1. Approve Change Orders #1 and #2 on PO 190658 to Acme
Moving and Storage for moving of court related offices to the
new Augusta Judicial Center and John H. Ruffin Courthouse in
the amount of $24,057.60 for additional services requested by
court officials. The revised PO amount will be $292,432.60.
Attachments
2. Consider a request from The First Tee of Augusta regarding an
adjustment of their monthly water rate and report from staff
regarding the water usage at other golf courses. (Referred
from October 10 Engineering Services Committee)
Attachments
3. Approve and accept the Resolution and Agreement (Contract)
from the Georgia Department of Transportation (GDOT) for the
Acquisition of Right of Way to improve the Windsor Spring
Road Section V Project, CPB Change Number Ten (323-
041110-299823786). Also, approve to adopt the Uniform
Relocation Assistance and Real Property Acquisition Policies
Act of 1970 and GDOT guidelines for this Project and authorize
Augusta, Georgia Mayor to execute this Resolution and
Agreement for the Engineering Department.
Attachments
Engineering Services Committee Meeting
10/24/2011 12:55 PM
Judicial Center Move - CO 1&2
Department:Recreation, Parks and Facilities - Facilities Management
Caption:Approve Change Orders #1 and #2 on PO 190658 to Acme
Moving and Storage for moving of court related offices to the new
Augusta Judicial Center and John H. Ruffin Courthouse in the
amount of $24,057.60 for additional services requested by court
officials. The revised PO amount will be $292,432.60.
Background:RFP 10-168 was issued and bid using a specific furniture
inventory and estimated number of file boxes and other items to
move. As operations began, it became necessary to rent document
storage carts for a longer time frame than initially anticipated.
Furthermore, court operations elected to relocate more of their
electronic filing systems than were initially included in the RFP.
Analysis:The additional cart and storages rental was required due to the
volume of files that had to be stored while still remaining
accessible to the courts. The original building plans were based on
a typical floor layout. The actual furnishings and open office
systems installed were slightly different than the initial
assumption and allowed for the departments to relocate additional
existing equipment to increase document storage capacity.
Financial Impact:The cost of the Change Orders is $24,057.60 for a revised PO of
$292,432.60 funded from SPLOST monies allocated to the
Judicial Center.
Alternatives:1. Approve Change Orders #1 and #2 on PO 190658 to Acme
Moving and Storage for moving of court related offices to the new
Augusta Judicial Center and John H Ruffin Courthouse in the
amount of $24,057.60 for additional services requested by court
officials. The revised PO amount will be $292,432.60. 2. Do not
approve Change Orders
Recommendation:#1. Approve Change Orders #1 and #2 on PO 190658 to Acme
Moving and Storage for moving of court related offices to the new
Augusta Judicial Center and John H Ruffin Courthouse in the
Cover Memo
Item # 1
amount of $24,057.60 for additional services requested by court
officials. The revised PO amount will be $292,432.60.
Funds are Available
in the Following
Accounts:
FUNDS ARE AVAILABLE IN ACCOUNT: GL 325-05-1120; JL
209-25-1104, Object Code 5413130.
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Cover Memo
Item # 1
Attachment number 1 \nPage 1 of 6
Item # 1
Attachment number 1 \nPage 2 of 6
Item # 1
Attachment number 1 \nPage 3 of 6
Item # 1
Attachment number 1 \nPage 4 of 6
Item # 1
Attachment number 1 \nPage 5 of 6
Item # 1
Attachment number 1 \nPage 6 of 6
Item # 1
Engineering Services Committee Meeting
10/24/2011 12:55 PM
The First Tee of Augusta
Department:Clerk of Commission
Caption:Consider a request from The First Tee of Augusta regarding an
adjustment of their monthly water rate and report from staff
regarding the water usage at other golf courses. (Referred
from October 10 Engineering Services Committee)
Background:
Analysis:
Financial Impact:
Alternatives:
Recommendation:
Funds are Available
in the Following
Accounts:
REVIEWED AND APPROVED BY:
Cover Memo
Item # 2
Attachment number 1 \nPage 1 of 1
Item # 2
Engineering Services Committee Meeting
10/24/2011 12:55 PM
Windsor Spring Road, Phase V
Department:Engineering Department-Abie L. Ladson, PE, CPESC
Caption:Approve and accept the Resolution and Agreement (Contract)
from the Georgia Department of Transportation (GDOT) for the
Acquisition of Right of Way to improve the Windsor Spring Road
Section V Project, CPB Change Number Ten (323-041110-
299823786). Also, approve to adopt the Uniform Relocation
Assistance and Real Property Acquisition Policies Act of 1970
and GDOT guidelines for this Project and authorize Augusta,
Georgia Mayor to execute this Resolution and Agreement for the
Engineering Department.
Background:The Windsor Spring Road Section V Improvement Project was
approved by the Augusta, Georgia Commission, and on April 6,
1999, Augusta, Georgia, entered into an agreement with GDOT to
accept responsibility for the project preliminary engineering,
right-of-way acquisition and utilities relocation. The project
improvements include road widening and construction to 4 lanes
with a 19’ wide raised median from just south of SR 88 in
Hephzibah to Willis Foreman Road. Road improvements also
include reconstructing the bridge over Norfolk Southern
Railroad. The project is under the design phase and ready for
Right-of-Way acquisition. Funding for the right of way is a joint
effort between Augusta-Richmond County ($1,100,000) and
GDOT (not to exceed $4,236,500). Augusta-Richmond County is
responsible for the acquisition of the right of way and GDOT is
responsible for the construction cost. The current estimated
construction cost is $13,235,553 and the project is currently
scheduled for letting in November 2013.
Analysis:Execution of this agreement is critical for maintaining project
right-of-way acquisition schedule and to receive aforementioned
federal funds as programmed by the GDOT. The estimated cost
for right-of-way acquisition is $5,550,000. Augusta Engineering
Department (AED) has identified $1,100,000 for this purpose and
has been working with GDOT and the Augusta Metropolitan
Planning Organization (MPO) to find additional needed funds. On
May 27, 2011, AED working with the MPO, was able to identify
funding from GDOT to assist with the acquisition of the right of
Cover Memo
Item # 3
way. $4,500,000 is included in the MPO Transportation
Improvement Plan (TIP) which is going through the approval
process now. TIP has been approved at local level and approval by
the state of Georgia and Federal Highway Administration is
expected in the fall of 2011. These funds should become available
in GDOT fiscal year 2012 (7/1/11 – 6/30/12).
Financial Impact:AED has funds available in the project Right-of-Way account in
an amount of $847,000 (CPB # 323-041110-
5411120/299823786). Funds are also available in the Windsor
Spring Road Section IV right of way account, (CPB # 323-
041110- 5411120/299823766) in the amount of $253,000 to be
transferred to the Windsor Spring Road Section V right of way
account upon Commission approval of this agreement. These
funds will also be used for hiring the appraisers to appraise the
parcels, and using legal counsel to close all parcels.
Alternatives:1) Approve and Accept the Resolution and Agreement (Contract)
from the Georgia Department of Transportation (GDOT) for the
Acquisition of Right of Way to improve the Windsor Spring Road
Section V Project, CPB Change Number Ten 323-041110-
299823786. Also, Approve to Adopt the Uniform Relocation
Assistance and Real Property Acquisition Policies Act of 1970
and GDOT guidelines for this Project and Authorize Augusta,
Georgia Mayor to Execute this Resolution and Agreement for the
Engineering Department. 2) Do not approve and delay the
construction and improvements on a major transportation corridor
that is vital to Augusta-Richmond County and also loose
designated state and Federal funding.
Recommendation:Approve Alternative Number One.
Funds are Available
in the Following
Accounts:
323-041110-5411120/299823766 & 323-041110-
5411120/299823786
REVIEWED AND APPROVED BY:
Finance.
Law.
Administrator.
Clerk of Commission
Cover Memo
Item # 3
Attachment number 1 \nPage 1 of 18
Item # 3
Attachment number 1 \nPage 2 of 18
Item # 3
Attachment number 1 \nPage 3 of 18
Item # 3
Attachment number 1 \nPage 4 of 18
Item # 3
Attachment number 1 \nPage 5 of 18
Item # 3
Attachment number 1 \nPage 6 of 18
Item # 3
Attachment number 1 \nPage 7 of 18
Item # 3
Attachment number 1 \nPage 8 of 18
Item # 3
Attachment number 1 \nPage 9 of 18
Item # 3
Attachment number 1 \nPage 10 of 18
Item # 3
Attachment number 1 \nPage 11 of 18
Item # 3
Attachment number 1 \nPage 12 of 18
Item # 3
Attachment number 1 \nPage 13 of 18
Item # 3
Attachment number 1 \nPage 14 of 18
Item # 3
Attachment number 1 \nPage 15 of 18
Item # 3
Attachment number 1 \nPage 16 of 18
Item # 3
Attachment number 1 \nPage 17 of 18
Item # 3
Attachment number 1 \nPage 18 of 18
Item # 3
Augusta-Richmond County, Georgia
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County,
Georgia that the following Capital Project Budget is hereby adopted:
Section 1: This project is authorized to CPB#323-041110-299823766 and Change Number Ten. The funding for
this project in the amount of $253,000 is needed for the Resolution and Agreement Contract from
GDOT for the Acquisition of Right of Way to improve the Windsor Spring Road, Section V project.
Approve to adopt the Uniform Relocation Assistane and Real Property Acquisition Policies Act of
1970 and GDOT guidelines for this project . The funding will be transferred to Section V of the
project Right of Way account.
Section 2: The following revenues are anticipated to be available to the Consolidated
Government to complete the project.
Special 1% Sales Tax, Phase III 1,560,500$
Special 1% Sales Tax, Phase IV 600,000$
2,160,500$
Section 3: The following amounts are appropriated for the project:
By Basin By District
4th, 6th, & 8th 2,160,500$
Section 4: Copies of this Capital Project Budget shall be made available to the
Comptroller for direction in carrying out this project.
Adopted this ____________________ day of ______________________.
Approved
_________________________________________________
Original-Commission Council Office
Copy-Engineering Department
Copy-Finance Department
Copy-Procurement Department
Honorable, Deke Copenhaver, Mayor
CPB#323-041110-299823766
CAPITAL PROJECT BUDGET
WINDSOR SPRING ROAD IMPROVEMENTS, SECTION IV
(WILLIS FOREMAN RD TO TOBACCO RD)
CHANGE NUMBER TEN
McBean/Spirit Crk $ 2,160,500
Please do not process this document. Once approved by the Commission the original will be sent to the Clerk of Commission for execution. For information reference this request, contact Engineering
at ext 5070. Thanks
1 of 2 10/3/2011
Attachment number 2 \nPage 1 of 2
Item # 3
Augusta-Richmond County, Georgia CPB#323-041110-299823766
CAPITAL PROJECT BUDGET
WINDSOR SPRING ROAD IMPROVEMENTS, SECTION IV
(WILLIS FOREMAN RD TO TOBACCO RD)
CHANGE NUMBER TEN
CPB AMOUNT CPB NEW
SOURCE OF FUNDS CPB CHANGE CPB
SALES TAX, PHASE III
323041110-000000-299823766 ($1,000)($1,000)
SALES TAX, PHASE III
323041110-000000-299823766 ($1,559,500)($1,559,500)
SPECIAL 1% SALES TAX, PHASE IV
324041110-000000-202824766 ($600,000)($600,000)
TOTAL SOURCES: ($2,160,500) ($2,160,500)
USE OF FUNDS
ADVERTISING
323041110-5233119-299823766 $1,000 $1,000
ENGINEERING
323041110-5212115-299823766 $1,248,639 $1,248,639
RIGHT OF WAY
323041110-5411120-299823766 $851,361 ($253,000)$598,361
(transferred to Section V 299823786)
UTILITIES
323041110-5414510-299823766 $50,000 $50,000
SIGNAL
323041110-5414610-299823766 $5,000 $5,000
CONTINGENCY
323041110-6011110-299823766 $4,500 $4,500
TOTAL USES: $2,160,500 $1,907,500
2 of 2 10/3/2011
Attachment number 2 \nPage 2 of 2