feet of 24-inch diameter
ductile iron pipe along Gordon Highway. The water main will run
along the Northside of Gordon Hwy from Barton Chapel Rd to
Jimmy Dyess Pkwy. The construction of this transmission main
will allow the Augusta Utilities Department to supply surface
water from the Highland Avenue Water Treatment Plant into Fort
Gordon and the west area of Richmond County.
Analysis:Gearing Brothers Civil Workers submitted an acceptable bid
package and was the lowest responsive bidder.
Financial Impact:The amount submitted for the construction of this project was
$1,811,949.00.These funds are available from account
512043410-5425110/80310153-5425110
Alternatives:None
Recommendation:It is recommended to award the contract to Gearing Brothers Civil
Workers in the amount of $1,811,949.00
Funds are Available
in the Following
Accounts:
$1,811,949.00 from account 512043410-5425110/80310153-
5425110
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Invitation to Bid
Sealed bids will be received at this office on Wednesday, September 10, 2014 @ 3:00 p.m. for furnishing:
Bid Item 14-194 Highland Avenue Reservoirs Mixers for Utilities Department
Bids will be received by Augusta, GA Commission hereinafter referred to as the OWNER at the offices of:
Geri A. Sams
Procurement Department
530 Greene Street - Room 605
Augusta, Georgia 30901
706-821-2422
Bid documents may be examined at the office of the Augusta, GA Procurement Department, 530 Greene Street –
Room 605, Augusta, GA 30901. Plans and specifications for the project shall be obtained by all prime,
subcontractors and suppliers exclusively from ARC Southern. The fees for the plans and specifications
which are non-refundable is $50.00.
It is the wish of the Owner that all businesses are given the opportunity to submit on this project. To facilitate this
policy the Owner is providing the opportunity to view plans online (www.e-arc.com) at no charge through ARC
Southern (706 821-0405) beginning Thursday, July 31, 2014. Bidders are cautioned that submitting a package
without Procurement of a complete set are likely to overlook issues of construction phasing, delivery of goods or
services, or coordination with other work that is material to the successful completion of the project. Bidders are
cautioned that acquisition of documents through any other source is not advisable. Acquisition of documents from
unauthorized sources places the bidder at the risk of receiving incomplete or inaccurate information upon which to
base his qualifications.
All questions must be submitted in writing by fax to 706 821-2811 or by email to
procbidandcontract@augustaga.gov to the office of the Procurement Department by Friday, August 22,
2014 @ 5:00 p.m. No bid will be accepted by fax, all must be received by mail or hand delivered.
No Bid may be withdrawn for a period of 60 days after time has been called on the date of opening. A 10% Bid
bond is required to be submitted along with the bidders’ qualifications; a 100% performance bond
and a 100% payment bond will be required for award.
Invitation for bids and specifications. An invitation for bids shall be issued by the Procurement Office and shall
include specifications prepared in accordance with Article 4 (Product Specifications), and all contractual terms and
conditions, applicable to the procurement. All specific requirements contained in the invitation to bid
including, but not limited to, the number of copies needed, the timing of the submission, the required
financial data, and any other requirements designated by the Procurement Department are considered
material conditions of the bid which are not waiveable or modifiable by the Procurement Director. All
requests to waive or modify any such material condition shall be submitted through the Procurement Director to
the appropriate committee of the Augusta, Georgia Commission for approval by the Augusta, Georgia
Commission. Please mark BID number on the outside of the envelope.
Bidders are cautioned that acquisition of BID documents through any source other than the office of the
Procurement Department is not advisable. Acquisition of BID documents from unauthorized sources places the
bidder at the risk of receiving incomplete or inaccurate information upon which to base his qualifications.
GERI A. SAMS, Procurement Director
Augusta Chronicle July 31, August 7, 14, 21, 2014
Metro Courier August 6, 2014
Revised: 8/15/2011
UNOFFICIAL
Bid Opening #14-194
Highland Avenue Reservoirs Mixers
For Augusta, GA - Utilities Department
Bid Opening Date:
Wednesday, September 10, 2014 @ 3:00 p.m.
Vendors
Gridbee - Solarbee
Medora Corporation
3225 Highway 22
Dickinson, ND 58601
Attachment B Yes
E-Verify Number 326776
SAVE Form Yes
Bid Bond Yes
Total Amount $238,440.00
Page 1 of 1
Engineering Services Committee Meeting
1/12/2015 1:15 PM
Approve construction contract award in the amount of $238,400.40 to Gridbee / Solarbee for the
Highland Avenue Reservoirs Mixers Project. Bid item #14-194.
Department:Augusta Utilities Department
Caption:Approve construction contract award to Gridbee/Solarbee in the
amount of $238,400.40 for the Utilities Department. Bid 14-194
Background:Raw river water is stored in two reservoirs at the Highland
Avenue Water Treatment Plant. The use of mixers in these
reservoirs will help to maintain the quality of our raw water. They
will also facilitate any pretreatment that needs to occur in order to
eliminate or mitigate the growth of algae or other substances that
adversely impact the taste or odor of our finished drinking water.
The mixers will also help insure the consistency of our water
quality and reduce the potential of having to remove undesirable
compounds once they are formed. The use of solar-powered
mixers has the added advantage of lower installation and operating
cost.
Analysis:Gridbee / Solarbee submitted an acceptable bid package and was
the lowest responsive bidder.
Financial Impact:The amount submitted for the construction of this project was
$238,400.40.These funds are available from account 506043520-
5425110
Alternatives:None
Recommendation:It is recommended to award the contract to Gridbee / Solarbee. in
the amount of $238,400.40
Funds are Available
in the Following
Accounts:
506043520-5425110 from account $238,400.40
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Engineering Services Committee Meeting
1/12/2015 1:15 PM
Downtown Sidewalks, Streets and Medians Clean Up and Maintenance
Department:Clerk of Commission
Caption:Discuss possible solutions for Augusta Richmond County to
provide consistent clean up and maintenance of downtown
sidewalks, streets and medians. (Requested by Commissioner
Davis)
Background:
Analysis:
Financial Impact:
Alternatives:
Recommendation:
Funds are Available
in the Following
Accounts:
REVIEWED AND APPROVED BY:
Engineering Services Committee Meeting
1/12/2015 1:15 PM
Minutes
Department:Clerk of Commission
Caption:Motion to approve the minutes of the Engineering Services
Committee held on December 8, 2014.
Background:
Analysis:
Financial Impact:
Alternatives:
Recommendation:
Funds are Available
in the Following
Accounts:
REVIEWED AND APPROVED BY:
Invitation to Bid
Sealed bids will be received at this office on Friday, October 31, 2014 @ 11:00 a.m. for furnishing:
Bid Item 14-215 Fort Gordon New Water & Sewage Connections Project for Utilities Department
Bids will be received by Augusta, GA Commission hereinafter referred to as the OWNER at the offices of:
Geri A. Sams
Procurement Department
530 Greene Street - Room 605
Augusta, Georgia 30901
706-821-2422
Bid documents may be examined at the office of the Augusta, GA Procurement Department, 530 Greene Street –
Room 605, Augusta, GA 30901. Plans and specifications for the project shall be obtained by all prime,
subcontractors and suppliers exclusively from Augusta Blue Print. The fees for the plans and
specifications which are non-refundable is $25.00.
It is the wish of the Owner that all businesses are given the opportunity to submit on this project. To facilitate this
policy the Owner is providing the opportunity to view plans online (www.augustablue.com) at no charge through
Augusta Blue Print (706 722-6488) beginning Friday, October 10, 2014. Bidders are cautioned that submitting a
package without Procurement of a complete set are likely to overlook issues of construction phasing, delivery of
goods or services, or coordination with other work that is material to the successful completion of the project.
Bidders are cautioned that acquisition of documents through any other source is not advisable. Acquisition of
documents from unauthorized sources places the bidder at the risk of receiving incomplete or inaccurate
information upon which to base his qualifications.
A Mandatory Pre Bid Conference will be held on Tuesday, October 21, 2014,@10:00 a.m. in the
Procurement Department, 530 Greene Street, Room 200 West.
All questions must be submitted in writing by fax to 706 821-2811 or by email to
procbidandcontract@augustaga.gov to the office of the Procurement Department by Thursday, October
23, 2014 @ 5:00 p.m. No bid will be accepted by fax, all must be received by mail or hand delivered.
No Bid may be withdrawn for a period of 60 days after time has been called on the date of opening. A 10% Bid
bond is required to be submitted along with the bidders’ qualifications; a 100% performance bond
and a 100% payment bond will be required for award.
Invitation for bids and specifications. An invitation for bids shall be issued by the Procurement Office and shall
include specifications prepared in accordance with Article 4 (Product Specifications), and all contractual terms and
conditions, applicable to the procurement. All specific requirements contained in the invitation to bid
including, but not limited to, the number of copies needed, the timing of the submission, the required
financial data, and any other requirements designated by the Procurement Department are considered
material conditions of the bid which are not waiveable or modifiable by the Procurement Director. All
requests to waive or modify any such material condition shall be submitted through the Procurement Director to
the appropriate committee of the Augusta, Georgia Commission for approval by the Augusta, Georgia
Commission. Please mark BID number on the outside of the envelope.
Bidders are cautioned that acquisition of BID documents through any source other than the office of the
Procurement Department is not advisable. Acquisition of BID documents from unauthorized sources places the
bidder at the risk of receiving incomplete or inaccurate information upon which to base his qualifications.
GERI A. SAMS, Procurement Director
Revised: 8/15/2011
UNOFFICIAL
VENDORS Attachment
B
BID
BOND
E-Verify
#
SAVE
Form Total
Blair Construction
P. O. Box 770
Evans, GA 30809
YES YES 224004 YES $696,334.89
Contract Management, Inc
1827 Killingsworth
Augusta, GA 30904
YES YES 225306 YES $721,975.75
Total Number Specifications Mailed Out: 4
Mandatory Pre-Bid Conference: 2
Total packages submitted: 2
Total Noncompliant: 0
Bid Opening Bid Item #14-215
Fort Gordon New Water & Sewage
Connections Project
for Augusta, Georgia - Utilities Department
Bid Due: Friday, October 31, 2014 @ 11:00 a.m.
Page 1 of 1
UTILITIES DEPARTMENT
Tom Wiedmeier
Director
MEMORANDUM
Horace Luke
Assistant Director
TO:
F'ROM:
DATE:
SUBJECT:
Geri A. Sams
Tom wiedm"i"d'J
November 412014
Bid Item #14-215 Fort Gordon New Water and Sewage Connections for Utilities Dept.
Bid Opening Date: September 30, 2014 @ I l:00am
We have reviewed the bid tab sheet and submittals received for the above item. I recommended award of bid
Item#14-215 to the lowest responsive bidder: Blair Construction in the amount of $696,334.89.
Cc: Tom Wiedmeier, P.E
Horace Luke
Deanna Davis P.E.
Engineering Division
360 Bay Street, Suite 180 - Augusta, GA 30901
(706) 312-4132 -Pax (706) 312-4133
WWW.AUGUSTAGA.GOV
QUALITY STORM WATER
SOLUTIONS
ATTN: THERON SAPP
437 CAMBRIDGE CIRCLE
MARTINEZ GA 30907
EAGLE UTILITY
ATTN: TONY HIGHFIELD
1350 BRANCH ROAD
BISHOP, GA 30627
BLAIR CONSTRUCTION
ATTN PATRICK DILLARD
PO BOX 770
EVANS, GA 30809
CONTRACT MANAGEMENT INC
ATTN: JAMES WILLIAMS
1827 KILLINGSWORTH
AUGUSTA GA 30904
Bid Item #14-215 Fort Gordon
New Water & Sewage
Connections Project
Mailed 10/8/14
Bid Item #14-215
Fort Gordon New Water & Sewage
Connections Project
for Utilities Department
Bid Due: Fri. 10/31/14 @ 11:00 a.m.
Deanna Davis
Utilities Department
Bay Street
Stanley Aye
Utilities Department
Bay Street
Yvonne Gentry
LSBOP
2ND FLOOR
Municipal Building
PAGE 1 OF 1
Emergency Bid Item #14-211
Lakeside Drive 6 Inch Water Main Project
Emergency
for Utilities Department
Engineering Services Committee Meeting
1/12/2015 1:15 PM
Notification of award for a construction contract to Blair Construction, Inc. for construction of the Fort
Gordon New Water and Sewage Connections under the Task Order Program for Infrastructure RFQ
#13-194 in the amount of $696,334.89. Bid item #14-215
Department:Augusta Utilities Department
Caption:Notification of the award of a contract with Blair Construction,
Inc. for services associated with construction of the Fort Gordon
New Water and Sewage Connections under the Task Order
Program for Infrastructure RFQ #13-194 in the amount of
$696,334.89. Bid item #14-215
Background:The objective of this project is to provide water and sewage
connections on Fort Gordon. This project will consist of multiple
connections of various sizes and installation up to 5,000 LF of
sewer main and 6,150 LF of water main. Some connections to the
existing infrastructure will be upgraded and some connections will
be for new infrastructure throughout the base.
Analysis:Blair Construction, Inc. submitted an acceptable bid package and
was the lowest responsive bidder. The Utilities Department desires
to inform commission of the award of this contract to construct the
Fort Gordon New Water and Sewage Connections under the Task
Order Program for Infrastructure RFQ #13-194 to Blair
Construction, Inc.
Financial Impact:$696,334.89 under account number 507043490-5425410 /
88886666-5425410
Alternatives:No alternatives due to the contract being awarded under the Task
Order Program for Infrastructure RFQ #13-194
Recommendation:We are notifing the commission of the award of a Task Order
contract to Blair Construction, Inc. in the amount of $696,334.89
for the construction of the Fort Gordon New Water and Sewage
Connections Project under the Task Order Program for
Infrastructure RFQ #13-194
Funds are Available
in the Following
Accounts:
$696,334.89 from account 507043490-5425410 / 88886666-
5425410
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission