HomeMy WebLinkAbout2009-05-11-Meeting Agendawww.augustaga.gov
Engineering Services Committee Meeting Committee Room- 5/11/2009- 12:50 PM
ENGINEERING SERVICES
1. Approve the Guaranteed Maximum Price (GMP) in the amount of
$ for Potts Construction to build the Augusta Judicial Center
currently under construction.
Attachments
2. Motion to advise the Augusta Commission of the possible need to notify
certain users of the Augusta Canal to curtail water usage due to ongoing
drought. (Approved by Engineering Services Committee April 29, 2009)
(Referred from May 5 Commission meeting)
Attachments
3. Approve Capital Project Budget and Supplemental Agreement Number
Three as requested by the Engineering Department with Heath & Lineback
Engineers, Inc. in the amount of $64,580 for revisions extending the work
on 15th Street from Broad Street to Reynolds Street; design of 14 additional
retaining walls to minimize impacts to properties and 2 additional bridges;
GDOT mandate to use a preapproved street lighting consultant for final
street lighting plans; design of traffic signals at 3 additional intersections;
and creation of final shop drawings on the St. Sebastian Way/Greene
Street/15th Street project, CPB #324-041110-202824003. Funds are
available in the project engineering account.
Attachments
4. Motion to supplement the city’s contract with Heery International in the
amount of $30,866 to cover the additional costs associated with installing
bases and associated wiring to complete the street light upgrade of the 800
block of Telfair Street as requested by Traffic Engineering.
Attachments
5. Award bid to L-J., Inc. (sole bidder) in the amount of $196,120.72 for the
removal and replacement of 200' of failed CMP at the Municipal Golf
Course. Approve under emergency conditions as the pipe would only
continue to fail while acquiring bids. The Contractor has been given a
"Notice to Proceed" under an emergency basis.
Attachments
Engineering Services Committee Meeting
5/11/2009 12:50 PM
Approve GMP on Judicial Center
Department:Public Services Department - Facilities Management Division
Caption:Approve the Guaranteed Maximum Price (GMP) in the amount of
$ for Potts Construction to build the Augusta Judicial Center
currently under construction.
Background:Potts Construction was selected under RFQ 07-180 as the Judicial Center Project’s
Construction Manager at Risk. This project is under construction at an accelerated
pace to take advantage of current market conditions to arrive at the best product for
the lowest cost. The estimated cost for construction has been refined as each step of
the design is completed. The GMP is for the scope of work as originally defined
upon issuance of the Notice to Proceed. There have been unforeseen conditions
occurring during the site grading and underground work as is typical of any project
in an urban setting in an older city. There are additional costs which will be incurred
on these items.
Analysis:The proposed GMP has been reviewed and is consistent with the current market and
owner instructions.
Financial Impact:The total construction contract amount will not exceed $
Alternatives:1. Approve the Guaranteed Maximum Price (GMP) in the amount of $ for Potts
Construction to build the Augusta Judicial Center currently under construction. 2. Do
not approve the GMP.
Recommendation:#1. Approve the Guaranteed Maximum Price (GMP) in the amount of $ for Potts
Construction to complete the Augusta Judicial Center currently under construction.
Funds are Available in the
Following Accounts:
FUNDS ARE AVAILABLE IN ACCOUNT:#325-05-1120/209251104 - Object
Code 5413130
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Cover Memo
Item # 1
Engineering Services Committee Meeting
5/11/2009 12:50 PM
Notification of Augusta Canal Users of Possible Need to Curtail Water Use
Department:Utilities
Caption:Motion to advise the Augusta Commission of the possible need to notify
certain users of the Augusta Canal to curtail water usage due to ongoing
drought. (Approved by Engineering Services Committee April 29, 2009)
(Referred from May 5 Commission meeting)
Background:The Augusta Utilities Department advised the Commission, in October
2008, of the need to notify certain users of the Augusta Canal to curtail
water usage due to a shortage of water in the Savannah River system
resulting from the ongoing drought. At that time, AUD advised that the
Canal user being asked to cease withdrawing water was Avondale Mills,
Inc. At that same briefing, we also noted that if drought persisted, other
Canal users would be affected and would be required to curtail as well. In
November 2008, the U S Army Corps of Engineers reduced the releases of
flows from Thurmond Dam from 3600cfs to 3100cfs. Although the flows in
the river have returned to 3600cfs that flow rate is not sufficient for the
demands of all the mills and the water necessary to provide water for the
public water system as the demands increase through the summer months.
Analysis:As the demand for the public water increases in the upcoming summer
months, the flows allocated to the Augusta Canal users will not be sufficient
for all users assuming the Corps of Engineers limits the flows in the
Savannah River due to the ongoing drought. In accordance with contracts
with the canal water users, Augusta has precedence over use of all other
users. In order of curtailment, the first user to be restricted will be Avondale
Mills, Inc., the second will be Enterprise Mill, LLC and the third will be
Standard Textile Augusta, Inc.
Financial Impact:This agenda item is for informational purposes. No funds are being
requested.
Alternatives:No alternatives are recommended.
Recommendation:We recommend the Commission be advised of the possible need to notify
certain users of the Augusta Canal to curtail water usage due to ongoing
drought.
Funds are Available in
the Following
Accounts:
This agenda item is for informational purposes. No funds are being
requested.
Cover Memo
Item # 2
REVIEWED AND APPROVED BY:
Clerk of Commission
Cover Memo
Item # 2
Engineering Services Committee Meeting
5/11/2009 12:50 PM
St Sebastian Way/Green St/15th St CPB-SA3
Department:Abie L. Ladson, PE, CPESC, Director of Engineering
Caption:Approve Capital Project Budget and Supplemental Agreement Number
Three as requested by the Engineering Department with Heath & Lineback
Engineers, Inc. in the amount of $64,580 for revisions extending the work
on 15th Street from Broad Street to Reynolds Street; design of 14 additional
retaining walls to minimize impacts to properties and 2 additional bridges;
GDOT mandate to use a preapproved street lighting consultant for final
street lighting plans; design of traffic signals at 3 additional intersections;
and creation of final shop drawings on the St. Sebastian Way/Greene
Street/15th Street project, CPB #324-041110-202824003. Funds are
available in the project engineering account.
Background:This is a Georgia Department of Transportation (GDOT) project that will
extend St. Sebastian Street on new location from Walton Way to Riverwatch
Parkway and provide connectivity to Broad Street. The Engineering
Department is responsible for development of the Preliminary Engineering
activities with reimbursement from GDOT equal to 80%. The Engineering
Department hired the firm of Heath & Lineback Engineers, Inc., to develop
the Preliminary Engineering activities. GDOT is reimbursing the
Engineering Department for the right of way acquisition costs and is
funding the construction cost. The project was awarded to Sunbelt
Structures, Inc. on April 9, 2008 at the low bid of $30,306,988.79.
Analysis:The Notice to Proceed to begin the preliminary engineering activities on this
project was issued to Heath & Lineback on February 10, 2000 and was
scheduled to be completed in2004The original scope of work was based on
the design of 4 bridges and 4retaining walls. The final design for this project
involved 6 bridges (increase of 2) and 18 retaining walls (increase of 14).
The additional retaining walls minimized impacts to property owners. The
original scope of work on 15th Street was from Butt Memorial Bridge to
Broad Street. The revised, approved limits of work on 15th Street were
extended to Reynolds Street. This included 3 additional intersections which
had to have their traffic signals redesigned to accommodate the additional
traffic lanes. When the original scope of work was agreed upon, it was not a
GDOT requirement that the street lighting design consultants had to be
preapproved by GDOT. GDOT changed its guidelines concerning this late
in the schedule of this project. The street lighting sub-consultant that Heath
& Lineback was originally using was not on the GDOT prequalified list.
Heath & Lineback had to change to a street lighting design consultant that
was prequalified with GDOT which resulted in additional compensation
costs that were not budget for by Heath & Lineback. The changes to the
original scope of work have also created additional shop drawing review
costs
Cover Memo
Item # 3
Financial Impact:Heath & Lineback, Inc. has proposed a total cost of $64,580 or these
additional services. $32,092 for the design of 2 additional bridges, 14
additional retaining walls and the costs associated with extending the 15th
Street project limits to Reynolds Street; $17,000 in additional funds to
reimburse the GDOT mandated street lighting design consultant; and
$15,488 in additional shop drawing costs. On March 13, 2009 GDOT agreed
to reimburse the Engineering Department 80% of all of the costs except for
the 15,488 for the review of the shop drawings. GDOT advised that cost will
be considered when the actual invoices are submitted for payment.
Alternatives:1) Approve Capital Project Budget and Supplemental Agreement Number
Three as requested by the Engineering Department with Heath & Lineback
Engineers, Inc. in the amount of $64,580 for revisions extending the work
on 15th Street from Broad Street to Reynolds Street; design of 14 additional
retaining walls to minimize impacts to properties and 2 additional bridges;
GDOT mandate to use a preapproved street lighting consultant for final
street lighting plans; design of traffic signals at 3 additional intersections;
and creation of final shop drawings on the St. Sebastian Way/Greene
Street/15th Street project, CPB #324-041110-202824003. Funds are
available in the project engineering account. 2) Do not approve the request
and jeopardize any future business opportunities with this reputable
Engineering Firm.
Recommendation:Approve Alternative Number One.
Funds are Available in
the Following
Accounts:
324-041110-5212115/202824003-5212115
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Cover Memo
Item # 3
Attachment number 1
Page 1 of 13
Item # 3
Attachment number 1
Page 2 of 13
Item # 3
Attachment number 1
Page 3 of 13
Item # 3
Attachment number 1
Page 4 of 13
Item # 3
Attachment number 1
Page 5 of 13
Item # 3
Attachment number 1
Page 6 of 13
Item # 3
Attachment number 1
Page 7 of 13
Item # 3
Attachment number 1
Page 8 of 13
Item # 3
Attachment number 1
Page 9 of 13
Item # 3
Attachment number 1
Page 10 of 13
Item # 3
Attachment number 1
Page 11 of 13
Item # 3
Attachment number 1
Page 12 of 13
Item # 3
Attachment number 1
Page 13 of 13
Item # 3
Engineering Services Committee Meeting
5/11/2009 12:50 PM
Supplemental Agreement for Street Lights along Telfair Street
Department:Abie L. Ladson, PE, CPESC, Director of Engineering
Caption: Motion to supplement the city’s contract with Heery International in the
amount of $30,866 to cover the additional costs associated with installing
bases and associated wiring to complete the street light upgrade of the 800
block of Telfair Street as requested by Traffic Engineering.
Background: The library construction project on the corner of James Brown Boulevard
and Telfair Street currently includes streetlight upgrades along the frontage
of only the library property. This supplemental agreement would provide for
installation of concrete bases and associated wire to continue this upgrade
for the remainder of the block. Richmond County forces would then install
the new light poles and fixtures.
Analysis:Upgrade would reduce maintenance and result in a uniform streetlight
system along the 800 block of Telfair Street.
Financial Impact:Based on the cost estimate provided by Heery and their subcontractors, the
cost of providing the bases and associated wiring is $30,866
Alternatives:1) Approve the proposed supplement. 2) Do not approve.
Recommendation:Approve option 1.
Funds are Available in
the Following
Accounts:
276-041610-5414410
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Cover Memo
Item # 4
Item # 4
Item # 4
Item # 4
Item # 4
Item # 4
Item # 4
Engineering Services Committee Meeting
5/11/2009 12:50 PM
Repair Cave-in at the Municipal Golf Course
Department:Public Services Department - Maintenance Division
Caption:Award bid to L-J., Inc. (sole bidder) in the amount of $196,120.72 for the
removal and replacement of 200' of failed CMP at the Municipal Golf
Course. Approve under emergency conditions as the pipe would only
continue to fail while acquiring bids. The Contractor has been given a
"Notice to Proceed" under an emergency basis.
Background:The 200' of deteriorated pipe runs from the adjacent detention pond,
underneath the cart path, and connects with the First Tee golf course.
Failure to correct this failed pipe could potentially also cause damage to the
First Tee golf course.
Analysis:Without immediate attention, the failed 36" pipe will continue to deteriorate
and cause further damage to the adjacent golf course, and repair costs will
surely rise.
Financial Impact:Funds are available in SPLOST IV, Grading and Drainage.
Alternatives:1. Award bid to L-J., Inc. (sole bidder) in the amount of $196,120.72 for the
removal and replacement of 200' of failed CMP at the Municipal Golf
Course. Approve under emergency conditions as the pipe would only
continue to fail while acquiring bids. The Contractor has been given a
"Notice to Proceed" under an emergency basis. 2. None recommended
Recommendation:#1. Award bid to L-J., Inc. (sole bidder) in the amount of $196,120.72 for
the removal and replacement of 200' of failed CMP at the Municipal Golf
Course. Approve under emergency conditions as the pipe would only
continue to fail while acquiring bids. The Contractor has been given a
"Notice to Proceed" under an emergency basis.
Funds are Available in
the Following
Accounts:
Funds are available in Grading and Drainage Account #324-04-
1110/201824021
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Cover Memo
Item # 5
Law.
Administrator.
Clerk of Commission
Cover Memo
Item # 5
Attachment number 1
Page 1 of 8
Item # 5
Attachment number 1
Page 2 of 8
Item # 5
Attachment number 1
Page 3 of 8
Item # 5
Attachment number 1
Page 4 of 8
Item # 5
Attachment number 1
Page 5 of 8
Item # 5
Attachment number 1
Page 6 of 8
Item # 5
Attachment number 1
Page 7 of 8
Item # 5
Attachment number 1
Page 8 of 8
Item # 5