ENGINEERING SERVICES
COMMITTEE
COMMITTEE ROOM - July 12, 1999
3:00 P. M.
PRESENT: Hons. Bob Young, Mayor; Powell, Chairman; Handy, Vice-
Chairman; Bridges and Colclough, members; Jim Wall, Attorney; Randy Oliver,
Administrator; Max Hicks, Utilities Dept. Director; Tom Wiedmeier, Utilities Dept. Asst.
Director; Robin McMillan, Utilities Dept.; Drew Goins, Asst. Com. of P. W. -
Engineering Division; Lena Bonner, Clerk of Commission and Nancy Morawski, Deputy
Clerk of Commission.
Also Present: Sylvia Cooper of The Augusta Chronicle, Stacey Eidson of The
Metropolitan Spirit, other members of the news media and Hons. Mays, H. Brigham and
Shepard Commissioners.
A request to approve option to purchase - Tax Map 20.3, Parcels 133 and
132 (powell), was read.
Mr. Bridges: I move for approval.
Mr. Colclough: Second.
Motion adopted unanimously.
I
A request to approve change order in the amount of $2,055.00 for additional
engineering work performed by James G. Swift & Associates on the Bedford
Heights Project, was read.
Mr. Bridges: I so move.
Mr. Handy: Second.
Motion adopted unanimously.
A request to award engineering services contract to ZEL Engineers for
design of the connection of new plant on Old Waynesboro Road to water system and
pumping rehabilitation at the Fort Gordon & Wrightsboro Road Booster Stations at
a cost of $46,000, was read.
After a short discussion, Mr. Bridges: I so move.
Mr. Colclough: Second.
Motion adopted unanimously.
I
ADJOURNMENT: There being no further business, the meeting was adjourned.
Lena J. Bonner
NWM Clerk of Commission
I
ENGINEERING SERVICES
AGENDA
COMMITTEE ROOM - July 12, 1999
3:00 P. M.
I. Approve option to purchase - Tax Map 20.3, Parcels 133 and 132 (powell).
2. Approve change order in the amount of$2,055.00 for additional engineering work
performed by James G. Swift & Associates on the Bedford Heights project.
3. Award of engineering services contract}o ZEL Engineers for desig~ of the
connection of new plant on Old Wayne~boro Road to Watersystem and Pumping
Rehabilitation at the Fort Gordon & Wrightsboro Road Booster Stations at a cost
of $46,000.
I
I