1. Consider approval of Augusta Utilities Master Plan proposal from
Constantine Engineering with a fee not to exceed $618,338.
Attachments
2. Motion to approve a donated Easement between James P. Helton,
Jr. and Margaret Knapp Helton, as owners, and Augusta, Georgia, as
optionee, in connection with the Fox Spring Road Drainage
Improvement Project, said perpetual easement consists of 0.10 acre
(4,355 sq. ft.) of permanent drainage and utility easement, more or
less, from the property located at 3026 Fox Spring Road, private.
Attachments
3. Motion to approve an Option for the purposes of acquiring an
Easement between Bobby Lenwood Thomas, Jr., as owner, and
Augusta, Georgia, as optionee, in connection with the East Augusta
Roadway and Drainage Improvement Project, said perpetual
easement consists of 0.002 acre (75.26 sq. ft.) of permanent drainage
and utility easement, more or less, and (563.18 sq. ft.) of temporary
construction easement from the property located at 802 Wallace
Street, private, at the purchase price of $150.00.
Attachments
4. Motion to approve an Option for the purposes of acquiring an
Easement between Sherry M. Smith, as owner, and Augusta,
Georgia, as optionee, in connection with the East Augusta Roadway
and Drainage Improvement Project, said perpetual easement consists
of (231.64 sq. ft.) of permanent drainage and utility easement, more
or less, and (408.73 sq. ft.) of temporary construction easement from
the property located at 409 Aiken Street, private, at the purchase
price of $538.00.
Attachments
5. Motion to approve Crosswalk Easement Agreement entered into by
Augusta, Georgia and The Whites Building Condominium
Association, Inc.
Attachments
Engineering Services Committee Meeting
1/9/2012 1:00 PM
Augusta Utilities Master Plan
Department:Utilities
Caption:Consider approval of Augusta Utilities Master Plan proposal from
Constantine Engineering with a fee not to exceed $618,338.
Background:Earlier in 2011, the Commission authorized Utilities to negotiate
with the top rated firm from the qualifications based selection
process for a Master Planning consultant. We were unable to
come to terms with the top rated consultant, and subsequently
entered into negotiations with the second rated firm, Constantine
Engineering. This process has been coordinated with the
Procurement Department. We have developed a mutually
acceptable scope and fee for this effort.
Analysis:The last Utilities Master Plan was completed in 2004; much of the
work identified in that plan has been accomplished. There is work
remaining from that plan that was not completed due to lack of
funding, as well as new needs that have arisen since the 2004 plan
was developed. The Master Planning process will take a
comprehensive look at our system including projected growth,
service delivery, state of existing infrastructure, regulatory outlook
and energy management and conservation. The Constantine team
includes the local firm of ZEL Engineering, a firm with extensive
knowledge of Augusta’s system. Roughly half the work for this
plan will be performed by ZEL. The recently adopted Savannah-
Upper Ogeechee Regional Water Plan calls for all systems to
develop/update local system master plans on a 5-year cycle.
Financial Impact:The work will be performed on a Time and Materials basis not-to-
exceed $618,338. Funding is available in 507043490-
5212999/81100010-5212999.
Alternatives:The Commission could choose not to proceed with the Master
Plan.
Recommendation:We recommend approval of Constantine’s proposal with a not-to-
exceed fee of $618,338.Cover Memo
Item # 1
Funds are Available
in the Following
Accounts:
507043490-5212999/81100010-5212999
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Cover Memo
Item # 1
1
TASK ORDER 1
THIS TASK ORDER IS ISSUED PURSUANT TO THE AGREEMENT FOR CONSULTING SERVICES DATED ____________, 2011, BETWEEN THE CITY OF AUGUSTA,
GEORGIA UTILITIES DEPARTMENT AND CONSTANTINE ENGINEERING, INC., WHICH IS INCORPORATED HEREIN BY THIS REFERENCE, WITH RESPECT TO
Scope of Basic Services
for the
City of Augusta Utilities Department
Water and Wastewater System Master Plan Project
Article A. Purpose:
The purpose of this Task Order is to authorize and direct CONSULTANT (Constantine Engineering, Inc.) to
proceed with professional engineering and technical services for the Water and Wastewater System Master
Plan Project (PROJECT) for the City of Augusta Utilities Department, Augusta, GA (CLIENT). The PROJECT
generally includes the development of a Master Plan to evaluate the present and future needs of the
CLIENT’s water and wastewater systems; develop alternatives for meeting these long-term needs; and
recommendations that the system can implement. The plan shall address water supply, distribution, and
storage and wastewater collection, treatment, and effluent and biosolids management. The activities that are
included are described in “Article B. Scope of Services.”
Article B. Base Scope of Services:
The CONSULTANT agrees to furnish general professional engineering and technical services for the work
related to the study; evaluation; analysis; field testing; alternatives development, and preparation of final
report documents. The PROJECT includes the services required to perform the engineering analysis and
technical services to assess existing water systems; existing wastewater systems; and to prepare a long range
plan to meet growing needs in the CLIENT’s service delivery area. The PROJECT recommendations are
expected to be implemented in phases over defined intervals of time.
The specific Engineering Services that CONSULTANT agrees to furnish to the CLIENT for the PROJECT and
the Specific Work Tasks are presented below.
1. Collect and Review Existing Information and Data
2. Population Projections and Service Delivery Area Expansion Plan
3. Future Water Demand and Wastewater Flow Projections
4. Water and Wastewater System Regulatory Review
5. Water and Wastewater System Energy Management Evaluation
6. Water Systems Evaluation
7. Wastewater Systems Evaluation
8. Fort Gordon Water and Wastewater Systems Evaluation
9. Water and Wastewater System Assessment of Needs
10. Potential Water Supply, Treatment, Storage and Distribution Systems Alternatives
11. Potential Wastewater Treatment and Effluent and Biosolids Management Alternatives
12. Water & Wastewater System Capital Improvement and Implementation Program
13. Workshops, Meetings, and Presentations
14. Intergovernmental Coordination and Community Outreach and Involvement
15. Water and Wastewater Master Plan Deliverable
A detailed description of the scope of services that are proposed for this task is presented below.
Attachment number 1 \nPage 1 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
2
Work Task 1—Collect and Review Existing Information and Data
Work Task 1 involves the collection of data and information that are required to perform assessments of the
CLIENT’s existing facilities and operations; make projections of future water demands and wastewater flows;
and develop alternatives to meet those existing and future CLIENT needs.
1.1 Existing Water and Wastewater Facility and Systems Data
CONSULTANT shall coordinate with the CLIENT to identify and collect information and data, including
electronic data, regarding the CLIENT’S existing water and wastewater utilities. This information may
include previous engineering planning and design documents or reports; capital improvements plan;
financial planning documents; billing records; water and wastewater quality data; water demand and
wastewater flow records; water and wastewater system maps; record drawings of the water and wastewater
facilities; land development plans and permits; topographical surveys of the CLIENT’s facilities; water and
wastewater system modeling data; supervisory control and data acquisition (SCADA) records; Geographical
Information System (GIS) data; and facility operation and maintenance records.
1.2 Local, State, and Federal Regulation Information
CONSULTANT shall identify and collect pertinent existing local, state, and federal regulations regarding the
CLIENT’s water and wastewater systems.
1.3 Review and Summarize Data and Information
CONSULTANT shall review and analyze the information and data collected and shall prepare a summary of
the pertinent data and information to be applied in the planning process. CONSULTANT shall prepare an
initial assessment of the water and wastewater facility information and data needs based on the initial data
set obtained. CONSULTANT shall identify any additional data needs that are required to complete the
assessment of CLIENT’s water and wastewater facilities.
1.4 Additional Data and Information Collection
If needed, CLIENT shall authorize CONSULTANT to obtain the additional data and information as per
Additional Scope Item 12.
CLIENT shall be responsible for any additional data collection costs for items such as field collection of water
and wastewater data; geotechnical data; flow monitoring; laboratory testing; or purchasing of relevant public
documents.
Work Task 2—Population Projections and Service Delivery Area Expansion Plan
In Work Task 2, CONSULTANT shall coordinate with CLIENT to develop population projections within the
CLIENT’s existing and potential future service areas. This information shall be used to develop CLIENT’s
strategy for meeting existing and future water demands and wastewater flows.
2.1 Population Projections
CONSULTANT shall assess the existing data provided by CLIENT regarding historic, current, and future
populations within the CLIENT’s existing and proposed future service area. CONSULTANT shall coordinate
with the CLIENT in order to account for any pending or proposed future land developments, and public,
commercial, or industrial customers. CONSULTANT shall coordinate population projection efforts with
CLIENT’s Rate Study Consultant to ensure consistency of population data between the two studies.
CONSULTANT shall review past population projections used by the CLIENT’s Planning and Zoning
Department.
2.2 Service Area Expansion Plan
CONSULTANT shall coordinate with CLIENT and other stakeholders to collect existing land use mapping
information and data. CONSULTANT shall meet with CLIENT and other stakeholders to develop
projections of future land use and expansions to CLIENT’s service area. Based on input from the CLIENT,
CONSULTANT shall prepare a future service area land use map. This map shall differentiate between the
Attachment number 1 \nPage 2 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
3
existing and future service areas; based on the results of Task 2.1 define the populations to be served within
sub-areas; and define the existing and future land uses for these areas. CONSULTANT shall consider service
area expansions to accommodate potential large water and/or wastewater customers identified by CLIENT,
such as potential re-development of the former Kimberly Clark site, and potential wholesale potable water
service to Burke County via the Highway 25 corridor.
Work Task 3—Future Water Demand and Wastewater Flow Projections
Work Task 3 involves the development of future water demands and wastewater flow projections based on
the projections of population and customer base developed during Work Task 3.
3.1 Water Demand Projections
Once the service area expansion plan has been competed, CONSULTANT shall perform calculations to
project water service demand at appropriate intervals of time that span the 20-year planning period.
CONSULTANT shall account for anticipated future residential, commercial, public and industrial water
needs. CONSULTANT shall assign specific future potential water demands to each of the areas delineated in
the Service Area Expansion Plan. CONSULTANT shall coordinate water demand projection efforts with
CLIENT’s Rate Study Consultant to ensure consistency of population data between the two studies.
3.2 Wastewater Flow Projections
Once the service area expansion plan has been completed, CONSULTANT shall perform calculations to
project wastewater flow at appropriate intervals of time that span the 20-year planning period.
CONSULTANT shall account for anticipated future residential, commercial, public and industrial wastewater
disposal. CONSULTANT shall assign specific future potential wastewater flows to each of the areas
delineated in the Service Area Expansion Plan. CONSULTANT shall coordinate wastewater demand
projection efforts with CLIENT’s Rate Study Consultant to ensure consistency of population data between the
two studies.
Work Task 4—Water and Wastewater Systems Regulatory Review
Work Task 4 involves a review of known, and proposed applicable local, state, and federal regulations that
affect the operation of the CLIENT’s existing, and expanded, water and wastewater systems. A description of
the specific work tasks included in this review is presented below. CONSULTANT shall review existing local,
state, and federal regulations regarding consumptive use of water and wastewater disposal. CONSULTANT
shall review and assess existing and pending regulations, such as the EPD Statewide Water Plan, the
Governor’s Water Contingency Plan, and the Savannah River TMDL, that might affect the development of a
water supply expansion and effluent reuse program in the planning area
4.1. Water System Regulatory Review
In Task 4.1, CONSULTANT will review current federal and state regulations regarding the water supply,
treatment, and distribution systems, including the Safe Drinking Water Act (SDWA) and subsequent
Amendments; consumptive use; the EPD Statewide Water Plan and the Governor’s Water Contingency Plan.
The regulatory information presented in this task shall be based on the most current regulatory literature
published by the U.S. Environmental Protection Agency (EPA) Office of Drinking Water and the American
Water Works Association; as well as literature published by the Georgia Department of Natural Resources
(DNR) Environmental Protection Division (EPD). In addition, it will present CONSULTANT’s
understanding of the anticipated changes in the regulations that may affect the CLIENT’S water system, as
we currently understand them. The section will be organized as follows:
Summary of regulatory effects
Current regulatory outlook
Regulatory review
CONSULTANT will review the rules and regulation included in the 1986 SDWA Amendments, as well as the
following additional rules and regulations:
Attachment number 1 \nPage 3 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
4
Surface Water Treatment Rule (SWTR)
Total Coliform Rule (TCR)
Groundwater Disinfection Rule (GWDR)
Lead and Copper Rule (LCR)
Volatile Organic Chemicals Rule–Phase I (VOCR)
Inorganic Chemical Rule–Phase II
Synthetic Organic Chemical Rule–Phase II
Inorganic Chemical Rule–Phase V
Synthetic Organic Chemical Rule–Phase V
The rules and regulations included in the 1996 SDWA Amendments also will be presented as they are
currently known:
Disinfection/Disinfection By-products Rule (D/DBPR)–Stage I and II
Enhanced Surface Water Treatment Rule (ESWTR) (Interim, Final and Ultimate)
Radionuclides Rule
Arsenic Rule
Sulfate and Perchlorate Rules
Additional regulations that will be reviewed and evaluated include the EPD Statewide Water Plan and the
Governor’s Water Contingency Plan.
4.2. Existing Water System Facility Regulatory Review
In Task 2.4, CONSULTANT will review operational data and information for the previous 12 months for the
existing major water supply, treatment, and distribution systems. CONSULTANT also will perform a site
visit to review the existing water system facilities and will assess the status of the existing major water
supply, treatment, and distribution systems to comply with federal and state regulations, including the
SDWA Amendments. In addition, the task will present CONSULTANT’s understanding of the anticipated
changes in the regulations that may affect the existing systems.
4.3. Water System Regulatory Compliance Assessment of Needs
In Task 4.3, CONSULTANT will develop and present a regulatory compliance assessment of needs for the
water system that will address facility and operational deficiencies and limitations that were identified in 4.1
and 4.2. This assessment of needs will be used in later tasks to develop improvement projects to address the
needs assessment.
4.4. Wastewater System Regulatory Review
In Task 4.4, CONSULTANT will review current federal and state regulations regarding the wastewater
collection, transmission, treatment, and effluent and biosolids management systems. The regulatory
information presented in this task shall be based on the most current regulatory literature published by the
Georgia EPD. In addition, it will present CONSULTANT’s understanding of the anticipated changes in the
regulations that may affect the CLIENT’S wastewater system, as we currently understand them, including
pending regulations, such as the Savannah River Total Maximum Daily Loadings (TMDL) Study and anticipated
nutrient limits in upcoming NPDES permit cycles. The section will be organized as follows:
Summary of regulatory effects
Current regulatory outlook
Regulatory review
4.5. Existing Wastewater System Facility Regulatory Review
In Task 4.5, CONSULTANT will review operational data and information for the previous 12 months for the
existing major wastewater collection, transmission, treatment, and effluent and biosolids management
systems. CONSULTANT also will perform a site visit to review the existing wastewater system facilities and
will assess the status of the existing major wastewater systems to comply with federal and state regulations.
In addition, the task will present CONSULTANT’s understanding of the anticipated changes in the
regulations that may affect the existing systems.
Attachment number 1 \nPage 4 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
5
4.6. Wastewater System Regulatory Compliance Assessment of Needs
In Task 4.6, CONSULTANT will develop and present a regulatory compliance assessment of needs for the
wastewater system that will address facility and operational deficiencies and limitations that were identified
in 4.4 and 4.5. This assessment of needs will be used in later tasks to develop improvement projects to
address the needs assessment.
Work Task 5—Water and Wastewater Systems Energy Management Evaluation
Work Task 5 involves reviewing the CLIENT’s water and wastewater systems to determine alternatives for
optimizing the system’s energy use and to develop an implementable energy management plan. The
CLIENT has recently installed a number of large generators at the major water treatment and wastewater
treatment plants (Hicks, Highland, and Messerly). CONSULTANT shall develop and evaluate feasible
alternative energy management and optimization projects, including:
5.1 Reviewing the CLIENTs program to shave peak energy use during high demand periods using the
generators at the major facilities
5.2 Water pressure zone management via the higher water pressure zones from Highland WTP and the
lower pressure zones from the Hicks WTP
5.3 Off-hour pumping to refill the elevated storage tanks
5.4 Installing variable frequency drives on high service pumps
5.5 Reviewing the CLIENT’s potential energy and maintenance savings from shutting down select
wastewater pump stations during non-peak flow periods.
Work Task 6—Water Systems Evaluation
In Work Task 6, CONSULTANT shall assess the CLIENT’s existing water system facilities and identify needs
for repair, replacement, up-grade and for the construction of new or additional facilities to meet the current
and future needs of the CLIENT’s water system. This assessment includes the water supply, treatment,
storage and distribution facilities and systems.
6.1 Review, Update, and Run, Existing Water Distribution System Hydraulic Model
CONSULTANT shall review and assist the CLIENT to update, and run the existing water distribution system
computerized hydraulic model. In no particular order, CONSULTANT shall:
6.1.1 Review existing map(s), GIS data and SCADA information of the water distribution systems and
assess the existing distribution system hydraulic model to ensure it accurately represents existing
conditions
6.1.2 Review and update the diurnal water demand curves in the model, including historical Average
Day Demand (ADD), Maximum Day Demand (MDD), and Peak Hour Demand (PHD)
6.1.3 Assist CLIENT to automatically allocate parcel water usage from the GIS database to the water
model demand nodes, if possible using the existing GIS and modeling software. If it is not possible
to automatically allocate these data using these systems, CONSULTANT shall assist CLIENT to
update the existing allocations using the current methodology of manual adjustments within the
modeling software
CLIENT shall provide CONSULTANT access and use of CLIENT’s existing H2O Map computerized
hydraulic modeling software for the sole use of the PROJECT and for the duration of the PROJECT.
6.2 Water Distribution System Evaluation
CONSULTANT shall evaluate the capability of the existing distribution system to meet current and projected
water demands using the information and data prepared in previous work tasks and shall analyze the needs
of the existing water distribution systems. In no particular order, CONSULTANT shall:
Attachment number 1 \nPage 5 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
6
6.2.1 Assess existing information and data about the physical condition of the existing water distribution
systems
6.2.2 Using the computerized hydraulic modeling software, perform a capacity analysis of the existing
water distribution systems, to assess the capability and reliability of the water system to meet peak
demands, including fire flow demands; to identify hydraulic deficiencies; to develop
recommendations for improvements; to evaluate the capability and capacity to convey large
volumes of water between individual water production centers, as well as Fort Gordon, for
redundancy; to assess future needs for expansion of the existing distribution systems. This analysis
shall be performed by pressure zones, including:
643 FG
630
597
564
521
500
457
417 north
417 south
330
6.2.3 Assess current operation and maintenance costs that might address:
6.2.3.1 System criticality analysis
6.2.3.2 Water hammer evaluations
6.2.3.3 Water age analysis
6.2.3.4 Tank mixing
6.2.3.5 Unidirectional flushing
6.2.3.6 Energy management
6.2.4 Evaluate the need to upgrade and/or clean small, tuberculated mains in rural areas to support the
daily water demands and to provide fire protection, including the Old Summerville system
6.2.5 Evaluate the need to pig the 16-inch diameter potable water main on Highland Avenue/Wheeless
Road to provide redundancy and two-way flow
6.2.6 Evaluate the need for and potential benefits of a comprehensive cleaning and flushing program for
potable water distribution mains greater than 12-inches in diameter
6.2.7 Develop recommendations for improvement and expansion
6.3 Water Supply System Evaluation
CONSULTANT shall analyze and develop a needs assessment of the existing water supply facilities.
CONSULTANT shall:
6.3.1 Perform a capacity analysis of existing water supply source(s) and facilities
6.3.2 Review water supply needs including impacts from outside issues such as the FERC license
renewal and Augusta Canal regulations
6.3.3 Evaluate the potential for wholesale raw sales and water supply regionalization, including
industrial customers:
6.3.3.1 Marvin-Griffin Road Area
6.3.3.2 Columbia Nitrogen Drive, North of Messerly
Attachment number 1 \nPage 6 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
7
6.3.3.3 Golf Courses, including the Patch, Forest Hills, Augusta National, and Augusta Country
Club
6.3.4 Review the current raw water supply strategy to develop raw water wholesale customers,
including upgrades and/or operational modifications to the Goodrich Street and Pistol Range Road
RWPSs
6.3.5 Review raw water quality
6.3.6 Assess the reliability of the raw water supply facilities to meet peak demands and provide
redundancy between surface and ground water treatment facilities
6.3.7 Perform a physical assessment of the condition of the existing raw water supply facilities
6.3.8 Develop an assessment of needs for the water supply systems
6.4 Water Treatment System Evaluation
CONSULTANT shall analyze and develop a needs assessment of the existing water treatment facilities, and
shall:
6.4.1 Perform a capacity analysis of existing water treatment facilities
6.4.2 Review finished water quality
6.4.3 Perform a physical assessment of the condition of the existing treatment facilities
6.4.4 Review biosolids handling and management practices
6.4.5 Review existing water chemistry laboratory capabilities and assess the need to develop a central
water laboratory for CLIENT’s systems
6.4.6 Assess existing chemical and power consumption rates and costs and other operation and
maintenance costs
6.4.7 Assess the reliability of these facilities to meet peak demands and to provide redundancy between
water treatment facilities
6.4.8 Develop recommendations for additional facilities to meet current and future demands for
improvement, expansion, and optimization
6.5 Water System Storage Capacity and Optimization Evaluation
CONSULTANT shall perform an assessment of existing water storage facilities and the capacity of these
facilities to meet current peak and fire flow demands. CONSULTANT shall:
6.5.1 Review existing information and data available regarding the physical assessment of the existing
storage facilities
6.5.2 Perform an existing storage capacity analysis using the updated hydraulic model of the system and
a review of SCADA trends
6.5.3 Assess deficiencies in the existing storage systems to meet current and future water storage
capacity requirements, including the potential needs for and benefits of remote ground storage
tanks
6.5.4 Assess current operation and maintenance costs
6.6 Water System Operation/Management Tools and Software Optimization Evaluation
CONSULTANT shall evaluate the operations of the overall water system and evaluate opportunities to
improve efficiency system-wide by implementing software upgrades to streamline data management
systems, decision tools currently utilized in water system operations and management, maintenance
management systems, GIS systems, material parts supply automation (construction and maintenance), and
automated work order systems.
Attachment number 1 \nPage 7 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
8
Work Task 7—Wastewater Systems Evaluation
In Work Task 7 CONSULTANT shall assess the CLIENT’s existing wastewater system facilities and identify
needs for repair, replacement, up-grade and or the construction of new or additional facilities to meet the
current and future needs of the CLIENT’s wastewater system. This assessment includes the wastewater
collection, pumping and transmission, treatment, effluent and biosolids management systems.
7.1 Wastewater Pumping and Transmission System Evaluation
CONSULTANT shall assess the existing wastewater pumping and transmission systems to establish the
capacity and capability of these facilities to meet current and future flows. CONSULTANT shall:
7.1.1 Perform a physical assessment of the major pumping stations, including:
Chafee
2nd Street
Arcadia
Butler Creek
Apple Valley
Spirit Creek
Goshen
7.1.2 Collect and review existing pump station equipment design and performance information and
data, including SCADA system data
7.1.3 Coordinate with CLIENT’s staff to develop a plan for the CLIENT to collect field information and
data necessary to verify performance characteristics of the pumping systems. Field tests the
CLIENT may perform may include flow tests, wet well draw downs, and pump run times.
7.1.4 Assess current operation and maintenance costs
7.1.5 Assess deficiencies at the major pump stations with recommendations for improvements
7.2 Review, Update, and Run the Existing Wastewater Collection System Hydraulic Model
CONSULTANT shall review and shall assist the CLIENT to update and run the existing wastewater
collection system computerized hydraulic model only as authorized by CLIENT as Additional Scope Item 11.
7.3 Wastewater Collection System Evaluation
CONSULTANT shall assess the existing wastewater collection systems and the capacity of these facilities to
meet current and future flows. CONSULTANT shall:
7.3.1 Using the computerized hydraulic modeling software, perform a capacity analysis of the existing
wastewater collection systems to identify deficiencies and recommend improvements to meet
current and future needs for the following basins:
Rock
Raes
Crane
East Augusta
Mid-City
Glass Factory Avenue
Rocky
Butler
Spirit Creek
7.3.2 Assess future needs for expansion of the existing collection system service area
7.3.3 Assess existing information and data about the physical condition of the existing collection system
Attachment number 1 \nPage 8 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
9
7.3.4 Evaluate the current and future needs for the Sanitary Sewer Trunk Main Rehabilitation Program
7.3.5 Review and evaluate the existing sanitary sewer policies and ordinances, including the sewer
connection policy
7.3.6 Identify areas that are part of the “Unsewered” Pockets Program and propose recommendations
for improvements
7.3.7 Assess current operation and maintenance costs
7.3.8 Review and assess of CLIENT’s CMOM Program, including:
7.3.8.1 SSO protocols and reporting
7.3.8.2 Maintenance programs
7.3.8.2.1 Cleaning
7.3.8.2.2 CCTV
7.3.8.2.3 Blockages
7.3.8.3 Fats oil and grease (FOG) program (coordinate with the CLIENT’s Watershed
Assessment Consultant)
7.3.8.4 Sewer use ordinances & private sources of I/I
7.3.8.5 Corrosion control program
7.3.8.6 Equipment resources and spare parts
7.3.8.7 Information management system
7.3.8.8 Pump station operations and maintenance procedures
7.3.8.9 Alarms and notifications
7.3.8.10 Root control
7.3.8.11 Spill response plan
7.3.8.12 Condition assessment programs
7.3.8.12.1 MH inspections
7.3.8.12.2 Smoke testing
7.3.8.12.3 CCTV
7.4 Wastewater Treatment Facility, Effluent and Biosolids Management Systems Evaluation
CONSULTANT shall assess existing wastewater treatment, effluent and biosolids management systems,
including:
7.4.1 Assess the capacity of the existing wastewater treatment facilities including the ability of the
existing treatment systems to meet the requirements of the current permits and any known or
anticipated modifications
7.4.2 Perform a physical assessment of the existing wastewater treatment facilities
7.4.3 Assess the additional facilities required to meet current and future wastewater flows
7.4.4 Assess the reliability of the facilities to meet current and future peak flow conditions
7.4.5 Assess the bio-solids production rates and the ability of existing solids handling facilities to process
the bio-solids and the continued use of land application for biosolids management
Attachment number 1 \nPage 9 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
10
7.4.6 Assess the bio-solids quality and alternative management methods including the feasibility of co-
generation using bio-solids and digester gas as a fuel source
7.4.7 Assess the potential for reuse water sales, including production costs and potential retail and
wholesale revenue generation
7.4.8 Assess the potential impact of anticipated effluent ultimate oxygen demand (UOD) requirements as
documented in preliminary NPDES permit modifications that CLIENT has negotiated with GEPD
and EPA in response to the Savannah River TMDL
7.5 Wastewater System Operation/Management Tools and Software Optimization Evaluation
CONSULTANT shall evaluate the operations of the overall wastewater system and evaluate opportunities to
improve efficiency system-wide by implementing software upgrades to streamline data management
systems, decision tools currently utilized in wastewater system operations and management, maintenance
management systems, GIS systems, material parts supply automation (construction and maintenance), and
automated work order systems.
Work Task 8—Fort Gordon Water and Wastewater Systems Evaluation
CONSULTANT shall review the existing Utility Privatization Contract with Fort Gordon and shall
incorporate previously identified Fort Gordon capital improvements projects into CLIENT’s Master Plan,
understanding that the schedule for some Fort Gordon renew and replace (R&R) projects has been altered by
the current Construction Management at Risk (CMAR) program.
Work Task 9—Water and Wastewater System Assessment of Needs
In Work Task 9, CONSULTANT shall analyze the results of evaluations performed in Work Tasks 1 through 8
and summarize the assessment of needs for both the water and wastewater systems.
Work Task 10—Potential Water Supply, Treatment, Storage and Distribution Systems
Alternatives
In Work Task 10, CONSULTANT shall identify, evaluate and develop viable water supply, treatment, storage
and distribution systems alternatives to address the assessment of needs identified in Work Task 9.
CONSULTANT shall develop specific water supply, treatment, storage and distribution alternatives, as
appropriate, to meet the needs of the planning area for the duration of the planning period (Year 2032).
Existing and potential water supplies will be evaluated for future development and consumptive use
permitting, as well as for reliability, redundancy, and wholesale water sales. The viability of available water
treatment technologies will be evaluated and those alternatives that are applicable, technically sound, cost-
effective, and that will be acceptable to the public will be identified. Improvements and expansions to the
water distribution and storage systems will be developed and presented. Individual alternatives may be
organized into alternative water management programs that the CLIENT can implement in a phased process.
Alternative or management programs that are deemed viable for addressing the existing and future water
system needs shall be evaluated.
Order-of-Magnitude Level opinions of estimated capital and non-capital costs (including engineering,
operations and maintenance, etc.) of the alternatives or water management programs shall be developed. The
cost estimates shall be presented as 20-year present worth values.
The CONSULTANT shall evaluate the water management programs to define a recommended program for
managing the CLIENT’s water system needs. This evaluation will address the range of potential capital and
operation/maintenance costs, economic and environmental effects, and regulatory requirements associated
with implementation of the alternative management programs.
The programs will also be ranked and evaluated using other subjective criteria developed through the
workshop process. Evaluation criteria may include:
Water Supply Capacity, Availability
Attachment number 1 \nPage 10 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
11
Future Water Demands
Potential for Future Water Demand Outside the Planning Area
Existing and Future Water Treatment and Storage Facilities
Site Availability for Expanded or New Facilities
Potential Environmental Impacts of Expanded or New Facilities
Capital and Operations/Maintenance Costs and Project Financing
Reliability and Redundancy
Implementation and Permitting Requirements
CONSULTANT shall evaluate issues that will affect the implementation of the alternatives and programs
including reliability and redundancy, financing, and regulatory requirements. It is imperative that the
recommended alternative ensures that continuous and uninterrupted water supply service is available.
CONSULTANT shall consider the effect that natural disasters and mechanical failure might have on
alternatives, as well as reserve capacity to meet peak or emergency demands.
Work Task 11—Potential Wastewater Treatment and Effluent and Biosolids Management
Alternatives
In Work Task 11, CONSULTANT shall identify, evaluate and develop wastewater collection, transmission,
treatment, and disposal alternatives for the CLIENT’s existing and potential future wastewater service areas.
The viability of available technologies will be evaluated and those alternatives that are applicable, technically
sound, cost-effective, and that will be acceptable to the public will be identified. CONSULTANT shall
develop specific wastewater collection, transmission, treatment, and disposal alternatives, as appropriate, to
meet the needs of the planning area for the duration of the planning period (Year 2032). Existing and
potential wastewater collections and transmission system rehabilitation, improvement, and expansion will be
evaluated to meet the current and future wastewater needs, as well as for reliability and redundancy. The
viability of available wastewater treatment and disposal technologies will be evaluated and those alternatives
that are applicable, technically sound, cost-effective, and that will be acceptable to the public will be
identified. Improvements and expansions to the wastewater systems will be developed and presented.
Individual alternatives may be organized into alternative wastewater management programs that the
CLIENT can implement in a phased process. Alternative or management programs that are deemed viable
for addressing the existing and future water system needs shall be evaluated.
Order-of-Magnitude Level opinions of estimated capital and non-capital costs (including engineering,
operations and maintenance, etc.) of the alternatives or wastewater management programs shall be
developed. The cost estimates shall be presented as 20-year present worth values.
The CONSULTANT shall evaluate the wastewater management programs to define a recommended program
for managing the CLIENT’s wastewater system needs. This evaluation will address the range of potential
capital and operation/maintenance costs, economic and environmental effects, and regulatory requirements
associated with implementation of the alternative management programs.
The programs will also be ranked and evaluated using other subjective criteria developed through the
workshop process. Evaluation criteria may include:
Facility siting, phasing, and environmental requirements
Site compatibility with surrounding land use for specific projects
Existing and Future Wastewater Collection System Capacity Availability
Future Wastewater Flows
Potential for Future Wastewater Flows from Outside the Planning Area
Existing and Future Wastewater Treatment and Disposal Facilities
Site Availability for Expanded or New Facilities
Potential Environmental Impacts of Expanded or New Facilities
Capital and Operations/Maintenance Costs and Project Financing
Reliability and Redundancy
Implementation and Permitting Requirements
Attachment number 1 \nPage 11 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
12
CONSULTANT shall evaluate issues that will affect the implementation of the alternatives and programs
including reliability and redundancy, financing, and regulatory requirements. It is imperative that the
recommended alternative ensures that the wastewater collection and transmission systems operate to
continuously convey wastewater flows without preventable SSOs and that the wastewater treatment facilities
operate without interruption. CONSULTANT shall consider the effect that natural disasters and mechanical
failure might have on alternatives, as well as capacity to meet peak or emergency flows.
Work Task 12—Recommended Water & Wastewater System Capital Improvement and
Implementation Program
In Work Task 12, CONSULTANT shall develop a recommended 20-year capital improvements program (CIP)
and implementation schedule for the water and wastewater improvement and expansion alternatives
developed in Work Tasks 10 and 11. The 20-Year CIP will be developed in 5 year implementation phase
increments. Design and construction phase requirements resulting from the recommended program will be
summarized, and their impact on the implementation schedule will be presented. The milestone schedule will
include an estimate of the construction duration of the major components of the recommended program and
of significant auxiliary activities, based on our experience with other comparable projects. An overall
schedule will be developed which will take advantage of construction and financial sequencing; will
accommodate local, state, and federal permitting requirements; and will allow an orderly startup of facilities
as construction contracts are completed. When possible, the schedule will be planned to take advantage of
favorable bidding conditions, such as time of year and timing compared to other major construction projects.
CONSULTANT shall coordinate the results of this evaluation with the contracted CLIENT’s Rate Study
Consultant.
Work Task 13—Workshops, Meetings, and Presentations
In Work Task 13 CONSULTANT shall include time for meetings, workshops, and presentations with the
CLIENT’s representatives, stakeholders and interested parties, representatives of FERC, the Georgia
Environmental Protection Division of the Department of Natural Resources (EPD) and other regulatory
agencies, representatives of Fort Gordon, local residents, and business representatives. This task is intended
to allow the CLIENT and CONSULTANT to meet with potential stakeholders and others to solicit
information and data needed to complete the scope of services.
13.1 Initial Workshop
CONSULTANT shall conduct an initial workshop for the CLIENT and members of the project team. It is
important to have a core group from the CLIENT attend and participate in this workshop to identify CLIENT
and CONSULTANT resources; to discuss PROJECT issues; to establish key PROJECT success factors; to
identify information and data needs; prepare a project schedule; to confirm project goals; to set evaluation
criteria for decision-making; and to establish lines of communication for the duration of the
planning/conceptual design activities. Alternative evaluation criteria such as site selections; costs;
compatibility with future land use; relative ease of implementation; regulatory constraints; water quality; and
overall potential for environmental impacts may also be reviewed.
13.2 Additional Workshops and Meetings
Additional workshops will be scheduled to discuss work task specific issues. The following workshops and
meetings are included in this scope of services:
13.2.1. (8)—Monthly project team workshops
13.2.2. (3)—Collect and Review Existing Information and Data Meetings/Workshops
13.2.3. (2)—Population Projections and Service Delivery Area Expansion Plan Meetings/Workshops
13.2.4. (1)—Future Water Demand and Wastewater Flow Projections Workshop
13.2.5. (2)—Water and Wastewater System Regulatory Review Meetings/Workshops
13.2.6. (1)—Water and Wastewater System Energy Management Evaluation Workshops
13.2.7. (4)—Water Systems Evaluation Meetings/Workshops
13.2.8. (4)—Wastewater Systems Evaluation Meetings/Workshops
13.2.9. (3)—Fort Gordon Water and Wastewater Systems Evaluation Meetings/Workshops
Attachment number 1 \nPage 12 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
13
13.2.10. (2)—Water and Wastewater System Assessment of Needs Meetings/Workshops
13.2.11. (4)—Potential Water Supply, Treatment, Storage and Distribution Systems 6Alternatives
Meetings/Workshops
13.2.12. (4)—Potential Wastewater Treatment and Effluent and Biosolids Management Alternatives
Meetings/Workshops
13.2.13. (2)—Capital Improvement and Implementation Program Meetings/Workshops
13.2.14. (1)—Draft and Final Report Review Meeting with CLIENT
13.2.15. (1)—Public presentation of Final Master Plan to Augusta/Richmond County Commission
Work Task 14—Intergovernmental Coordination and Community Outreach and
Involvement
Work Task 14 includes the work associated with intergovernmental coordination and for community
outreach and involvement meetings and presentations. CONSULTANT shall coordinate with governmental
stakeholders and local agencies, industries, community leaders, and other local and state interested parties to
inform them of the pertinent issues regarding the PROJECT; attend or present briefings to the City Council
and the CLIENT as requested, and provide other necessary intergovernmental coordination and public
involvement assistance during the course of the PROJECT. Additionally, the CONSULTANT shall develop
an internet web page to facilitate communication with the public, outside agencies, consultants, and
subconsultants. Specific services that the CONSULTANT shall perform include:
14.1 Intergovernmental Coordination and Community Outreach and Involvement Meetings and Presentations
Plan and conduct a maximum of 10 coordination meetings with CLIENT staff, interested stakeholders, the
public, and federal, state, and local governmental agencies. The purpose of the workshops will be to
distribute information and data, to review specific deliverables, to develop an understanding of the specific
issues and requirements of the PROJECT, to inform them on the progress of the PROJECT, to resolve issues
and conflicts, adjust goals, further improve the planning process, and to provide public involvement and
outreach. CONSULTANT shall coordinate these meetings and presentations with CLIENT and shall prepare
any meeting summaries.
14.2 Internet Web Page
Develop a website that can be accessed through the CLIENT’s website to provide information on the progress
of the PROJECT to inform the general public.
14.3 Briefings to the City Council and other Governmental Officials
Prepare for and attend a maximum of 4 presentations and a maximum of 20 briefings to CLIENT Officials to
discuss the features and the progress of the PROJECT and the schedule. Such briefings and presentations
shall also be used to facilitate receipt of periodic approvals and policy decisions; and shall be conducted at
various stages of the project. CONSULTANT shall coordinate these meetings and presentations with CLIENT
and shall prepare any meeting summaries.
Work Task 15—Water and Wastewater Master Plan Deliverable
CONSULTANT shall prepare interim draft versions of report sections as each work task is completed. The
interim draft versions will be combined into the following interim report deliverables and submitted to the
CLIENT for review and comments. CONSULTANT shall provide 1 electronic copy in Adobe PDF Format
and 10 hardcopies of the interim draft deliverables to the CLIENT.
15.1 Interim Deliverable 1 (Sections 1, 2, and 3)
15.1.1. Section 1—Introduction and Description of existing Water and Wastewater Systems
15.1.2. Section 2—Population Projections and Service Delivery Area Expansion Plan
15.1.3. Section 3—Future Water Demand and Wastewater Flow Projections
15.2 Interim Deliverable 2 (Section 4)
Attachment number 1 \nPage 13 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
14
15.2.1. Section 4—Water and Wastewater System Regulatory Review
15.3 Interim Deliverable 3 (Sections 5, 6, 7, 8, and 9)
15.3.1. Section 5—Water and Wastewater System Energy Management Evaluation
15.3.2. Section 6—Water Systems Evaluation
15.3.3. Section 7—Wastewater Systems Evaluation
15.3.4. Section 8—Fort Gordon Water and Wastewater Systems Evaluation
15.3.5. Section 9—Water and Wastewater System Assessment of Needs
15.4 Interim Deliverable 4 (Sections 10 and 11)
15.4.1. Section 10 —Potential Water Supply, Treatment, Storage and Distribution Systems Alternatives
15.4.2. Section 11 —Potential Wastewater Treatment and Effluent and Biosolids Management Alternatives
15.5 Draft Master Plan Report
CONSULTANT shall combine the revised interim deliverables listed above with the draft sections that
present the Executive Summary and Section 12—Water & Wastewater System Capital Improvement and
Implementation Program into a draft copy of the final report. This draft report shall presents the details of
the engineering evaluations performed, the potential environmental impacts, the alternative water and
wastewater programs evaluated, the recommended water and wastewater programs to be developed, the
capital funding requirements; and an implementation and schedule. The draft report shall be reviewed by
CONSULTANT quality control personnel and designated CLIENT staff. CONSULTANT shall present the
draft report to the CLIENT at a workshop or public meeting and provide 1 electronic copy in Adobe PDF
Format and 10 hardcopies of the draft report to the CLIENT.
15.6 Final Master Plan Report
Following this QC review of the draft report, CONSULTANT shall adjudicate any comments and finalize the
report and present it to the CLIENT at a workshop or public meeting and provide 1 electronic copy in Adobe
PDF Format and 10 hardcopies of the final report to the CLIENT.
Additional Scope Items
The following services are not included as part of this base scope of services and would be performed only as
authorized by the CLIENT. Authorization to proceed would be in the form of a written authorization from
CLIENT.
Add. 1- Purchase of additional software licenses for CLIENT to perform water/sewer system modeling
Add. 2- Sewer system model conversion from MOUSE to SWMM
Add. 3- Training of CLIENT on the new Sewer System modeling software
Add. 4- Field services for water and sewer system modeling data acquisition, including:
Add. 4.1- Flow monitoring
Add. 4.2- Surveying, mapping, or GIS services
Add. 4.3- Manhole inspections
Add. 4.4- Fire hydrant flow/pressure tests
Add. 4.5- Pump station draw-downs or flow/pressure tests
Add. 5- Permitting or design services, construction services or resident observation services for
improvements or modifications to facilities
Add. 6- Financial services for rate studies or adjustments to the CLIENT’s rate structure
Add. 7- Development of operation or maintenance manuals
Attachment number 1 \nPage 14 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
15
Add. 8- Provide 40 hours of onsite training of CLIENT’s staff in the practical application of the hydraulic
model in the routine operation and evaluation of the CLIENT’s water distribution system.
(Basic/advanced training in the H2O Map software is not included in this task. )
Add. 9- Coordinate with CLIENT’s leak detection consultant
Add. 10- Evaluate the existing automated metering replacement program
Add. 11- Review, Update, and Run the Existing Wastewater Collection System Hydraulic Model
Add. 11.1- Review existing map(s), GIS data and SCADA information of the wastewater
collection systems and assess the existing collection system hydraulic model to
ensure it accurately represents existing conditions
Add. 11.2- Assess existing flow monitoring information
Add. 11.3- Assess the inflow and infiltration component of existing wastewater flows (peaking
factors)
Add. 11.4- Assess the needs and benefits of converting the existing MOUSE collection system
hydraulic model to SWMM
Add. 11.5- Assess changes to the wastewater collection system since the model was created and
calibrated and needed updates to the model to accurately simulate current conditions
Add. 11.6- Identify the need for flow monitoring at select locations within the collection system
Add. 11.7- Assist the CLIENT to perform limited calibration and testing of the up-dated
hydraulic model
Add. 11.8- Provide 40 hours of onsite training of CLIENT’s staff in the practical application of
the hydraulic model in the routine operation and evaluation of the CLIENT’s
wastewater collection system.
Basic/advanced training in the existing or any new modeling software is not included in this
task.
CLIENT shall provide CONSULTANT access and use of CLIENT’s existing MOUSE, and
SWMM, computerized hydraulic modeling software for the sole use of the PROJECT
and for the duration of the PROJECT.
Add. 12- Additional Data and Information Collection
Add. 13- Client’s $20,000 Contingency Allowance (scope to be determined)
Article C. Compensation Provisions:
As compensation for providing the scope of services described within this Task Order, CLIENT shall pay
CONSULTANT the Lump Sum Amount of $598,338.00, in accordance with Section 5 of the Master Services
Agreement. The Lump Sum Amount presented above table was developed from estimates of the level of
effort required to perform the proposed services based on CONSULTANTS experience and engineering
judgment.
If CLIENT authorizes CONSULTANT in writing to proceed with Additional Scope Items, CLIENT shall pay
CONSULTANT the Lump Sum Amounts listed below:
Add. 1 Scope and fee to be determined
Add. 2 $27,760
Attachment number 1 \nPage 15 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
16
Add. 3 $23,180
Add. 4 $ 68,260
Add. 5 Scope and fee to be determined
Add. 6 Scope and fee to be determined
Add. 7 Scope and fee to be determined
Add. 8 $8,060
Add. 9 $3,300
Add. 10 $2,200
Add. 11 $34,440
Add. 12 $6,680
Add. 13 $20,000
Article D. Period of Service:
The schedule for the Project within this Task Order is as follows:
Authorization to Proceed February 1, 2012
Termination of Task Order February 1, 2013
Article E. Authorized Representatives:
The Authorized Representatives designated below are authorized to act with respect to this Task Order.
Communications between the parties shall be through the Authorized Representatives:
For CLIENT For CONSULTANT
Name: Tom Wiedmeier, P.E.
Director
Name: James P. Kizer, Jr., P.E.
President
Address: City of Augusta Utilities Department
360 Bay Street
Augusta, GA 30901-1546
Address: Constantine Engineering, Inc.
2004 Lewis Turner Boulevard, Suite B
Fort Walton Beach, FL 32547
Telephone: 706.312.4160 Telephone: 850.244.5800
Email: twiedmeier@augustaga.gov Email: jkizer@tcgeng.com
Article F. Authorization:
Accepted for the CLIENT by: Offered for CONSULTANT by:
Attachment number 1 \nPage 16 of 17
Item # 1
TASK ORDER 1─ CITY OF AUGUSTA, GA UTILITIES DEPARTMENT
WATER AND WASTEWATER MASTER PLAN PROJECT
17
Name Name
Title Title
Date Date
*************** End ***************
Attachment number 1 \nPage 17 of 17
Item # 1
Augusta Utilities Department Water and Wastewater System Master Plan
Preliminary Cost Estimate
Description
Work Task 1—Collect and Review Existing Information and Data 402 40,610.00$ 12,300$ 28,310$ 40,610$
1.1 Existing Water and Wastewater Facility and Systems Data 204 20,730.00$ 4,380$ 16,350$ 20,730$
1.2 Local, State, and Federal Regulation Information 80 8,440.00$ 3,960$ 4,480$ 8,440$
1.3 Review and Summarize Data and Information 118 11,440.00$ 3,960$ 7,480$ 11,440$
1.4 Additional Data and Information Collection ‐ ‐$ ‐$ ‐$ ‐$
Work Task 2—Population Projections and Service Delivery Area Expansion Plan 133 14,010.00$ 5,230$ 8,780$ 14,010$
2.1 Population Projections 49 5,230.00$ 5,230$ ‐$ 5,230$
2.2 Service Area Expansion Plan 84 8,780.00$ ‐$ 8,780$ 8,780$
Work Task 3—Future Water Demand and Wastewater Flow Projections 209 20,910.00$ 13,550$ 7,360$ 20,910$
3.1 Water Demand Projections 117 11,930.00$ 7,770$ 4,160$ 11,930$
3.2 Wastewater Flow Projections 92 8,980.00$ 5,780$ 3,200$ 8,980$
Work Task 4—Water and Wastewater Systems Regulatory Review 160 20,040.00$ 9,960$ 10,080$ 20,040$
4.1. Water System Regulatory Review 40 5,100.00$ 3,420$ 1,680$ 5,100$
4.2. Existing Water System Facility Regulatory Review 24 3,060.00$ 1,380$ 1,680$ 3,060$
4.3. Water System Regulatory Compliance Assessment of Needs 24 3,060.00$ 1,380$ 1,680$ 3,060$
4.4. Wastewater System Regulatory Review 24 2,940.00$ 1,260$ 1,680$ 2,940$
4.5. Existing Wastewater System Facility Regulatory Review 24 2,940.00$ 1,260$ 1,680$ 2,940$
4.6. Wastewater System Regulatory Compliance Assessment of Needs 24 2,940.00$ 1,260$ 1,680$ 2,940$
Work Task 5—Water and Wastewater Systems Energy Management Evaluation 28 3,420.00$ 3,420$ ‐$ 3,420$
Work Task 6—Water Systems Evaluation 1,378 171,145.00$ 62,345$ 108,800$ 171,145$
6.1 Review, Update, and Run, Existing Water Distribution System Hydraulic Model ‐ ‐$ ‐$ ‐$ ‐$
6.1.1 Review and assess existing distribution system hydraulic model for accuracy 47 5,765.00$ 2,565$ 3,200$ 5,765$
6.1.2 Review and update the diurnal water demand curves 44 5,360.00$ 2,160$ 3,200$ 5,360$
6.1.3 Assist CLIENT to automatically allocate parcel water usage into modeling software 78 9,950.00$ 2,700$ 7,250$ 9,950$
6.1.4 Provide 40 hours of onsite training of CLIENT’s staff in the practical application of the hydraulic model ‐ ‐$ ‐$ ‐$ ‐$
6.2 Water Distribution System Evaluation
6.2.1 Assess existing information and data about the physical condition of the existing water distribution systems 40 4,480.00$ 2,700$ 1,780$ 4,480$
6.2.2 Perform a capacity analysis of the existing water distribution systems 44 4,900.00$ 2,160$ 2,740$ 4,900$
6.2.3 Coordinate with CLIENT’s leak detection consultant ‐ ‐$ ‐$ ‐$ ‐$
6.2.4 Evaluate the existing automated metering replacement program ‐ ‐$ ‐$ ‐$ ‐$
6.2.5 Assess current operation and maintenance costs that might address:20 1,900.00$ 1,080$ 820$ 1,900$
6.2.6 Evaluate the need to upgrade small/tuberculated mains in rural areas 28 2,980.00$ 2,160$ 820$ 2,980$
6.2.7 Develop recommendations for improvement and expansion 62 7,980.00$ 2,160$ 5,820$ 7,980$
6.3 Water Supply System Evaluation ‐ ‐$ ‐$ ‐$
6.3.1 Perform a capacity analysis of existing water supply source(s) and facilities 29 3,780.00$ 1,350$ 2,430$ 3,780$
6.3.2 Review water supply needs including impacts from outside issues such as the FERC license renewal and Augusta Canal regulations 31 3,910.00$ 480$ 3,430$ 3,910$
6.3.3 Evaluate the potential for wholesale raw sales and water supply regionalization, including industrial customers:51 6,300.00$ 960$ 5,340$ 6,300$
6.3.4 Review the current raw water supply strategy 28 3,420.00$ 960$ 2,460$ 3,420$
6.3.5 Review raw water quality 20 2,400.00$ 480$ 1,920$ 2,400$
6.3.6 Assess the reliability of the raw water supply facilities 32 3,960.00$ 540$ 3,420$ 3,960$
6.3.7 Perform a physical assessment of the condition of the existing raw water supply facilities 44 5,460.00$ 2,040$ 3,420$ 5,460$
6.3.8 Develop an assessment of needs for the water supply systems 56 6,940.00$ 1,500$ 5,440$ 6,940$
Constantine ZEL Total
Total Engineering
Hours Total Labor Cost
At
t
a
c
h
m
e
n
t
n
u
m
b
e
r
2
\
n
P
a
g
e
1
o
f
4
It
e
m
#
1
Augusta Utilities Department Water and Wastewater System Master Plan
Preliminary Cost Estimate
Description
Constantine ZEL Total
Total Engineering
Hours Total Labor Cost
6.4 Water Treatment System Evaluation ‐ ‐$ ‐$ ‐$ ‐$
6.4.1 Perform a capacity analysis of existing water treatment facilities 28 3,420.00$ 1,620$ 1,800$ 3,420$
6.4.2 Review of finished water quality 28 3,420.00$ 1,620$ 1,800$ 3,420$
6.4.3 Perform a physical assessment of the condition of the existing treatment facilities 56 7,200.00$ 1,620$ 5,580$ 7,200$
6.4.4 Review solids handling and disposal practices 56 7,200.00$ 1,620$ 5,580$ 7,200$
6.4.5 Review existing water chemistry laboratory capabilities and assess the need to develop a central water laboratory for CLIENT’s systems 24 2,880.00$ 1,350$ 1,530$ 2,880$
6.4.6 Assess existing chemical and power consumption rates and costs and other operation and maintenance costs 44 5,580.00$ 2,700$ 2,880$ 5,580$
6.4.7 Assess the reliability of these facilities to meet peak demands and to provide redundancy between water treatment facilities 124 16,440.00$ 7,140$ 9,300$ 16,440$
6.4.8 Develop recommendations for additional facilities to meet current and future demands for improvement, expansion, and optimization 132 17,440.00$ 7,140$ 10,300$ 17,440$
6.5 Water System Storage Capacity and Optimization Evaluation
6.5.1 Review existing information and data available regarding the physical assessment of the existing storage facilities 104 12,180.00$ 2,580$ 9,600$ 12,180$
6.5.2 Perform an existing storage capacity analysis using the updated hydraulic model of the system and a review of SCADA trends 44 5,580.00$ 2,340$ 3,240$ 5,580$
6.5.3 Assess deficiencies in the existing storage systems to meet current and future water storage capacity requirements 32 3,880.00$ 1,800$ 2,080$ 3,880$
6.5.4 Assess current operation and maintenance costs 28 3,420.00$ 1,800$ 1,620$ 3,420$
6.6 Water System Operation/Management Tools and Software Optimization Evaluation 24 3,020.00$ 3,020$ ‐$ 3,020$
Work Task 7—Wastewater Systems Evaluation 924 110,680.00$ 64,360$ 46,320$ 110,680$
7.1 Wastewater Pumping and Transmission System Evaluation
7.1.1 Perform a physical assessment of the major pumping stations, including:56 6,600.00$ 4,060$ 2,540$ 6,600$
7.1.2 Collect and review existing pump station equipment design and performance information and data, including SCADA system data 44 4,900.00$ 2,860$ 2,040$ 4,900$
7.1.3 Coordinate with CLIENT’s staff to develop a plan for the CLIENT to collect field information and data 44 5,360.00$ 3,780$ 1,580$ 5,360$
7.1.4 Assess current operation and maintenance costs 28 3,280.00$ 1,200$ 2,080$ 3,280$
7.1.5 Assess deficiencies at the major pump stations with recommendations for improvements 44 5,580.00$ 4,500$ 1,080$ 5,580$
7.2 Review, Update, and Run, Existing Wastewater Collection System Hydraulic Model ‐ ‐$ ‐$ ‐$
7.2.1 Review and assess the existing collection system hydraulic model for accuracy ‐ ‐$ ‐$ ‐$ ‐$
7.2.2 Assess existing flow monitoring information ‐ ‐$ ‐$ ‐$ ‐$
7.2.3 Assess the inflow and infiltration component of existing wastewater flows (peaking factors)‐ ‐$ ‐$ ‐$ ‐$
7.2.4 Assess the needs and benefits of converting the existing MOUSE collection system hydraulic model to SWMM ‐ ‐$ ‐$ ‐$ ‐$
7.2.5 Assess changes to the wastewater collection system since the model was created ‐ ‐$ ‐$ ‐$ ‐$
7.2.6 Identify the need for flow monitoring at select locations within the collection system ‐ ‐$ ‐$ ‐$ ‐$
7.2.7 Assist the CLIENT to perform limited calibration and testing of the up‐dated hydraulic model ‐ ‐$ ‐$ ‐$ ‐$
7.2.8 Provide 40 hours of onsite training of CLIENT’s staff in the practical application of the hydraulic model ‐ ‐$ ‐$ ‐$ ‐$
7.3 Wastewater Collection System Evaluation ‐ ‐$ ‐$ ‐$
7.3.1 Perform a capacity analysis of the existing wastewater collection systems 44 5,580.00$ 3,420$ 2,160$ 5,580$
7.3.2 Assess future needs for expansion of the existing collection system service area 66 8,370.00$ 5,460$ 2,910$ 8,370$
7.3.3 Assess existing information and data about the physical condition of the existing collection system 60 7,280.00$ 2,700$ 4,580$ 7,280$
7.3.4 Evaluate the current and future needs for the Sanitary Sewer Trunk Main Rehabilitation Program 36 4,320.00$ 2,700$ 1,620$ 4,320$
7.3.5 Review and evaluate the existing sanitary sewer policies and ordinances, including the sewer connection policy 20 2,460.00$ 1,380$ 1,080$ 2,460$
7.3.6 Identify areas that are part of the “Unsewered” Pockets Program and propose recommendations for improvements 24 2,580.00$ 720$ 1,860$ 2,580$
7.3.7 Assess current operation and maintenance costs 28 3,100.00$ 1,140$ 1,960$ 3,100$
7.3.8 Review and assess of CLIENT’s CMOM Program 24 2,760.00$ 1,140$ 1,620$ 2,760$
7.4 Wastewater Treatment Facility, Effluent and Biosolids Disposal Systems Evaluation ‐ ‐$ ‐$ ‐$
7.4.1 Assess the capacity of the existing wastewater treatment facilities to meet the requirements of the permits 88 11,200.00$ 7,340$ 3,860$ 11,200$
7.4.2 Perform a physical assessment of the existing wastewater treatment facilities 56 6,600.00$ 3,440$ 3,160$ 6,600$
7.4.3 Assess the additional facilities required to meet current and future wastewater flows 40 4,840.00$ 2,540$ 2,300$ 4,840$
7.4.4 Assess the reliability of the facilities to meet current and future peak flow conditions 40 4,480.00$ 2,360$ 2,120$ 4,480$
At
t
a
c
h
m
e
n
t
n
u
m
b
e
r
2
\
n
P
a
g
e
2
o
f
4
It
e
m
#
1
Augusta Utilities Department Water and Wastewater System Master Plan
Preliminary Cost Estimate
Description
Constantine ZEL Total
Total Engineering
Hours Total Labor Cost
7.4.5 Assess the bio‐solids production rates and the existing solids handling and disposal facilities and the continued use of land application for disposal 54 6,350.00$ 3,440$ 2,910$ 6,350$
7.4.6 Assess the bio‐solids quality and alternative methods of disposal including co‐generation using digester gas as a fuel source 48 5,600.00$ 3,440$ 2,160$ 5,600$
7.4.7 Assess the potential for reuse water sales, including production costs and potential retail and wholesale revenue generation 36 3,980.00$ 2,360$ 1,620$ 3,980$
7.4.8 Assess the potential impact that the Savannah River TMDL could have on effluent ultimate oxygen demand (UOD) requirements 20 2,440.00$ 1,360$ 1,080$ 2,440$
7.5 Wastewater System Operation/Management Tools and Software Optimization Evaluation 24 3,020.00$ 3,020$ ‐$ 3,020$
Work Task 8—Fort Gordon Water and Wastewater Systems Evaluation 76 9,640.00$ 4,800$ 4,840$ 9,640$
Work Task 9—Water and Wastewater System Assessment of Needs 67 7,855.00$ 3,405$ 4,450$ 7,855$
Work Task 10—Potential Water Supply, Treatment, Storage and Distribution Systems Alternatives 88 10,920.00$ 7,080$ 3,840$ 10,920$
Work Task 11—Potential Wastewater Treatment and Effluent and Biosolids Disposal Alternatives 97 12,195.00$ 8,955$ 3,240$ 12,195$
Work Task 12—Recommended Water & Wastewater System Capital Improvement and Implementation Program 231 29,420.00$ 18,360$ 11,060$ 29,420$
Work Task 13—Workshops, Meetings, and Presentations 247 31,605.00$ 14,055$ 17,550$ 31,605$
13.1 Initial Workshop 48 5,960.00$ 3,570$ 2,390$ 5,960$
13.2 Additional Workshops and Meetings ‐ ‐$ ‐$ ‐$
13.2.1 (8)—Monthly project team workshops 25 3,350.00$ 1,815$ 1,535$ 3,350$
13.2.2 (3)—Collect and Review Existing Information and Data Meetings/Workshops 11 1,400.00$ 540$ 860$ 1,400$
13.2.3 (2)—Population Projections and Service Delivery Area Expansion Plan Meetings/Workshops 7 860.00$ 270$ 590$ 860$
13.2.4 (1)—Future Water Demand and Wastewater Flow Projections Workshop 7 890.00$ 435$ 455$ 890$
13.2.5 (2)—Water and Wastewater System Regulatory Review Meetings/Workshops 7 860.00$ 270$ 590$ 860$
13.2.6 (1)—Water and Wastewater System Energy Management Evaluation Workshops 5 590.00$ 135$ 455$ 590$
13.2.7 (4)—Water Systems Evaluation Meetings/Workshops 31 3,985.00$ 975$ 3,010$ 3,985$
13.2.8 (4)—Wastewater Systems Evaluation Meetings/Workshops 27 3,430.00$ 975$ 2,455$ 3,430$
13.2.9 (3)—Fort Gordon Water and Wastewater Systems Evaluation Meetings/Workshops 12 1,580.00$ 855$ 725$ 1,580$
13.2.10 (2)—Water and Wastewater System Assessment of Needs Meetings/Workshops 12 1,580.00$ 855$ 725$ 1,580$
13.2.11 (4)—Potential Water Supply, Treatment, Storage and Distribution Systems 6Alternatives Meetings/Workshops 17 2,240.00$ 1,110$ 1,130$ 2,240$
13.2.12 (4)—Potential Wastewater Treatment and Effluent and Biosolids Disposal Alternatives Meetings/Workshops 17 2,240.00$ 1,110$ 1,130$ 2,240$
13.2.13 (2)—Capital Improvement and Implementation Program Meetings/Workshops 9 1,160.00$ 570$ 590$ 1,160$
13.2.14 (1)—Draft and Final Report Review Meeting with CLIENT 6 740.00$ 285$ 455$ 740$
13.2.15 (1)—Public presentation of Final Master Plan to Augusta/Richmond County Commission 6 740.00$ 285$ 455$ 740$
Work Task 14—Intergovernmental Coordination and Community Outreach and Involvement 270 29,015.00$ 4,905$ 24,110$ 29,015$
14.1 Intergovernmental Coordination and Community Outreach and Involvement Meetings and Presentations 84 8,240.00$ 690$ 7,550$ 8,240$
14.2 Internet Web Page 104 10,840.00$ 3,330$ 7,510$ 10,840$
14.3 Briefings to the City Council and other Governmental Officials 82 9,935.00$ 885$ 9,050$ 9,935$
Work Task 15—Water and Wastewater Master Plan Deliverable 593 63,860.00$ 36,130$ 27,730$ 63,860$
15.1 Interim Deliverable 1 (Sections 1, 2, and 3) 2 90.00$ 90$ ‐$ 90$
15.1.1. Section 1—Introduction and Description of existing Water and Wastewater Systems 22 2,560.00$ 1,290$ 1,270$ 2,560$
15.1.2. Section 2—Population Projections and Service Delivery Area Expansion Plan 31 3,670.00$ 2,400$ 1,270$ 3,670$
15.1.3. Section 3—Future Water Demand and Wastewater Flow Projections 22 2,440.00$ 1,170$ 1,270$ 2,440$
15.2 Interim Deliverable 2 (Section 4) ‐ ‐$ ‐$ ‐$
15.2.1. Section 4—Water and Wastewater System Regulatory Review 30 3,370.00$ 1,170$ 2,200$ 3,370$
15.3 Interim Deliverable 3 (Sections 5, 6, 7, 8, and 9)‐ ‐$ ‐$ ‐$
15.3.1. Section 5—Water and Wastewater System Energy Management Evaluation 36 4,030.00$ 2,850$ 1,180$ 4,030$
15.3.2. Section 6—Water Systems Evaluation 42 4,820.00$ 2,850$ 1,970$ 4,820$
15.3.3. Section 7—Wastewater Systems Evaluation 42 4,700.00$ 2,730$ 1,970$ 4,700$
15.3.4. Section 8—Fort Gordon Water and Wastewater Systems Evaluation 44 4,940.00$ 3,810$ 1,130$ 4,940$
At
t
a
c
h
m
e
n
t
n
u
m
b
e
r
2
\
n
P
a
g
e
3
o
f
4
It
e
m
#
1
Augusta Utilities Department Water and Wastewater System Master Plan
Preliminary Cost Estimate
Description
Constantine ZEL Total
Total Engineering
Hours Total Labor Cost
15.3.5. Section 9—Water and Wastewater System Assessment of Needs 38 4,280.00$ 2,310$ 1,970$ 4,280$
15.4 Interim Deliverable 4 (Sections 10 and 11) ‐ ‐$ ‐$ ‐$
15.4.1. Section 10 —Potential Water Supply, Treatment, Storage and Distribution Systems Alternatives 62 6,010.00$ 4,640$ 1,370$ 6,010$
15.4.2. Section 11 —Potential Wastewater Treatment and Effluent and Biosolids Disposal Alternatives 62 6,010.00$ 4,640$ 1,370$ 6,010$
15.5 Draft Master Plan Report 92 10,300.00$ 3,600$ 6,700$ 10,300$
15.6 Final Master Plan Report 68 6,640.00$ 2,580$ 4,060$ 6,640$
4,569 575,325$ 268,855$ 306,470$ 575,325$
47% 53%
Subcontractor Markup (0%)‐$ ‐$
Total Labor Costs 575,325$ 575,325$
Expenses (4%) 23,013$ 23,013$
Total 598,338$ 598,338$
Additional Scope Items 1654 194,100$
ADD 1. Purchase of additional software licenses for CLIENT to perform water/sewer system modeling ‐ ‐$
ADD 2. Sewer system model conversion from MOUSE to SWMM 292 27,760$
ADD 3. Training of CLIENT on the new Sewer System modeling software 228 23,380$
ADD 4. Field services for water and sewer system modeling data acquisition, including:664 68,260$
ADD 4.1. Flow monitoring 156 19,000$
ADD 4.2. Surveying, mapping, or GIS services 240 15,660$
ADD 4.3. Manhole inspections 168 20,620$
ADD 4.4. Fire hydrant flow/pressure tests 24 2,980$
ADD 4.5. Pump station draw‐downs or flow/pressure tests 76 10,000$
ADD 5. Permitting or design services, construction services or resident observation services for improvements or modifications to facilities (scope and fee to be determined)‐ ‐$
ADD 6. Financial services for rate studies or adjustments to the CLIENT’s rate structure (scope and fee to be determined)‐ ‐$
ADD 7. Development of operation or maintenance manuals (scope and fee to be determined)‐ ‐$
ADD 8. Provide 40 hours of onsite training of CLIENT’s staff in the practical application of the water system hydraulic model 64 8,060$
ADD 9. Coordinate with CLIENT’s leak detection consultant 32 3,300$
ADD 10. Evaluate the existing automated metering replacement program 22 2,220$
ADD 11. Review, Update, and Run, Existing Wastewater Collection System Hydraulic Model 280 34,440$
ADD 11.1. Review existing map(s), GIS data and SCADA information of the wastewater collection systems and assess the existing collection system hydraulic model to ensure it
accurately represents existing conditions 36 4,500$
ADD 11.2. Assess existing flow monitoring information 36 4,320$
ADD 11.3. Assess the inflow and infiltration component of existing wastewater flows (peaking factors)36 4,620$
ADD 11.4. Assess the needs and benefits of converting the existing MOUSE collection system hydraulic model to SWMM 16 1,800$
ADD 11.5. Assess changes to the wastewater collection system since the model was created and calibrated and needed updates to the model to accurately simulate current
conditions 44 5,580$
ADD 11.6. Identify the need for flow monitoring at select locations within the collection system 12 1,260$
ADD 11.7. Assist the CLIENT to perform limited calibration and testing of the up‐dated hydraulic model 36 4,380$
ADD 11.8. Provide 40 hours of onsite training of CLIENT’s staff in the practical application of the hydraulic model 64 7,980$
ADD 12. Additional Data and Information Collection 72 6,680$
ADD 13. Client's $20,000 Contingency Allowance (scope to be determined)‐ 20,000$
TOTALS
At
t
a
c
h
m
e
n
t
n
u
m
b
e
r
2
\
n
P
a
g
e
4
o
f
4
It
e
m
#
1
REQUEST FOR QUALIFICATIONS
Request for Qualifications will be received at this office until Wednesday, January 12, 2011 @ 3:00 p.m. FOR
FURNISHING:
RFQ Item #11-054 Water and Wastewater System Master Plan for Utilities Department
RFQ Item #11-055 Utility Business Plan for Utilities Department
RFQ Item #11-056 Water and Wastewater Rate Study for Utilities Department
RFQ Item #11-059 Watershed Assessment/Source Water Assessment Plan for Utilities
Department
RFQ Item #11-077 Emergency Response Plan for Utilities Department
RFQ Item #11-080 Leak Detection Study for Utilities Department
RFQs will be received by: The Augusta Commission hereinafter referred to as the OWNER at the offices of:
Geri A. Sams, Director
Augusta Procurement Department
530 Greene Street - Room 605
Augusta, Georgia 30901
RFQ documents may be examined at the office of the Augusta, GA Procurement Department, 530 Greene Street
– Room 605, Augusta, GA 30901. All questions must be submitted in writing to the office of the
Procurement Department by Tuesday, December 28, 2010 @ 5:00 p.m. by fax at 706-821-2811 or by email
@ procbidandcontract@augustaga.gov. No RFQ will be accepted by fax, all must be received by mail
or hand delivered.
The local bidder preference program is applicable to this project. To be approved as a local bidder and
receive bid preference on an eligible local project, the certification statement as a local bidder and all
supporting documents must be submitted to the Procurement Department with your bonafide bid
package.
No RFQ may be withdrawn for a period of 90 days after time has been called on the date of opening.
An invitation for bids shall be issued by the Procurement Office and shall include specifications prepared in
accordance with Article 4 (Product Specifications), and all contractual terms and conditions, applicable to the
procurement. All specific requirements contained in the invitation to bid including, but not limited to, the number
of copies needed, the timing of the submission, the required financial data, and any other requirements
designated by the Procurement Department are considered material conditions of the bid which are not waiveable
or modifiable by the Procurement Director. Please mark RFQ number on the outside of the envelope.
Bidders are cautioned that sequestration of RFQ documents through any source other than the office of the
Procurement Department is not advisable. Acquisition of RFQ documents from unauthorized sources places the
bidder at the risk of receiving incomplete or inaccurate information upon which to base his qualifications.
Disadvantage Business Enterprise (DBE) Augusta-Richmond County, Georgia does not operate a DBE,
MBE or WBE Program for Augusta funded projects, as a Federal Court has entered an Order enjoining the
Race-Based portion of Augusta’s DBE Program. Instead Augusta operates a Local Small Business
Opportunity Program. However, for various projects utilizing the expenditure of State or Federal funds,
Augusta enforces DBE requirements and/or DBE goals set by the Federal and/or State Agencies in
accordance with State and Federal laws.
GERI A. SAMS, Procurement Director
Publish:
Augusta Chronicle December 2, 9, 16, 23, 2010
Metro Courier December 8, 2010
cc: Tameka Allen Interim Deputy Administrator
Tom Wiedmeier Utilities Department
Drew Goins Utilities Department
Attachment number 3 \nPage 1 of 1
Item # 1
VENDORS Attachment B Bidders Form
Addendums
1 & 2 Original 7 Copies
AECOM
1360 Peachtree Street, NE Ste 500
Atlanta GA 30309
YES YES YES YES YES
Brown & Caldwell
990 Hammond Drive Ste 400
Atlanta GA 30328
YES YES YES YES YES
CH Guernsey & Company
1100 Circle 75 Parkway Ste 1530
Atlanta GA 30339
YES YES YES YES YES
Constantine Engineering
6400 Peake Road
Macon GA 31210
YES YES YES YES YES
Dewberry
2835 Brandywine Road Ste 100
Atlanta GA 30341
YES YES YES YES YES
Jacobs Engineering Group
6801 Governors Lake Pkwy Bldg 200
Norcross GA 30071
YES YES YES YES YES
Parsons Brinckerhoff
3340 Peachtree Road, NE Ste 2400
Tower Place 100
Atlanta GA 30326
YES YES YES YES YES
Stevenson & Palmer
723 Industrial Park Drive, Suite 2
Evans, GA 30809
YES YES YES YES YES
Woodard & Curran
2905 Premiere Parkway, Suite 175
Duluth, GA 30097
YES YES YES YES YES
Heery International
999 Peachtree Street, NE Suite 300
Atlanta, GA 30309
RFQ Item #11-054
Water and Wastewater System Master Plan
for the City of Augusta - Utilities Department
RFQ Due: Wednesday, January 26, 2011 @ 11:00 a.m.
SUBMITTED NO BID RESPONSE
Page 1 of 1
Attachment number 4 \nPage 1 of 1
Item # 1
Evaluation Criteria PTS
AECOM
1360 Peachtree
Street, NE Ste 500
Atlanta GA 30309
Brown & Caldwell
990 Hammond Drive
Ste 400
Atlanta GA 30328
CH Guernsey &
Company
1100 Circle 75
Parkway Ste 1530
Atlanta GA 30339
Constantine
Engineering
6400 Peake Road
Macon GA 31210
Dewberry
2835 Brandywine Road
Ste 100
Atlanta GA 30341
Jacobs Engineering
Group
6801 Governors Lake
Pkwy Bldg 200
Norcross GA 30071
Parsons Brinckerhoff
3340 Peachtree Road,
NE Ste 2400
Tower Place 100
Atlanta GA 30326
Stevenson & Palmer
723 Industrial Park
Drive, Suite 2
Evans, GA 30809
Woodard & Curran
2905 Premiere Parkway,
Suite 175
Duluth, GA 30097
1. Firms experience and
performance on projects of
similar size and scope 25
22.7 20.0 15.0 19.0 17.7 19.3 17.7 14.3 15.0
2. Firms Quality Control,
Quality Assurance and Project
Tracking 20
17.0 17.0 14.3 17.0 18.0 19.0 16.3 16.0 15.7
3. Project Approach and
Understanding 25 22.7 21.7 17.0 19.0 18.7 21.7 18.7 17.7 18.3
4. Qualifications, experience,
references and availability of
Key Staff 25
24.3 21.7 16.7 21.7 19.3 19.7 19.3 16.7 17.0
5. Proximity to Area 5 4.0 4.0 3.3 3.3 3.7 4.0 3.3 4.3 3.0
Total 100 90.7 84.3 66.3 80.0 77.3 83.7 75.3 69.0 69.0
1 2 4 3
1 3 2 4
Cumulative Presentation Evaluation Sheet - RFQ Item #11-054
Water and Wastewater System Master Plan
for the City of Augusta - Utilities Department
Shortlist
Presentation Ranking
Item # 1
Attachment number 6 \nPage 1 of 1
Item # 1
Attachment number 7 \nPage 1 of 6
Item # 1
Attachment number 7 \nPage 2 of 6
Item # 1
Attachment number 7 \nPage 3 of 6
Item # 1
Attachment number 7 \nPage 4 of 6
Item # 1
Attachment number 7 \nPage 5 of 6
Item # 1
Attachment number 7 \nPage 6 of 6
Item # 1
Engineering Services Committee Meeting
1/9/2012 1:00 PM
Donated Easement
Department:Law
Caption:Motion to approve a donated Easement between James P. Helton, Jr.
and Margaret Knapp Helton, as owners, and Augusta, Georgia, as
optionee, in connection with the Fox Spring Road Drainage
Improvement Project, said perpetual easement consists of 0.10 acre
(4,355 sq. ft.) of permanent drainage and utility easement, more or
less, from the property located at 3026 Fox Spring Road, private.
Background:The property owner has agreed to convey a certain option for
easement to Augusta, Georgia, for the Fox Spring Road Drainage
Improvement Project.
Analysis:The purchase of the referenced property is necessary for the project.
Financial Impact:The costs necessary for this purchase will be covered under the
project budget.
Alternatives:Deny the Motion
Recommendation:Approve the Motion
Funds are Available
in the Following
Accounts:
REVIEWED AND APPROVED BY:
Finance.
Law.
Administrator.
Clerk of Commission
Cover Memo
Item # 2
At
t
a
c
h
m
e
n
t
n
u
m
b
e
r
1
\
n
P
a
g
e
1
o
f
3
It
e
m
#
2
At
t
a
c
h
m
e
n
t
n
u
m
b
e
r
1
\
n
P
a
g
e
2
o
f
3
It
e
m
#
2
At
t
a
c
h
m
e
n
t
n
u
m
b
e
r
1
\
n
P
a
g
e
3
o
f
3
It
e
m
#
2
Engineering Services Committee Meeting
1/9/2012 1:00 PM
Option for Easement
Department:Law
Caption:Motion to approve an Option for the purposes of acquiring an
Easement between Bobby Lenwood Thomas, Jr., as owner, and
Augusta, Georgia, as optionee, in connection with the East
Augusta Roadway and Drainage Improvement Project, said
perpetual easement consists of 0.002 acre (75.26 sq. ft.) of
permanent drainage and utility easement, more or less, and
(563.18 sq. ft.) of temporary construction easement from the
property located at 802 Wallace Street, private, at the purchase
price of $150.00.
Background:The property owner has agreed to convey a certain option for
easement to Augusta, Georgia, for the East Augusta Roadway and
Drainage Improvement Project.
Analysis:The purchase of the referenced property is necessary for the
project.
Financial Impact:The costs necessary for this purchase will be covered under the
project budget.
Alternatives:Deny the Motion
Recommendation:Approve the Motion
Funds are Available
in the Following
Accounts:
REVIEWED AND APPROVED BY:
Finance.
Law.
Cover Memo
Item # 3
Administrator.
Clerk of Commission
Cover Memo
Item # 3
At
t
a
c
h
m
e
n
t
n
u
m
b
e
r
1
\
n
P
a
g
e
1
o
f
2
It
e
m
#
3
At
t
a
c
h
m
e
n
t
n
u
m
b
e
r
1
\
n
P
a
g
e
2
o
f
2
It
e
m
#
3
Engineering Services Committee Meeting
1/9/2012 1:00 PM
Option for Easement
Department:Law
Caption:Motion to approve an Option for the purposes of acquiring an
Easement between Sherry M. Smith, as owner, and Augusta,
Georgia, as optionee, in connection with the East Augusta
Roadway and Drainage Improvement Project, said perpetual
easement consists of (231.64 sq. ft.) of permanent drainage and
utility easement, more or less, and (408.73 sq. ft.) of temporary
construction easement from the property located at 409 Aiken
Street, private, at the purchase price of $538.00.
Background:The property owner has agreed to convey a certain option for
easement to Augusta, Georgia, for the East Augusta Roadway and
Drainage Improvement Project.
Analysis:The purchase of the referenced property is necessary for the
project.
Financial Impact:The costs necessary for this purchase will be covered under the
project budget.
Alternatives:Deny the Motion
Recommendation:Approve the Motion
Funds are Available
in the Following
Accounts:
REVIEWED AND APPROVED BY:
Finance.
Law.
Administrator.
Cover Memo
Item # 4
Clerk of Commission
Cover Memo
Item # 4
At
t
a
c
h
m
e
n
t
n
u
m
b
e
r
1
\
n
P
a
g
e
1
o
f
2
It
e
m
#
4
At
t
a
c
h
m
e
n
t
n
u
m
b
e
r
1
\
n
P
a
g
e
2
o
f
2
It
e
m
#
4
Engineering Services Committee Meeting
1/9/2012 1:00 PM
Resolution to adopt and enter Crosswalk Easement Agreement
Department:Law
Caption:Motion to approve Crosswalk Easement Agreement entered into
by Augusta, Georgia and The Whites Building Condominium
Association, Inc.
Background:The Whites Building Condominium Association, Inc. desires to
have an easement agreement approved that would establish all
easements and air rights necessary for the Crosswalk over Ellis
Street. Construction of the crosswalk was approved by the City of
Augusta in 1951, but no easement was ever granted.
Analysis:N/A
Financial Impact:None in that maintainence of crosswalk would be grantte's
responsibilty
Alternatives:Deny the motion
Recommendation:Approve Resolution and Easement Agreement
Funds are Available
in the Following
Accounts:
N/A
REVIEWED AND APPROVED BY:
Finance.
Law.
Administrator.
Clerk of Commission
Cover Memo
Item # 5
After recording return to:
James B. Trotter
Trotter Jones, LLP
3527 Walton Way
Augusta, Georgia 30909
(706) 737-3138
Clerk: Please Cross Reference:
Deed Book 1183, Page 876
___________________________________________________________________________
CROSSWALK EASEMET AGREEMET
THIS CROSSWLK EASEMENT AGREEMENT (the "Agreement") is entered into this
____ of _____________, 2012, by and among Augusta, Georgia, a Political Subdivision of
the State of Georgia (hereafter referred to as the “City”), CML-GA WB, LLC, a Georgia
limited liability company (hereafter referred to as “CML-GA”), and The Whites Building
Master Condominium Association, Inc., a Georgia nonprofit corporation, as nominee for unit
owners at The Whites Building, A Master Condominium (hereinafter referred to as the
“Association”).
WITNESSETH:
WHEREAS, CML-GA is also the holder of the fee interest in certain property located in
the State of Georgia, County of Richmond, and City of Augusta, having a street address of
920 Ellis Street, Augusta, Richmond County, Georgia, and known as the Whites Warehouse
Property as more fully described on Exhibit “A” attached hereto, which property is
improved with a four story warehouse building (the “Warehouse”);
WHEREAS, that certain Declaration of Condominium for The Whites Building, A Master
Condominium was recorded in Deed Book 1183, Page 876, et seq., of the Richmond County, Georgia
land records, as amended (hereinafter referred to as the "Master Declaration");
WHEREAS, the Association is the condominium association for The Whites Building, A
Master Condominium (the “Master Condominium”) created pursuant to the Master
Declaration;
Attachment number 1 \nPage 1 of 7
Item # 5
WHEREAS, in accordance with Section 9.4 of the Master Declaration and O.C.G.A.
Section 44-3-106(b), the Association is authorized to accept easements benefiting the Master
Condominium;
WHEREAS, the City owns the street in the State of Georgia, County of Richmond, and
City of Augusta known as Ellis Street, which right-of-way runs between the Warehouse and
the Master Condominium;
WHEREAS, for many years, a crosswalk bridge has connected the Master Condominium
to the Warehouse and has spanned over Ellis Street (the “Crosswalk”); as shown on that
certain plat prepared by Besson and Gore for Augusta Renaissance Partners, LLC dated
August 20, 1999, revised January 9, 2001 and recorded in the Office of the Clerk of Superior
Court of Richmond County, Georgia in Plat Cabinet B, Slide 82, Plat N (the “Plat”);
WHEREAS, on January 2, 1951, the City passed a motion approving the construction of
the crosswalk bridge above and across Ellis Street;
WHEREAS, CML-GA, the Association, and the City desire to enter into this Agreement
to establish all easements necessary for the Crosswalk over Ellis Street; and
NOW, THEREFORE, in consideration of the mutual covenants contained herein, the sum
of $10.00 paid by each party to the other, and other good and valuable consideration, the
receipt and sufficiency of which are hereby acknowledged, the parties to this Agreement
covenant and agree as follows:
1. DECLARATION; PERSONS BENEFITED AND BOUND:
1.01 Declaration. The City, the Association and CML-GA declare that the Warehouse,
the Master Condominium and the Crosswalk, respectively, and every portion thereof, are and
shall be held, developed, occupied, used, leased, transferred, encumbered, sold, and
conveyed subject to the rights, covenants, obligations, duties, benefits, easements, and other
provisions created, declared, or contained in this Agreement.
1.02 Persons and Property Benefited and Bound:
A. The rights, covenants, obligations, duties, benefits, burdens, easements,
and other provisions created, declared, or contained in this Agreement shall benefit and bind
the Warehouse, the Master Condominium and the Crosswalk, respectively, and each
purchaser, tenant, licensee, invitee, user, security deed holder, and lien holder, of any portion
of the Warehouse, Master Condominium and Crosswalk, and each of their respective heirs,
personal representatives, successors, and assigns, and shall at all times hereafter be
appurtenant to, affect, and run with the land generally.
B. This Agreement shall be recorded in the Office of the Clerk of Superior
Court for Richmond County, Georgia and, when so recorded: (i) every deed, lease, security
deed, or any other instrument hereafter conveying, leasing, encumbering or in any way
Attachment number 1 \nPage 2 of 7
Item # 5
affecting title to or any interest in the Warehouse, the Master Condominium and the
Crosswalk generally, or any portion thereof, shall refer to this Agreement and in any case
shall be under and subject to this Agreement and to the rights, covenants, obligations, duties,
benefits, easements, and other provisions herein created, declared, or contained, as though
the same were therein fully recited and set forth in their entireties; and (ii) the execution or
acceptance of any instrument, or the act of occupancy use of the Warehouse, the Master
Condominium and the Crosswalk generally, or any portion of either of them, shall constitute
an agreement to be subject to and bound by this Agreement, and in acceptance and
ratification of this Agreement.
2. CREATION AND GRANT OF EASEMENTS. The City hereby grants, sells, and
conveys to the Association and its Permittees (as defined below), and its successors and assigns,
a perpetual, non-exclusive, and irrevocable easement to use the Crosswalk over Ellis Street for
the purpose of pedestrian ingress, egress, and access as well as for the use and installation of
electrical, telephone, computer, and security systems wiring in the Crosswalk. The Association
shall be entitled to designate from time to time which, if any, unit owners, occupants, tenants, and
invitees of the Master Condominium (“Permittees”) shall be entitled to utilize and enjoy the
easements granted herein; it being the intent of this Section that no independent rights shall be
created by this Section as to any such Permittees except for those which may be terminated or
withdrawn at any time by the Association.
3. ADDITIONAL OBLIGATIONS:
3.01 Limitation of Rights. Nothing herein shall be construed as a grant to the general
public. The easements described in this Agreement are not intended to benefit parcels of
land other than those specifically identified herein without the consent in writing, in
recordable form, of the City, the Association, and CML-GA, or their successors and assigns.
3.02 Reservation of Rights. The easements and other rights and benefits granted in this
Agreement are non-exclusive, and the City, the Association, and CML-GA reserve and retain
the right to convey similar rights and easements to such other persons or entities as they may
deem proper.
3.03 Repair and Maintenance of Crosswalk. Whenever it shall become necessary to
repair or rebuild the Crosswalk, the expenses of such repairing or rebuilding shall be solely
borne by the Association. It shall become necessary to repair or rebuild the Crosswalk or any
part thereof if any of the following occur: (i) repairs or rebuilding shall be necessary to
maintain the Crosswalk or any part thereof in good repair and condition; (ii) repairs or
rebuilding shall be required by any law, ordinance, regulation, or requirement of any public
authority having jurisdiction; or (iii) the Crosswalk or any part thereof shall be damaged or
destroyed by fire or other casualty. Notwithstanding the foregoing, if the Crosswalk is so
extensively damaged by fire or other casualty that it is not reasonable to rebuild it, then the
Association, at its sole option, may elect not to rebuild the Crosswalk. Whenever the
Crosswalk or any part thereof shall be rebuilt, however, it shall be rebuilt in substantially the
same location as, shall be substantially the same size as, and shall be of quality at least good
Attachment number 1 \nPage 3 of 7
Item # 5
as the Crosswalk existing immediately prior to the event necessitating the rebuilding.
Nothing herein shall be deemed to limit the Association from seeking reimbursement from
any person or entity that causes damages to the Crosswalk.
3.04 Maintenance and Insurance. The Association shall be responsible for all routine
maintenance necessary for the Crosswalk. Furthermore, the Association shall maintain
general commercial liability insurance in the amount of at least $1,500,000.00 per
occurrence, and shall increase the amount of insurance periodically as reasonably requested
by Augusta, Georgia or as determined by the Association. Said policy shall name CML-GA,
or the successor owner of the Warehouse, as an additional insured.
3.05 Indemnification. To the extent allowed by law, Grantees CML-GA and the
Association shall indemnify and hold Grantor City and its commissioners, managers,
employees, agents, legal representatives and the successors and assigns of each of them
harmless from and against any and all actions, suits, proceedings, claims, demands, losses,
liabilities, damages and expenses (including reasonable attorneys' fees) arising out of or
relating to (i) the use of the Easement by Grantees, its contractors, agents, employees,
permittees, invitees or licensees, including but not limited to death, personal injury or loss or
damage to property, and (ii) any breach by Grantees of their/its covenants or obligations
under this Agreement. This indemnification shall not apply to injury or damage caused by
the willful, grossly negligent, or negligent acts of Grantor City. In the event of any damage
or injury to the Easement resulting from any negligent or willful acts or misconduct of
Grantor City or its commissioners, employees, agents, managers, legal representatives or
successors or assigns, Grantor City shall pay for the actual and reasonable cost of any repairs
necessary to restore the Easement to the reasonably same condition prior to such damage.
4. MISCELLANEOUS PROVISION:
4.01 Effective Date; Amendments. This Agreement shall become effective upon
execution. This Agreement may be amended from time to time by recorded written
instrument duly executed and acknowledged by the fee owner of the Warehouse and the
Association (or the successor fee owner of the Master Condominium property in event the
Master Condominium is terminated).
4.02 Invalidity. If any provision of this Agreement is determined to be invalid, such
determination shall not affect the validity or effect of the remaining provisions of this
Agreement, all of which shall continue in effect as if such invalid provision had not been
included in this Agreement.
4.03 Headings. The paragraph titles and headings of this Agreement are for
convenience of reference only, do not form a part hereof, and shall not affect the meaning or
interpretation of this Agreement.
4.04 Pronouns and Plurals. All pronouns and any variation thereof are deemed to refer
to the masculine, feminine, and neuter, singular, or plural, as the identity of the persons may
require.
Attachment number 1 \nPage 4 of 7
Item # 5
4.05 Entire Agreement. This Agreement contains the entire understanding and
agreement among the parties hereto, and supersedes any prior understandings and agreements
among them respecting subject matter of this Agreement.
5.06 Parties in Interest. This Agreement shall bind and inure to the benefit of the City,
the Association, and CML-GA, and their respective successors and assigns.
IN WITNESS WHEREOF, the Parties hereto have set their hands and seals to the
foregoing Crosswalk Easement Agreement the day and year first above written:
[Signatures Appear on Next Page]
Attachment number 1 \nPage 5 of 7
Item # 5
Signed, sealed and delivered in the presence
of:
Unofficial Witness
Notary Public
[NOTARIAL SEAL]
My Commission Expires:
AUGUSTA, GEORGIA
By: ________________________________
As its Mayor
By: _________________________________
As its Clerk of Commission
Signed, sealed and delivered in the presence
of:
Unofficial Witness
Notary Public
[NOTARIAL SEAL]
My Commission Expires:
CML-GA WB, LLC
By: Multibank 2009-1 CML-ADC Venture, LLC,
its sole member
By: RL CML 2009-1 Investments, LLC, its
Manager
By: ________________________________
As its: ______________________________
Signed, sealed and delivered in the presence
of:
Unofficial Witness
Notary Public
[NOTARIAL SEAL]
My Commission Expires:
THE WHITES BUILDING MASTER
CONDOMINIUM ASSOCIATION, INC.,
a Georgia nonprofit corporation
By: ________________________________
As its President
By: _________________________________
As its Secretary
[CORPORATE SEAL]
Attachment number 1 \nPage 6 of 7
Item # 5
Exhibit A
“Warehouse Property”
All that certain lot, tract or parcel of land, situate, lying and being in the State of
Georgia, County of Richmond and City of Augusta, fronting 120.10 feet on the
Southern Right of Way of Ellis Street and 160.59 feet on the Northern Right of
Way of Greene Street and being shown and designated as “0.86 acre 37,657 SF”
on a certain Plat prepared for Augusta Renaissance Partners, LLC by Besson &
Gore, dated August 20, 1999, a copy of said Plat being recorded in the Office of
the Clerk of the Superior Court of Richmond County, Georgia at Realty Reel 666,
Pages 2188-2189. Reference is hereby made to said Plat for a more particular and
accurate description as to the metes, bounds, and location of said property.
Tax Map & Parcel No. 047-1-115-01-0.
Attachment number 1 \nPage 7 of 7
Item # 5
A RESOLUTIO OF THE AUGUSTA-RICHMOD COUTY COMMISS IO
TO ADOPT THE CROSSWALK EASEMET AGREEMET WITH THE
WHITES BUILDIG MASTER CODOMIIUM ASSOCIATIO, I C.
THIS RESOLUTIO, adopted by the Augusta-Richmond County, Georgia
Commission (“Commission”):
WHEREAS, CML-GA, a Georgia limited liability company is also the holder of the fee
interest in certain property located in the State of Georgia, County of Richmond, and City of
Augusta, having a street address of 920 Ellis Street, Augusta, Richmond County, Georgia, and
known as the Whites Warehouse Property, which property is improved with a four story
warehouse building;
WHEREAS, that certain Declaration of Condominium for The Whites Building, A
Master Condominium was recorded in Deed Book 1183, Page 876, et. seq., of the Richmond
County, Georgia land records, as amended;
WHEREAS, the Association is the condominium association for The Whites Building, A
Master Condominium created pursuant to the Declaration of Condominium for The Whites
Building;
WHEREAS, in accordance with Section 9.4 of the Declaration of Condominium and
O.C.G.A Section 44-3-106(b), the Association is authorized to accept easements benefiting the
Master Condominium;
WHEREAS, Augusta, Georgia owns the street in the State of Georgia, County of
Richmond, and City of Augusta known as Ellis Street, which right-of-way runs between the
Warehouse and the Master Condominium;
WHEREAS, for many years, a crosswalk bridge has connected the Master
Condominium to the Warehouse and has spanned over Ellis Street;
WHEREAS, on January 2, 1951, the City passed a motion approving the construction of
the crosswalk bridge above and across Ellis Street;
Attachment number 2 \nPage 1 of 2
Item # 5
WHEREAS, CML-GA, the Association and Augusta, Georgia desire to enter into this
agreement to establish all easements necessary for the Crosswalk over Ellis Street; and
OW, THEREFORE, be it resolved by the Commission and it is hereby resolved that
Augusta, Georgia, CML-GA, and the Association shall entered into an agreement establishing all
easements necessary for the Crosswalk over Ellis Street as listed in the Crosswalk Easement
Agreement and the Mayor is hereby authorized to execute the documents necessary to effectuate
such agreement in the form deemed appropriate by Augusta Law Department.
DULY ADOPTED by the Augusta-Richmond County, Georgia Commission this
_______ day of _____________________, 2012.
AUGUSTA-RICHMOD COUTY,
GEORGIA COMMISSIO
By:_________________________________
David S. Copenhaver
As its Mayor
Attest:______________________________
Lena J. Bonner
As its Clerk
(COUNTY SEAL)
Attachment number 2 \nPage 2 of 2
Item # 5