HomeMy WebLinkAbout02-09-1998 Meeting
I
I
I
SUB-COMMITTEE -
SOUTH AUGUSTA
REGIONAL PARK
COMMITTEE ROOM - February 9, 1998
12:00 P. M.
PRESENT: Hons. Kuhlke, Chairman; Bridges, Mays, members;
Moses Todd, Commissioner; Tom Beck, Recreation Dept. Director;
Ron Houck of the Recreation Dept.; Randy Oliver, Administrator;
Glenn Greenway, Acting Comptroller; Greg Woodlief, Finance
Department; Jack Murphy, Interim Public Works Director and Nancy
Morawski, Deputy Clerk of Commission.
ABSENT: Hon. J. B. Powell, member.
Also Present: George Eskola of WJBF Television.
Mr. Beck: We have the plans here if anyone wants to see
them and on your summary sheet the first column shows what it
will cost to complete the park to full scale in this phase. This
includes the completion of the main road through the park which
runs from Windsor spring Rd. to Willis Foreman Rd. In the cost
of $726,000 the road would end within the complex to service the
baseball and softball fields.
Mr. Todd: What would be the impact on traffic on Windsor
Spring Road?
Mr. Kuhlke: I believe there was some highway work planned
there.
Mr. Bridges: We're trying to push the widening of Windsor
Spring up by a year or two.
Mr. Beck: There will also have to be a decel and turn lanes
installed and some right-of-way may have to be acquired.
Mr. Todd: Could we come up with some recaptured money to
help with the road?
Mr. Kuhlke: We have $5 million budgeted for this project so
if we want to do more on the project, we've got to find some more
money than we initially had programmed.
Mr. Todd: I think we should try to do the complete park by
the summer of '99 since we are hosting the Georgia Games and make
a request from the State for some funding for that purpose.
Mr. Beck: We feel we can build the road into the middle
area but what would not be built would be two of the fields in
the softball complex and one of the fields in the baseball
complex. The scoring towers will have to be built and those
fields could be completed at a later date.
Mr. Bridges: Could we ask Public Works to try and find some
money in their budget for the road to be completely built and if
we could do that, maybe we could find some money for the
gymnasium and the remaining fields.
Mr. Beck: We may still fall a little short but it would be
close.
I
Mr. Oliver: Mr. Wall advises me that the parking lots can
be considered public works projects.
Mr. Murphy: It would be cheaper to do the road completely.
The work for the decel and left turn lanes would qualify for a
county contract if we could get it from Commissioner Shackelford
but I'm not sure the road through the complex would qualify.
Mr. Kuhlke: We will talk to him later this week so we could
ask him then.
Mr. Murphy: If you would give me a little time, I'll see if
I can find $1.5 million and then you could say what you could do
without.
Mr. Oliver: That would bring us down to about a $6.6
million dollar project and there is about $5.2 budgeted so we
still need to find $1.3 million to do the full project. That
would either be through reprogramming Parks and Rec projects
because I understand from Mr. Wall that you can't take Public
Works money and move it to Parks and Rec and vice versa.
I
Mr. Kuhlke: On the Eisenhower fields, if the Board of
Education provides any participation on that, is there any chance
that our participation would be half of what it is now?
Mr. Beck: Our plan was to spend a half a million on a
gymnasium facility and $1.5 million on ballfield renovations.
The joint deal with Board could save us maybe a couple of hundred
thousand on the buildings.
Mr. Bridges: So what are we saying now?
Mr. Oliver: I think we're saying that Jack will look for
roughly $1.5 million through either Secretary Shackelford or
public works monies to see what give and take can be done there
and what projects we would have to postpone but I think we will
have to look internally through Parks and Rec for the other $1.3
million if it is the desire of the Mayor and Commission to do the
full program for this site.
Mr. Kuhlke: We'll talk to the delegation about it this
week.
Mr. Murphy: When does this actually need to be on the
ground?
I
Mr. Beck: It would be nice to have it done by the time of
I
I
I
the Georgia Games. I need some direction to know exactly what we
are going to be bidding out. We had planned to bid the project
out with basically those seven fields being completed and the
road up to a certain point and then we were going to have add
alternates to complete all ten fields.
Mr. Kuhlke: Does the engineering contract cover everything?
Mr. Beck: Yes.
Mr. Kuhlke: At what point are you going out for bids?
Mr. Beck: Our timetable is to be out for bids May 1 and
that is the date we feel we will need to get the project ready
for the summer of 1999.
Mr. Kuhlke: Could we go out for bids with the add
alternates to include the fields, the extension of the road out
to Willis Foreman and the gym?
Mr. Beck: Yes. The gym
we could ask them to go ahead
that would be ready by May 1.
could maybe come a little later and
with the plans for it but I doubt
It could be bid separately.
Mr. Kuhlke: Well, I think that's the way we should move
with it. We could also maybe identify some things in the Rec
budget that we could transfer funds from and see if we can get
six votes.
Mr. Todd: I agree.
ADJOURNMENT: There being no further business, the meeting
was adjourned.
Nancy W. Morawski
Deputy Clerk of Commission
NWM